    (a) Except as provided in paragraph (b) below of this section, a contract is considered to be physically completed when -

    (1)

    (i) The contractor has completed the required deliveries and the Government has inspected and accepted the supplies;

    (ii) The contractor has performed all services and the Government has accepted these services; and

    (iii) All option provisions, if any, have expired; or

    (2) The Government has given the contractor a notice of complete contract termination.

    (b) Rental, use, and storage agreements are considered to be physically completed when -

    (1) The Government has given the contractor a notice of complete contract termination; or

    (2) The contract period has expired.

    [48 FR 42113, Sept. 19, 1983, as amended at 72 FR 27383, May 15, 2007; 84 FR 19841, May 6, 2019]