§ 63.2160 - By what date must I conduct an initial compliance demonstration?  


Latest version.
  • § 63.2160 By what date must I conduct an initial compliance demonstration?

    (a) For each emission limitation in Table 1 to this subpart for which compliance is demonstrated by monitoring fermenter exhaustyou demonstrate compliance using the Average Option, you must demonstrate initial compliance for the period ending on the last day of the month that is 12 calendar months (or 11 calendar months, if the compliance date for your affected source is the first day of the month) after the compliance date that is specified for your affected source in § 63.2133.

    (

    For example, if the compliance date is October 15, 2003, the first 12-month period for which you must demonstrate compliance would be October 15, 2003 through October 31, 2004.)

    (b) For each emission limitation in Table 1 to this subpart for which initial compliance is demonstrated by monitoring brew ethanol concentration and calculating volatile organic compound (VOC) concentration in the fermenter exhaust according to the procedures in § 63.2161you demonstrate compliance using the Batch Option, you must demonstrate initial compliance within 180 calendar days before the for the period ending June 30 or December 31 (use whichever date is the first date following the compliance date that is specified for your affected source in § 63.2133).