§ 2803.2 - Holder activity.
-
(a) If a notice to proceed requirement has been included in the grant or permit, the holder shall not initiate construction, occupancy or use until the authorized officer issues a notice to proceed.
(b) Any substantial deviation in location or authorized use by the holder during construction, operation or maintenance shall be made only with prior approval of the authorized officer under § 2803.6-1 of this title for the purposes of this paragraph, substantial deviation means:
(1) With respect to location, the holder has constructed the authorized facility outside the prescribed boundaries of the right-of-way authorized by the instant grant or permit.
(2) With respect to use, the holder has changed or modified the authorized use by adding equipment, overhead or underground lines, pipelines, structures or other facilities not authorized in the instant grant or permit.
(c) The holder shall notify the authorized officer of any change in status subsequent to the application or issuance of the right-of-way grant or temporary use permit. Such changes include, but are not limited to, legal mailing address, financial condition, business or corporate status. When requested by the authorized officer, the holder shall update and/or attest to the accuracy of any information previously submitted.
(d) If required by the terms of the right-of-way grant or temporary use permit, the holder shall, subsequent to construction and prior to commencing operations, submit to the authorized officer a certification of construction, verifying that the facility has been constructed and tested in accordance with terms of the right-of-way grant or temporary use permit, and in compliance with any required plans and specifications, and applicable Federal and State laws and regulations.