§ 1850.104-70 - Lead NASA installation.  


Latest version.
  • Link to an amendment published at 80 FR 36722, June 26, 2015.

    (a) Contractors applying for indemnification shall determine which NASA installation has the highest dollar amount of contracts for which indemnification is requested. The indemnification request should be submitted to the procurement officer for that installation, who will then designate a cognizant contracting officer. Contractors shall submit a single request and ensure duplicate requests are not submitted by associate divisions, subsidiaries, or central offices of the contractor.

    (b) The receiving installation will become the lead installation and will remain so indefinitely. Lead installation designation may change to another installation if the affected procurement officers agree to the change. Should a change occur in the lead installation, all records related to indemnification of that contractor shall be transferred to the gaining installation.