§ 2932.102 - Description of contract financing methods.


Latest version.
  • (a) Progress payments based on a percentage or stage of completion accomplished are authorized for use in contracts for construction, alteration, or repair.

    (b) The Head of the Contracting Activity, or designee, is authorized to approve the use of progress payments based on percentage or stage of completion accomplished for contracts other than those listed in paragraph (a) of this section.

    (c) Requests for approval under paragraph (b) of this section, shall be in the form of a written determination by the contracting officer that:

    (1) Use of progress payments based on costs (see FAR subpart 32.5) is impracticable; and

    (2) Adequate measures exist for determining percentage or stage of completion as a basis for determining payment.