Code of Federal Regulations (Last Updated: November 8, 2024) |
Title 48 - Federal Acquisition Regulations System |
Chapter 2 - Defense Acquisition Regulations System, Department of Defense |
SubChapter G - Contract Management |
Part 243 - Contract Modifications |
Subpart 243.2 - Change Orders |
§ 243.204-70-6 - Allowable profit.
-
243.204-70-6 Allowable profit.
When the final price of an unpriced change order is negotiated after a substantial portion of the required performance has been completed, the head of the contracting activity shall ensure the profit allowed reflects -
(a) Any reduced cost risk to the contractor for costs incurred during contract performance before negotiation of the final price;
(b) Any reduced cost risk to the contractor for costs expected to be incurred during performance of the remainder of the contract; and
(c) The extent to which costs have been incurred prior to definitization of the unpriced change order (see 215.404-71-3(d)(2)). The risk assessment shall be documented in the price negotiation memorandum .
[75 FR 48277, Aug. 10, 2010, as amended at 83 FR 30587, June 29, 2018]