§ 315.608-73 - Receipt of proposals.  


Latest version.
  • (a) After the closing date set by the solicitation for the receipt of proposals, the contracting officer will use a transmittal memorandum to forward the technical proposals to the project officer or chairperson for evaluation. The business proposals will be retained by the contracting officer for evaluation (see 315.608-77).

    (b) The transmittal memorandum to the chairperson shall include at least the following:

    (1) A list of the names of the organizations submitting proposals;

    (2) A reference to 315.604(d) on the need to preserve the integrity of the source selection process;

    (3) A requirement for a technical evaluation report in accordance with 315.608-76; and

    (4) The establishment of a date for receipt of the technical evaluation report.