§ 315.7006 - Review.


Latest version.
  • Upon receipt of the RFC, the contracting activity shall review the contents to ensure that all pertinent information has been provided by the program office. If pertinent information is missing or if there are discrepancies in previously agreed upon information, such as significant alterations in the statement of work, the contracting activity shall obtain or clarify the information so that the acquisition schedule is met. If the program office delays furnishing the information or clarification, the acquisition schedule may have to be changed. When this circumstance arises, the contracting activity should notify the head of the sponsoring program office of the problem, in writing, of the possible slippage in the acquisition schedule, and the need for an expeditious remedy. If the head of the sponsoring program office is not responsive to the request for expediency, the matter should be referred to higher management authorities for resolution.