§ 64.77 - Inspection and test.  


Latest version.
  • § 64.77 Inspection and test.

    For the handling and stowage requirements in § 98.30-3 of this chapter, each MPT must pass the following inspections and tests conducted by the owner or the owner's representative:

    (a) Pressure relief and vacuum relief devices must be inspected one time or more during each 12 month period of service in accordance with § 64.79.

    (b) An MPT must be inspected during the 30 months before any month in which it is in service in accordance with § 64.81.

    (c) An MPT must pass a hydrostatic test in accordance with § 64.83 during the 60 months before any month in which it is in service.

    (d) After each welded repair, an MPT must pass a hydrostatic test in accordance with § 64.83.