Subpart UUUUb - Emission Guidelines for Greenhouse Gas Emissions for Electric Utility Generating Units  


Definitions
§ 60.5880b - What definitions apply to this subpart?
Applicability of State Plans to Affected EGUs
§ 60.5840b - Does this subpart directly affect EGU owners or operators in my State?
§ 60.5850b - What EGUs are excluded from being affected EGUs?
§ 60.5845b - What affected EGUs must I address in my State plan?
Introduction
§ 60.5700b - What is the purpose of this subpart?
§ 60.5710b - Am I affected by this subpart?
§ 60.5720b - What if I do not submit a State plan or my State plan is not approvable?
§ 60.5730b - Is there an approval process for a negative declaration letter?
§ 60.5705b - Which pollutants are regulated by this subpart?
§ 60.5715b - What is the review and approval process for my State plan?
§ 60.5725b - In lieu of a State plan submittal, are there other acceptable option(s) for a State to meet its CAA section 111(d) obligations?
State Plan Requirements
§ 60.5740b - What must I include in my federally enforceable State plan?
§ 60.5780b - What compliance dates and compliance periods must I include in my State plan?
§ 60.5790b - What is the procedure for revising my State plan?
§ 60.5775b - What standards of performance must I include in my State plan?
§ 60.5785b - What are the timing requirements for submitting my State plan?
§ 60.5795b - Commitment to review emission guidelines for coal-fired affected EGUs
Recordkeeping and Reporting Requirements
§ 60.5860b - What applicable monitoring, recordkeeping, and reporting requirements do I need to include in my State plan for affected EGUs?
§ 60.5870b - What are my reporting and notification requirements?
§ 60.5865b - What are my recordkeeping requirements?
§ 60.5875b - How do I submit information required by these emission guidelines to the EPA?
§ 60.5876b - What are the recordkeeping and reporting requirements for EGUs that have committed to permanently cease operations by January 1, 2032?