§ 1816.404-274 - Award fee evaluation factors.  


Latest version.
  • (a) Evaluation factors will be developed by the contracting officer based upon the characteristics of an individual procurement. Normally, technical and schedule considerations will be included in all CPAF contracts as evaluation factors.

    (b) Cost control shall be included as an evaluation factor in all CPAF contracts. When explicit evaluation factor weightings are used, cost control shall be no less than 25 percent of the total fee, excluding any base fee. When explicit weightings are not used (which should only occur on service contracts), cost control shall be a substantial factor in the performance evaluation plan. The predominant consideration of the cost control evaluation should be an objective measurement of the contractor's performance against the negotiated estimated cost of the contract. This estimated cost may include the value of undefinitized change orders when appropriate.

    (c) In rare circumstances, contract costs may increase for reasons outside the contractor's control and for which the contractor is not entitled to an equitable adjustment. One example is a weather-related launch delay on a launch support contract. The Government shall take such situations into consideration when evaluating contractor cost control.

    (d) Emphasis on cost control should be balanced against other performance requirement objectives. The contractor should not be incentivized to pursue cost control to the point that overall performance is significantly degraded. For example, incentivizing an underrun that results in direct negative impacts on technical performance, safety, or other critical contract objectives is both undesirable and counterproductive. Evaluation of cost control shall conform to the following guidelines:

    (1) Normally, the contractor should be given a score of 0 for cost control when there is a significant overrun within its control. However, the contractor may receive higher scores for cost control if the overrun is insignificant. Scores should decrease sharply as the size of the overrun increases. In any evaluation of contractor overrun performance, the Government shall consider the reasons for the overrun and assess the extent and effectiveness of the contractor's efforts to control or mitigate the overrun.

    (2) The contractor should normally be rewarded for an underrun within its control, up to the maximum score allocated for cost control, provided the average numerical rating for all other award fee evaluation factors is 81 or greater. See 1816.404-275 for information on numerical scoring. An underrun shall be rewarded as if the contractor has met the estimated cost of the contract (see 1816.404-274(d)(3)) when the average numerical rating for all other factors is less than 81 but greater than 60.

    (3) The contractor should be rewarded for meeting the estimated cost of the contract, but not to the maximum score allocated for cost control, to the degree that the contractor has prudently managed costs while meeting contract requirements. No award shall be given in this circumstance unless the average numerical rating for all other award fee evaluation factors is 61 or greater.

    (e) Only the award fee performance evaluation factors set forth in the award fee plan shall be used to determine award fee scores. The Government may unilaterally modify the award fee performance evaluation factors and performance evaluation areas applicable to the evaluation period. The contracting officer shall notify the contractor in writing of any such changes prior to the start of the relevant evaluation period.