(a) The rationale for the use of the down-selection technique shall be thoroughly justified in the acquisition planning requirement. Because the initial phase solicitation will also lead to subsequent phase award(s), the decision to use a downselection strategy must be made prior to release of the initial solicitation. Accordingly, all phases must be addressed in the initial acquisition strategy planning and documented in the acquisition plan or ASM minutes.
(b) If there is no direct link between successful performance in the preceding phase and successful performance in a subsequent phase, down-selection is inappropriate. In this case, the phases should be contracted for separately without a down-selection.
(c) With one exception, both the initial and subsequent phase(s) of an acquisition down-selection process are considered to be full and open competition if the procedures in 1817.7301-4 and 1817.7301-5 (if using the progressive competition technique) are followed. If only one contractor successfully completed a given phase and no other offers are solicited for the subsequent phase, award of the subsequent phase may be made only if justified by one of the exceptions in FAR 6.302 or one of the exclusions in FAR 6.2, and only after compliance with the synopsis requirements of FAR 5.202 and 5.205 and 1804.570-2.