§ 1052.234-70 - Notice of Earned Value Management System—Pre-Award IBR (Core) AUG 2011  


Latest version.
  • Link to an amendment published at 80 FR 11597, Mar. 4, 2015.

    As prescribed in DTAR 1034.203, insert this provision in solicitations and awards that require the Contractor to use an earned value management system (EVMS) and for which the Government requires an IBR prior to award.

    (a) The offeror shall provide either documentation that the Cognizant Federal Agency has determined that the proposed earned value management system (EVMS) complies with the EVMS guidelines in ANSI/EIA Standard-748 (ANSI Standard) or documentation that supports its self-validation that the EVMS used for this award complies with Core EVM criteria.

    (b) If the offeror proposes to use a system that has not been determined to be in compliance with the requirements of paragraph (a) of this provision, the offeror shall submit a comprehensive plan for compliance with the EVMS guidelines.

    (1) The plan shall—

    (i) Describe the EVMS the offeror intends to use in performance of the contracts;

    (ii) Distinguish between the offeror's existing management system and modifications proposed to meet the guidelines;

    (iii) Describe the management system and its application in terms of the EVMS guidelines;

    (iv) Describe the proposed procedures for administration of the guidelines, as applied to subcontracts; and

    (v) Provide documentation describing the process and results of any third-party or self-evaluation of the system's compliance with the EVMS guidelines.

    (2) The offeror shall provide information and assistance as required by the contracting officer to support review of the plan.

    (3) The Government will review and approve the offeror's plan for an EVMS before contract award.

    (4) The offeror's EVMS plan must provide milestones that indicate when the offeror anticipates that the EVM system will be compliant with the requirements in paragraph (a) of this provision.

    (c) Offerors shall identify the major subcontractors, or major subcontracted effort if major subcontracts have not been selected subject to the guidelines. The prime Contractor and the Government shall agree to subcontractors selected for application of the EVMS requirements.

    (d) The Government will conduct an Integrated Baseline Review (IBR), as designed by the agency, prior to contract award. The objective of the IBR is for the Government and the Contractor to jointly assess technical areas, such as the Contractor's planning, to ensure complete coverage of the contract requirements, logical scheduling of the work activities, adequate resources, methodologies for earned value (budgeted cost for work performed (BCWP)), and identification of inherent risks.

    (End of provision)