§ 35.930-6 - Limitation on Federal share.  


Latest version.
  • The grantee must exert its best efforts to perform the project work as specified in the grant agreement within the approved cost ceiling. If at any time the grantee believes that the costs which it expects to incur in the performance of the project will exceed or be substantially less than the previously approved estimated total project costs, the grantee must notify the Regional Administrator and the State agency promptly in writing. As soon as practicable, the grantee must give the revised estimate of total cost for the performance of the project (see §30.900 of this subchapter). Delay in submission of the notice and excess cost information may prejudice approval of an increase in the grant amount. The United States shall not be obligated to pay for costs incurred in excess of the approved grant amount or any amendment to it until the State has approved an increase in the grant amount from available allotments under §35.915 and the Regional Administrator has issued a written grant amendment under §35.955.