§ 342.7103-2 - Procedures.


Latest version.
  • (a) Upon notification that a cost overrun is anticipated, the contracting officer shall inform the contractor to submit a request for additional funds which is to include:

    (1) Name and address of contractor.

    (2) Contract number and expiration date.

    (3) Contract item(s) and amount(s) creating the overrun.

    (4) The elements of cost which changed from the original estimate (i.e., labor, material, travel, overhead, etc.) to be furnished in the following format:

    (i) Original estimate,

    (ii) Costs incurred to date,

    (iii) Estimated cost to completion,

    (iv) Revised estimate, and

    (v) Amount of adjustment.

    (5) The factors responsible for the increase, i.e., error in estimate, changed conditions, etc.

    (6) The latest date by which funds must be available for commitment to avoid contract slippage, work stoppage, or other program impairment.

    (b) When the contractor submits a notice of an impending overrun, the contracting officer shall:

    (1) Immediately advise the appropriate program office and furnish a copy of the notice and any other data received;

    (2) Request audit or cost advisory services, and technical support, as necessary, for evaluation of information and data received; and

    (3) Maintain continuous follow-up with the program office in order to obtain a timely decision as to whether the work under the contract should be continued and additional funds provided, or the contract terminated. The decision of the program office must be supported by an appropriate written statement and funding authority, or a formal request for termination, when applicable. After a programming and funding decision is received from the program office, the contracting officer shall promptly notify the contractor in writing that:

    (i) A specified amount of additional funds has been allotted to the contract by a contractual instrument; or

    (ii) Work will be discontinued when the funds allotted to the contract have been exhausted, and that any work performed after that date is at the contractor's risk; or

    (iii) The Government is considering whether additional funds should be allotted to the contract and will notify the contractor as soon as possible, but that any work performed after the funds then allocated to the contract have been exhausted is at the contractor's risk.

    Timely, formal notification of the Government's intention is essential in order to preclude loss of contractual rights in the event of dispute, termination, or litigation.

    (c) If program requirements permit, contracting officers should refrain from issuing any contractual documents which will require new work or an extension of time, pending resolution of an overrun or additional fund request.