§ 1815.406-170 - Content of the prenegotiation position memorandum.  


Latest version.
  • The prenegotiation position memorandum (PPM) should fully explain the contractor and Government positions. Since the PPM will ultimately become the basis for negotiation, it should be structured to track to the price negotiation memorandum (see FAR 15.406-3 and 1815.406-3). In addition to the information described in FAR 15.406-1 and, as appropriate, 15.406-3(a), the PPM should address the following subjects, as applicable, in the order presented:

    (a) Introduction. Include a description of the acquisition and a history of prior acquisitions for the same or similar items. Address the extent of competition and its results. Identify the contractor and place of performance (if not evident from the description of the acquisition). Document compliance with law, regulations and policy, including JOFOC, synopsis, EEO compliance, and current status of contractor systems (see FAR 15.406-3(a)(4)). In addition, the negotiation schedule should be addressed and the Government negotiation team members identified by name and position.

    (b) Type of contract contemplated. Explain the type of contract contemplated and the reasons for its suitability.

    (c) Special features and requirements. In this area, discuss any special features (and related cost impact) of the acquisition, including such items as—

    (1) Letter contract or precontract costs authorized and incurred;

    (2) Results of preaward survey;

    (3) Contract option requirements;

    (4) Government property to be furnished;

    (5) Contractor/Government investment in facilities and equipment (and any modernization to be provided by the contractor/Government);

    (6) Any deviations, special clauses, or unusual conditions anticipated, for example, unusual financing, warranties, EPA clauses and when approvals were obtained, if required; and

    (7) Any risk management issues, e.g., mission success, safety, occupational health, information technology, export control, security, and environmental risks.

    (d) Cost analysis. For the basic requirement, and any option, include—

    (1) A parallel tabulation, by element of cost and profit/fee, of the contractor's proposal and the Government's negotiation objective. The negotiation objective represents the fair and reasonable price the Government is willing to pay for the supplies/services. For each element of cost, compare the contractor's proposal and the Government position, explain the differences and how the Government position was developed, including the estimating assumptions and projection techniques employed, and how the positions differ in approach. Include a discussion of excessive wages found (if applicable) and their planned resolution. Explain how historical costs, including costs incurred under a letter contract (if applicable), were used in developing the negotiation objective.

    (2) Significant differences between the field pricing report (including any audit reports) and the negotiation objectives and/or contractor's proposal shall be highlighted and explained. For each proposed subcontract meeting the requirement of FAR 15.404-3(c), there shall be a discussion of the price and, when appropriate, cost analyses performed by the contracting officer, including the negotiation objective for each such subcontract. The discussion of each major subcontract shall include the type of subcontract, the degree of competition achieved by the prime contractor, the price and, when appropriate, cost analyses performed on the subcontractor's proposal by the prime contractor, any unusual or special pricing or finance arrangements, and the current status of subcontract negotiations.

    (3) The rationale for the Government's profit/fee objectives and, if appropriate, a completed copy of the NASA Form 634, Structured Approach—Profit/Fee Objective, and DD Form 1861, Contract Facilities Capital Cost of Money, should be included. For incentive and award fee contracts, describe the planned arrangement in terms of share lines, ceilings, and cost risk.

    (e) Negotiation approval sought. The PPM represents the Government's realistic assessment of the fair and reasonable price for the supplies and services to be acquired. If negotiations subsequently demonstrate that a higher dollar amount (or significant term or condition) is reasonable, the contracting officer shall document the rationale for such a change and request approval to amend the PPM from the original approval authority.