§ 1815.304-70 - NASA evaluation factors.  


Latest version.
  • (a) Typically, NASA establishes three evaluation factors: Mission Suitability, Cost/Price, and Past Performance. Evaluation factors may be further defined by subfactors. Evaluation subfactors should be structured to identify significant discriminators, or “key swingers”—the essential information required to support a source selection decision. Too many subfactors undermine effective proposal evaluation. All evaluation subfactors should be clearly defined to avoid overlap and redundancy.

    (b) Mission Suitability factor. (1) This factor indicates the merit or excellence of the work to be performed or product to be delivered. It includes, as appropriate, both technical and management subfactors. Mission Suitability shall be numerically weighted and scored on a 1000-point scale.

    (2) The Mission Suitability factor may identify evaluation subfactors to further define the content of the factor. Each Mission Suitability subfactor shall be weighted and scored. The adjectival rating percentages in 1815.305(a)(3)(A) shall be applied to the subfactor weight to determine the point score. The number of Mission Suitability subfactors is limited to five. The Mission Suitability evaluation subfactors and their weights shall be identified in the RFP.

    (3) For cost reimbursement acquisitions, the Mission Suitability evaluation shall also include the results of any cost realism analysis. The RFP shall notify offerors that the realism of proposed costs may significantly affect their Mission Suitability scores.

    (4) If the solicitation requires the submission of a Safety and Health Plan (see 1823.7001(c) and NPG 8715.3, NASA Safety Manual, Appendix H), safety and health must be a consideration in the evaluation. For acquisitions valued at $10 million or more, or $25 million or more for commercial items, then the Mission Suitability factor, if used, shall include a subfactor for safety and health. Otherwise, use of that subfactor is optional.

    (c) Cost/Price factor. This factor evaluates the reasonableness and, if necessary, the cost realism, of proposed costs/prices. The Cost/Price factor is not numerically weighted or scored.

    (d) Past Performance factor. (1) This factor indicates the relevant quantitative and qualitative aspects of each offeror's record of performing services or delivering products similar in size, content, and complexity to the requirements of the instant acquisition.

    (2) The RFP shall instruct offerors to submit data (including data from relevant Federal, State, and local governments and private contracts) that can be used to evaluate their past performance. Typically, the RFP will require:

    (i) A list of contracts similar in size, content, and complexity to the instant acquisition, showing each contract number, the type of contract, a brief description of the work, and a point of contact from the organization placing the contract. Normally, the requested contracts are limited to those received in the last three years. However, in acquisitions that require longer periods to demonstrate performance quality, such as hardware development, the time period should be tailored accordingly.

    (ii) The identification and explanation of any cost overruns or underruns, completion delays, performance problems, and terminations.

    (3) The contracting officer may start collecting past performance data before proposal receipt. One method for early evaluation of past performance is to request offerors to submit their past performance information in advance of the proposal due date. The RFP could also include a past performance questionnaire for offerors to send their previous customers with instructions to return the completed questionnaire to the Government. Failure of the offeror to submit its past performance information early or of the customers to submit the completed questionnaires shall not be a cause for rejection of the proposal nor shall it be reflected in the Government's evaluation of the offeror's past performance.

    (4) The contracting officer shall evaluate the offeror's past performance in occupational health, security, safety, and mission success (e.g., mishap rates and problems in delivered hardware and software that resulted in mishaps or failures) when these areas are germane to the requirement.