§ 536.303-70 - Bids that include alternates.  


Latest version.
  • (a) The base bid must include all features that are essential to a sound and adequate building design. However, if it appears that funds available for a project may be insufficient to include all desired features in the base bid, the contracting officer may issue a solicitation for a base bid and include one or more alternates in the order of priority. Alternates may be used only when they are clearly justified and should involve substantial amounts of work in relation to the base bid. Their use must be limited and should involve only “add” alternates.

    (b) The language used in soliciting alternates must be approved in writing by counsel.

    (c) Before opening bids that include alternates, the contracting officer shall determine and record in the contract file the amount of funds available for the project. The amount recorded must be announced at the beginning of the bid opening and must be the controlling factor in determining the low bidder. This amount may be increased later when determining the alternate items to be awarded to the low bidder, provided that the award amount of the base bid plus the combination of alternate items do not exceed the amount offered by any other responsible bidder whose bid conforms to the solicitation for the base bid and the same combination of alternate items.