§ 30.602-2 - Noncompliance with CAS requirements.  


Latest version.
  • (a) Determination of noncompliance. (1) Within 15 days of the receipt of a report of alleged noncompliance from the cognizant auditor, the ACO shall make an initial finding of compliance or noncompliance and advise the auditor.

    (2) If an initial finding of noncompliance is made, the ACO shall immediately notify the contractor in writing of the exact nature of the noncompliance and allow the contractor 60 days within which to agree or to submit reasons why the existing practices are considered to be in compliance.

    (3) If the contractor agrees with the initial finding of noncompliance, the ACO shall review the contractor submissions required by paragraph (a) of the clause at FAR 52.230-6, Administration of Cost Accounting Standards.

    (4) If the contractor disagrees with the initial noncompliance finding, the ACO shall review the reasons why the contractor considers the existing practices to be in compliance and make a determination of compliance or noncompliance. If the ACO determines that the contractor's practices are in noncompliance, a written explanation shall be provided as to why the ACO disagrees with the contractor's rationale. The ACO shall notify the contractor and the auditor in writing of the determination. If the ACO makes a determination of noncompliance, the procedures in (b) through (d), as appropriate, shall be followed.

    (b) Accounting changes. (1) The clause at FAR 52.230-6, Administration of Cost Accounting Standards, requires the contractor to submit a description of any cost accounting practice change needed to correct a noncompliance.

    (2) The ACO shall review the proposed change concurrently for adequacy and compliance (see 30.202-7). If the description of the change meets both tests, the ACO shall notify the contractor and request submission of a cost impact proposal in accordance with FAR 30.602.

    (c) Contract price adjustments. (1) The ACO shall request that the contractor submit a cost impact proposal within the time specified in the clause at FAR 52.230-6, Administration of Cost Accounting Standards.

    (2) Upon receipt of the cost impact proposal, the ACO shall then follow the procedures in 30.602-1(c)(1). In accordance with the clause at 52.230-2, Cost Accounting Standards, or FAR 52.230-5, Cost Accounting Standards—Educational Institution, the ACO shall include and separately identify, as part of the computation of the contract price adjustment(s), applicable interest on any increased costs paid to the contractor as a result of the noncompliance. Interest shall be computed from the date of overpayment to the time the adjustment is effected. If the costs were incurred and paid evenly over the fiscal years during which the noncompliance occurred, then the midpoint of the period in which the noncompliance began may be considered the baseline for the computation of interest. An alternate equitable method should be used if the costs were not incurred and paid evenly over the fiscal years during which the noncompliance occurred. Interest under 52.230-2 should be computed pursuant to Public Law 100-679.

    (d) Remedies for contractor failure to make required submissions. (1) If the contractor does not submit the accounting change description or the general dollar magnitude of the change or cost impact proposal (in the form and manner specified), the ACO, with the assistance of the cognizant auditor, shall estimate the general dollar magnitude of the cost impact on CAS-covered contracts and subcontracts. The ACO may then withhold an amount not to exceed 10 percent of each subsequent amount determined payable related to the contractor's CAS-covered prime contracts, up to the estimated general dollar magnitude of the cost impact until the required submission is furnished by the contractor.

    (2) If the contractor has not submitted the cost impact proposal before the total withheld amount reaches the estimated general dollar magnitude and the ACO determines that an adjustment is required (see 30.602), the ACO shall notify the contractor and request agreement as to the cost or price adjustment together with any applicable interest as computed in accordance with 30.602-2(c)(2). The contractor shall also be advised that in the event no agreement on the cost or price adjustment is reached within 20 days, the ACO may make a unilateral adjustment, subject to contractor appeal, as provided in the clause at 52.233-1, Disputes.

    (3) If the ACO determines that there is no material increase in costs as a result of the noncompliance, the ACO shall notify the contractor in writing that the contractor is in noncompliance, that corrective action should be taken, and that if such noncompliance subsequently results in materially increased costs to the Government, the provisions of the clause at 52.230-2, Cost Accounting Standards, 52.230-5, Cost Accounting Standards—Educational Institution, and/or the clause at 52.230-3, Disclosure and Consistency of Cost Accounting Practices, will be enforced.