  • (a) For Central Office contracts, the Chief Facilities Management Officer, Office of Facilities Management, after analyzing all bids received, will submit a memorandum to the Secretary (00) recommending award or other disposition of the project. A copy of each of the following will accompany the memorandum:

    (1) The invitation.

    (2) Each bid received.

    (3) The abstract.

    (4) Any other pertinent data.

    (b) On facility level contracts, the Chief, Engineering Service, will analyze all bids received and submit to the contracting officer a memorandum recommending award or other disposition of the project. However, the final decision to accept or reject the lowest responsive bid and the determination as to the responsibility of a prospective contractor shall be made by the contracting officer alone.