§ 3276.13 - What additional information must I give BLM in the monthly report for flash and dry steam facilities?  


Latest version.
  • § 3276.13 What additional information must I give BLM in the monthly report for flash and dry steam facilities?

    In addition to the regular monthly report information required by § 3276.12, send to BLM:

    (a) Steam flow into the turbine in klbs; for dual flash facilities, you must separate the steam flow into high pressure steam and low pressure steam;

    (b) Condenser pressure in psia;

    (c) Condenser temperature in deg. F;

    (d) Auxiliary steam flow used for gas ejectors, steam seals, pumps, etc., in klbs;

    (e) Flow of condensate out of the plant (after the cooling towers) in klbs; and

    (f) Any other information we may require.