§ 2831.205-3270 - Precontract costs.


Latest version.
  • (a) Precontract cost authorizations shall be used only on cost reimbursement contracts, contain no provisions for payment of fees, and be treated as advance agreements in accordance with the provisions of FAR 31.109 and 2831.109-70 of this chapter.

    (b) The following limitations apply to the execution of precontract cost authorizations.

    (1) Contracts which are estimated to be $100,000 or less may contain a precontract cost authorization providing the authorization is for a period of 30 days or less and the dollar amount does not exceed one third of the total estimated costs (including fee if any) of the contract.

    (2) Contracts which are estimated to be greater than $100,000 may contain a precontract cost authorization providing the authorization is for a period of 60 days or less and the dollar amount does not exceed the lesser of $100,000 or one third of the total estimated costs (including fee if any) of the contract.

    (3) The limitations expressed under paragraphs (b) (1) and (2) of this section may be increased in unusual circumstances as appropriate, with the written approval of the head of the contracting authority, but in no event shall they exceed one-third of the total estimated costs (including fee if any) of the contract or be for periods of time which exceed 90 days.