§ 3173.22 - Requirements for off-lease measurement.
Latest version.
-
§ 3173.22 Requirements for off-lease measurement.
The BLM will consider granting a request for off-lease measurement if the request:
(a) Involves only production from a single lease, unit PA, CA, or CAA;
(b) Provides for accurate production accountability;
(c) Is in the public interest (considering factors such as BMPs, topographic and environmental conditions that make on-lease measurement physically impractical, and maximum ultimate economic recovery); and
(d) Occurs at an approved FMP. A request for approval of an FMP (see § 3173.12) may be filed concurrently with the request for off-lease measurement.