Appendix C to Part 404 - Procedures for Annual Review of Base Pilotage Rates  


Latest version.
  • The ratemaking methodology detailed in appendix A is used by the Director to determine base pilotage rates at least once every five years, as required by §404.1. In the intervening years the Director will review, if warranted by cost changes, recalculate base pilotage rates proposed for coordination with Canada using the following procedures:

    Step 1: Calculate the total economic costs for the base period (i.e. pilot compensation expense plus all other recognized expenses plus the return element) and divide by the total bridge hours used in setting the base period rates;

    Step 2: Calculate the “expense multiplier,” the ratio of other expenses and the return element to pilot compensation for the base period;

    Step 3: Calculate an annual “projection of target pilot compensation” using the same procedures found in Step 2 of appendix A;

    Step 4: Increase the projected pilot compensation in Step 3 by the expense multiplier in Step 2;

    Step 5: Adjust the result in Step 4, as required, for inflation or deflation;

    Step 6: Divide the result in Step 5 by projected bridge hours to determine total unit costs;

    Step 7: Divide prospective unit costs in Step 6 by the base period unit costs in Step 1;

    Step 8: Adjust the base period rates by the percentage change in unit costs in Step 7. For example if the total economic costs per bridge hour is $30.00 for the base period and $33.00 for the prospective rate period, then the rates established for the base period would be increased by 10% to determine the proposed rates for the prospective rate period, which would then be subject to negotiation with Canada.

    [60 FR 18370, Apr. 11, 1995. Redesignated and amended at 61 FR 32655, June 25, 1996, and further redesignated and amended by USCG-1998-3976, 63 FR 35139, 35140, June 29, 1998]