§ 436.604 - Performance evaluation.  


Latest version.
  • 436.604 Performance evaluation.

    Preparation of performance evaluation reports.

    (a) In addition to the requirements of FAR 36.604, performance evaluation reports shall be prepared for indefinite-delivery type contracts when either the contract maximum or the contracting activities reasonable estimate of services to be ordered exceeds $25,000.00. For these contracts, performance evaluation reports shall be prepared for each order at the time of final acceptance of the work under the order.

    (b) The contracting officer may require a performance evaluation report on the work done by the architect-engineer after the completion of or during the construction of the designed project.