§ 236.270 - Expediting construction contracts.  


Latest version.
  • 236.270 Expediting construction contracts.

    (a) 10 U.S.C. 2858 requires agency head approval to expedite the completion date of a contract funded by a Military Construction Appropriations Act, if additional costs are involved. This approval authority may not be redelegated. The approval authority must -

    (1) Certify that the additional expenditures are necessary to protect the National interest; and

    (2) Establish a reasonable completion date for the project.

    (b) The contracting officer may approve an expedited completion date if no additional costs are involved.