§ 230.7001-2 - Completion instructions.  


Latest version.
  • Complete a DD Form 1861 only after evaluating the contractor's cost proposal, establishing cost of money factors, and establishing a prenegotiation objective on cost. Complete the form as follows:

    (a) List overhead pools and direct-charging service centers (if used) in the same structure as they appear on the contractor's cost proposal and Form CASB-CMF. The structure and allocation base units-of-measure must be compatible on all three displays.

    (b) Extract appropriate contract overhead allocation base data, by year, from the evaluated cost breakdown or prenegotiation cost objective and list against each overhead pool and direct-charging service center.

    (c) Multiply each allocation base by its corresponding cost of money factor to get the facilities capital cost of money estimated to be incurred each year. The sum of these products represents the estimated contract facilities capital cost of money for the year's effort.

    (d) Total contract facilities cost of money is the sum of the yearly amounts.

    (e) Since the facilities capital cost of money factors reflect the applicable cost of money rate in Column 1 of Form CASB-CMF, divide the contract cost of money by that same rate to determine the contract facilities capital employed.