  • (a) The Director approves applications meeting the requirements of this subpart on first-come, first-served basis, in the order in which it is determined by IMLS that such requirements (including all application requirements) have been met.

    (b) There are no selection criteria.

    (c) Section 1180.16 (IMLS share of the cost of a proposal) does not apply to grants under this subpart.

    (d) A museum receiving assistance under this subpart must submit a final financial and narrative report that evaluates the success of the assessment and actions taken by the museum as a result of the assessment. IMLS may request that the report be submitted up to 12 months after the close of the grant period.

    (e)(1) Except as provided in § 1180.71 and paragraph (e)(2) of this section subparts A, B, and C of part 1180 of title 45 CFR do not apply to the Museum Assessment Program.

    (2) The following sections do apply to the Museum Assessment Program: Sections 1180.5(a); 1180.5(c); 1180.5(d); 1180.5(e); 1180.15; 1180.44; 1180.47; and 1180.51-1180.57.