Code of Federal Regulations (Last Updated: October 10, 2024) |
Title 46 - Shipping |
Chapter I - Coast Guard, Department of Homeland Security |
SubChapter Q - Equipment, Construction, and Materials: Specifications and Approval |
Part 159 - Approval of Equipment and Materials |
Subpart 159.007 - Production Inspection and Tests of Approved Equipment and Materials |
§ 159.007-5 - Production inspections and tests: Application for acceptance.
Latest version.
-
§ 159.007-5 Production inspections and tests: Application for acceptance.
(a) If the applicable subpart requires production inspections and tests by an independent laboratory, the manufacturer must select a laboratory and submit an application for acceptance that meets § 159.010-5(a) unless the laboratory -
(1) Is listed in the subpart; or
(2) Is accepted by the Commandant for approval inspections and tests of the equipment or material under § 159.005-7(a)(1).
(b) If the manufacturer wants to follow the laboratory's procedures for production inspections and tests instead of meeting the Coast Guard procedures under this subchapter, the application must contain a description of those procedures.