Code of Federal Regulations (Last Updated: November 8, 2024) |
Title 43 - Public Lands: Interior |
Subtitle B - Regulations Relating to Public Lands |
Chapter II - Bureau of Land Management, Department of the Interior |
SubChapter B - Land Resource Management (2000) |
Part 2880 - Rights-of-Way Under the Mineral Leasing Act |
Subpart 2885 - Terms and Conditions of MLA Grants and TUPs |
§ 2885.14 - What happens if I need a right-of-way wider than 50 feet plus the ground occupied by the pipeline and related facilities?
Latest version.
-
§ 2885.14 What happens if I need a right-of-way wider than 50 feet plus the ground occupied by the pipeline and related facilities?
(a) You may apply to BLM at any time for a right-of-way wider than 50 feet plus the ground occupied by the pipeline and related facilities. In your application you must show that the wider right-of-way is necessary to:
(1) Properly operate and maintain the pipeline after you have constructed it;
(2) Protect the environment; or
(3) Provide for public safety.
(b) BLM will notify you in writing of its finding(s) and its decision on your application for a wider right-of-way. If the decision is adverse to you, you may appeal it under § 2881.10 of this part.