§ 852.211-74 - Liquidated damages.  


Latest version.
  • 852.211-74 Liquidated damages.

    As prescribed in 811.503 and 836.206, the contracting officer may insert the following clause when appropriate:

    Liquidated Damages (JAN 2008)

    If any unit of the work contracted for is accepted in advance of the whole, the rate of liquidated damages assessed will be in the ratio that the value of the unaccepted work bears to the total amount of the contract. If a separate price for unaccepted work has not been stated in the contractor's bid, determination of the value thereof will be made from schedules of costs furnished by the contractor and approved by the contracting officer, as specified elsewhere in the contract.

    (End of clause)