§ 243.204-70-6 - Allowable profit.  


Latest version.
  • 243.204-70-6 Allowable profit.

    When the final price of an unpriced change order is negotiated after a substantial portion of the required performance has been completed, the head of the contracting activity shall ensure the profit allowed reflects -

    (a) Any reduced cost risk to the contractor for costs incurred during contract performance before negotiation of the final price;

    (b) Any reduced cost risk to the contractor for costs expected to be incurred during performance of the remainder of the contract; and

    (c) The extent to which costs have been incurred prior to definitization of the unpriced change order (see 215.404-71-3(d)(2)). The risk assessment shall be documented in the price negotiation memorandum .

    [75 FR 48277, Aug. 10, 2010, as amended at 83 FR 30587, June 29, 2018]