Table 3 to Subpart ZZZZZ of Part 63 - Applicability of General Provisions to New and Existing Affected Sources Classified as Large Foundries  


Latest version.
  • Table 3 to Subpart ZZZZZ of Part 63 - Applicability of General Provisions to New and Existing Affected Sources Classified as Large Foundries

    As required in § 63.10900(a), you must meet each requirement in the following table that applies to you:

    Citation Subject Applies to large
    foundry?
    Explanation
    63.1 Applicability Yes
    63.2 Definitions Yes
    63.3 Units and abbreviations Yes
    63.4 Prohibited activities Yes
    63.5 Construction/reconstruction Yes
    63.6(a) through (d) Compliance applicability and dates Yes
    63.6(e) Operating and maintenance requirements No This subpart specifies operating and maintenance requirements.
    63.6(f)(1) Applicability of non-opacity emission standards No This subpart specifies applicability of non-opacity emission standards.
    63.6(f)(2) through (3) Methods and finding of compliance with non-opacity emission standards Yes
    63.6(g) Use of an alternative nonopacity emission standard Yes
    63.6(h)(1) Applicability of opacity and visible emissions standards No This subpart specifies applicability of opacity and visible emission standards.
    63.6(h)(2) through (9) Methods and other requirements for opacity and visible emissions standards Yes
    63.6(i) through (j) Compliance extension and Presidential compliance exemption Yes
    63.7(a)(1) through (2) Applicability and performance test dates No This subpart specifies applicability and performance test dates.
    63.7(a)(3) through (4) Administrators rights to require a performance test and force majeure provisions Yes
    63.7(b) through (d) Notification of performance test, quality assurance program, and testing facilities Yes
    63.7(e)(1) Performance test conditions No This subpart specifies performance test conditions.
    63.7(e)(2) through (4), (f) through (h) Other performance testing requirements Yes
    63.8(a)(1) through (3), (b), (c)(1)(ii), (c)(2) through (3), (c)(6) through (8), (d)(1) through (2) Monitoring requirements Yes
    63.8(a)(4) Additional monitoring requirements for control devices in § 63.11 No
    63.8(c)(1)(i), (c)(1)(iii) Operation and maintenance of continuous monitoring systems No Not necessary in light of other requirements of § 63.8 that apply.
    63.8(c)(4) Continuous monitoring system (CMS) requirements No
    63.8(c)(5) Continuous opacity monitoring system (COMS) minimum procedures No
    63.8(d)(3) Quality control program No This subpart specifies records that must be kept associated with site-specific performance evaluation test plan.
    63.8(e), (f)(1) through (6), (g)(1) through (4) Performance evaluations and alternative monitoring Yes
    63.8(g)(5) Data reduction No
    63.9 Notification requirements Yes. Except for opacity performance tests.
    63.10(a), (b)(1), (b)(2)(xii) through (xiv), (b)(3), (d)(1) through (4), (e)(1) through (2), (f) Recordkeeping and reporting requirements Yes
    63.10(b)(2)(i) through (xi) Malfunction and CMS records No
    63.10(c) Additional records for CMS No This subpart specifies records requirements.
    63.10(d)(5) Periodic startup, shutdown, and malfunction reports No
    63.10(e)(3) Excess emissions reports No This subpart specifies reporting requirements.
    63.10(e)(4) Reporting COMS data No
    63.11 Control device requirements No
    63.12 State authority and delegations Yes
    63.13(a) Reporting to EPA regional offices Yes Except: reports and notifications required to be submitted to CEDRI meet this obligation through electronic reporting.
    63.13(b) through 63.16 Addresses of state air pollution control agencies. Incorporation by reference. Availability of information and confidentiality. Performance track provisions Yes

    [85 FR 56105, Sept. 10, 2020]