§ 1315.902 - Policy.


Latest version.
  • (a) Except as provided in (b) and (c) of this section, a structured approach for determining profit or fee prenegotiation objectives shall be used in the negotiation of all contracts, subcontracts, and contract modifications above $100,000 where adequate price competition does not exist. A structured approach for determining profit or fee prenegotiation objectives may be used at lower dollar thresholds.

    (b) Regardless of whether price competition exists, the structured approach for determining profit or fee prenegotiation objectives is not required for negotiation of contracts, subcontracts, and contract modifications for the following:

    (1) Architect—engineering contracts;

    (2) Management contracts for operation or maintenance of Government facilities;

    (3) Construction contracts;

    (4) Contracts primarily requiring delivery of material supplied by subcontractors;

    (5) Termination settlements;

    (6) Cost-plus-award-fee contracts; and

    (7) Unusual pricing situations where the structured approach has been determined to be unsuitable. This exception must be justified in writing and signed by the head of the contracting office.

    (c) In many circumstances, an examination of cost and profits is not required. Where adequate price competition exists and in other situations where cost analysis is not required (e.g., established catalog or market prices of commercial items sold in substantial quantities to the general public or prices set by law or regulation), contracts may be awarded without regard to the amount of profit involved.

    (d) Additional internal instruction on the use of the structured approach can be found in Procurement Letters or policy manuals issued by the Office of Procurement and Federal Assistance.