§ 245.302-1 - Policy.  


Latest version.
  • (a)(4)(A) Comply with DoD Directive 4275.5, Acquisition and Management of Industrial Resources, in processing a request for facilities. Submit requests for approval of facilities projects—

    (1) To the Secretaries of the Military Departments and the directors of defense agencies for Government-owned facilities projects if the project—

    (i) Is a research and development-funded effort not exceeding $3 million per fiscal year; or

    (ii) Is funded from procurement appropriations, approved on a location basis, and does not exceed $5 million for all property efforts during one fiscal year; or

    (iii) Is in support of a major system or subsystem (including ammunition-related projects) and the total investment will not exceed $25 million during the projected acquisition or maintenance effort.

    (2) To the Office of the Deputy Under Secretary of Defense (Industrial Affairs and Installations) for projects exceeding the limitations in paragraph (a)(4)(A)(1) of this subsection.

    (B) The contracting officer shall coordinate the Determination and Finding with the program or project manager.

    (C) Departments and agencies must submit reports of facilities projects to the House and Senate Armed Services Committees—

    (1) At least 30 days before starting facilities projects involving real property (10 U.S.C. 2662); and

    (2) In advance of starting construction for a facilities project regardless of cost. Use DD Form 1391, FY __, Military Construction Project Data, to notify congressional committees of projects that are not included in the annual budget.

    (b)(1)(A) Industrial plant equipment. Before acquiring industrial plant equipment—

    (1) Submit a DD Form 1419, DoD Industrial Plant Equipment Requisition, to the Defense Supply Center, Richmond (DSCR), Attn: DSCR-JH, 8000 Jefferson Davis Highway, Richmond, Va 23297-5100, in accordance with AR 700-43/NAVSUP PUB 5009/AFM 78-9/DLAM 4215.1, Management of Defense-Owned Industrial Plant Equipment, to determine whether existing, reallocable Government-owned facilities can be used.

    (2) Do not acquire any item listed on the DD Form 1419 until a certificate of nonavailability is received from DSCR.

    (B) Automatic data processing equipment. The administrative contracting officer submits contractor requests to acquire automatic data processing equipment to the Defense Information Systems Agency, Chief Information Officer, Defense Automation Resources Management Program Division, Attn: D03D, 701 South Courthouse Road, Arlington, VA 22204-2199, in accordance with the Defense Automation Resources Management Manual.