§ 90.755 - Procedures for license modification.  


Latest version.
  • (a) A Phase I non-nationwide licensee seeking modification of its authorization to relocate its authorized base station in accordance with the provisions of § 90.753 must file the following on or before May 1, 1996:

    (1) Form 600 requesting license modification, and providing all applicable information;

    (2) Certification that the location of its proposed base station is in conformance with the provisions of § 90.753, or, as provided in § 90.753(d), a letter evidencing consent of a co-channel licensee that the licensee may be authorized less than 120 km from the co-channel licensee;

    (3) If applicable, the required certification by a licensee with a Special Temporary Authority, in accordance with § 90.753(c);

    (4) If applicable, certification that the licensee has constructed its base station and placed it in operation, or commenced service, at its initially authorized location on or before March 11, 1996.

    (b) A licensee seeking modification of its authorization to relocate its base station in accordance with the provisions of § 90.753, should file, on or before March 11, 1996, either a modification application, as provided in paragraph (a) of this section, or a letter certifying to the Commission its intent to file an application to modify its authorization to relocate its base station. For a licensee that has not constructed its authorized base station and placed it in operation, or commenced service, by March 11, 1996, this filing will serve to extend the licensee's construction requirement in accordance with the provisions of § 90.757.