§ 763.124 - Reporting.  


Latest version.
  • (a) Employers subject to this rule must report to the Regional Asbestos Coordinator for the EPA Region in which the asbestos abatement project is located at least 10 days before they begin any asbestos abatement project, except one that involves less than either 3 linear feet or 3 square feet of friable asbestos material, and an emergency project. Employers must report any emergency project covered by this rule as soon as possible but in no case more than 48 hours after the project begins. A list of the EPA Regional Offices is given under § 1.7(b) of this chapter.

    (b) The report must include:

    (1) The employer's name and address.

    (2) The location, including street address, of the asbestos abatement project.

    (3) The scheduled starting and completion dates for the asbestos abatement project.

    (c) If a report is mailed to EPA, the report must be postmarked at least 10 days before the asbestos abatement project begins unless the report is for an emergency project. In such a case, the report must be postmarked as soon as possible but in no case more than 48 hours after the project begins.

    (d) Employers do not have to report under this section if they submit a notice to EPA under the National Emission Standard for Asbestos, § 61.146 of this chapter, at least 10 days before they begin the asbestos abatement project and that notice clearly indicates that employees covered by this rule will perform some or all of the asbestos abatement work.