§ 1332.102 - Description of contract financing methods.  


Latest version.
  • (e)(2) Progress payments based on a percentage or stage of completion are authorized for use as a payment method under Department contracts and subcontracts for construction, alteration, repair, ship construction, ship alteration, and ship repair. For all other contracts, progress payments shall be based on costs except when the head of the contracting office determines that progress payments based on costs cannot be practically employed. In those cases, progress payments based on a percentage or stage of completion may be authorized when the head of the contracting office also determines that adequate safeguards are provided for the administration of those payments.