§ 1252.216-72 - Award Fee Plan.  


Latest version.
  • 1252.216-72 Performance evaluation planAward Fee Plan.

    As prescribed in (TAR) 48 CFR 1216.406-70(b), insert the following clause:

    Performance Evaluation Award Fee Plan (OCT 1994NOV 2022)

    (a) A Performance Evaluation An Award Fee Plan shall be unilaterally established by the Government based on the criteria stated in the contract and used for the determination of award fee. This plan shall include the criteria used to evaluate each area and the percentage of award fee (, if any) , available for each area. A copy of the plan shall be provided to the contractor Contractor______ (insert number) calendar days prior to the start of the first evaluation period.

    (b) The criteria contained within the Performance Evaluation Award Fee Plan may relate to: (1) Technical (including schedule) requirements, if appropriate; (2) Management; and (3) Cost.

    (c) The Performance Evaluation Award Fee Plan may, consistent with the contract, be revised unilaterally by the Government at any time during the period of performance. Notification of such changes shall be provided to the contractor Contractor______ (insert number) calendar days prior to the start of the evaluation period to which the change will apply.

    (End of clause)