§ 511.503 - Contract clauses.
Latest version.
- Link to an amendment published at
511.503 XXX
Cross Reference
Contract clauses.
(a) Insert the clause at 552.211-12, Liquidated Damages-Construction, in solicitations and contracts for construction, other than cost-plus-fixed-fee, when the contracting officer determines that liquidated damages are appropriate (see FAR 11.501(a)).
(b) Insert the clause at 552.211-13, Time Extensions, in solicitations and contracts for construction that includes the clause at 552.211-12.
[86 FR 55518, Oct. 6, 2021
.]