§ 32.502-2 - Contract finance office clearance.  


Latest version.
  • 32.502-2 Contract finance office clearance.

    The contracting officer shall obtain the approval of the contract finance office or other offices designated under agency procedures before taking any of the following actions:

    (a) Providing a progress payment rate higher than the customary rate (see 32.501-1).

    (b) Deviating from the progress payments terms prescribed in this part.

    (c) Providing progress payments to a contractor -

    (1) Whose financial condition is in doubt;

    (2) Who has had an advance payment request or loan guarantee denied for financial reasons (or approved but withdrawn or lapsed) within the previous 12 months; or

    (3) Who is named in the consolidated list of contractors indebted to the United States (known commonly as the Hold-up List).