§ 315.805-5 - Field pricing support.


Latest version.
  • (2) When some or all information sufficient to determine the reasonableness of the proposed cost or price is already available or can be obtained by phone from the cognizant audit agency, contracting officers may request less-than-complete field pricing support (specifying in the request the information needed) or may waive in writing the requirement for audit and field pricing support by documenting the file to indicate what information is to be used instead of the audit report and the field pricing report.

    (c)(1) When initiating audit and field pricing support, the contracting officer shall do so by sending a request to the cognizant administrative contracting officer (ACO), with an information copy to the cognizant audit office. When field pricing support is not available, the contracting officer shall initiate an audit by sending, in accordance with agency procedures, two (2) copies of the request to the OIG Office of Audits’ Regional Audit Director. In both cases, the contracting officer shall, in the request:

    (i) Prescribe the extent of the support needed;

    (ii) State the specific areas for which input is required;

    (iii) Include the information necessary to perform the review (such as the offeror's proposal and the applicable portions of the solicitations, particularly those describing requirements and delivery schedules);

    (iv) Provide the complete address of the location of the offeror's financial records that support the proposal;

    (v) Identify the office having audit responsibility if other than an HHS Regional Audit Office; and

    (vi) Specify a due date for receipt of a verbal report to be followed by a written audit report. (If the time available is not adequate to permit satisfactory coverage of the proposal, the auditor shall so advise the contracting officer and indicate the additional time needed.) Normally, the Office of Audits will need 30 days after receipt of the proposal for submission of oral results. However, the Office of Audits’ ability to conduct reviews by the due date will be influenced by the OPDIV's ability to properly plan its acquisitions. If the Office of Audits requires additional time to conduct the review, the contracting officer has the option, at the time the auditor acknowledges receipt of the request, to accept the revised due date or cancel the request and use cost advisory services within the agency to satisfy the requirement. In such cases, the contracting officer shall immediately advise the OIG/OA/Regional Audit Director and the OIG/OA/Division of Audit Coordination (OIG/OA/DAC) of the revised due date or cancellation of the request.

    (4) One copy of the audit request letter that was submitted to the Regional Audit Director and a complete copy of the contract price proposal shall be submitted to OIG/OA/DAC.

    (5) Whenever, an audit review has been conducted by the Office of Audits, two (2) copies of the memorandum of negotiation shall be forwarded to OIG/OA/DAC by the contracting officer (see FAR 15.808(b)).