§ 35.930-5 - Federal share.  


Latest version.
  • (a) General. The grant shall be 75 percent of the estimated total cost of construction that the Regional Administrator approves in the grant agreement, except as otherwise provided in paragraphs (b) and (c) of this section and in §§35.925-15, 35.925-16, 35.925-17, 35.930-1(b), and paragraph 10 of appendix A.

    (b) Innovative and alternative technology. In accordance with §35.908(b), the amount of any step 2, step 3, or step 2=3 grant assistance awarded from funds allotted for fiscal years 1979, 1980, and 1981 shall be 85 percent of the estimated cost of construction for those eligible treatment works or significant portions of them that the Regional Administrator determines meet the criteria for innovative or alternative technology in appendix E. These grants depend on the availability of funds from the reserve under §35.915-1(b). The proportional State contribution to the non-Federal share of construction costs for 85-percent grants must be the same as or greater than the proportional State contribution (if any) to the non-Federal share of eligible construction costs for all treatment works which receive 75-percent grants in the State.

    (c) Modification and replacement of innovative and alternative projects. In accordance with §35.908(c) and procedures published by EPA, the Regional Administrator may award grant assistance to fund 100 percent of the eligible costs of the modification or replacement of any treatment works constructed with grant assistance based upon a Federal share of 85 percent under paragraph (b) of this section.