Code of Federal Regulations (Last Updated: July 5, 2024) |
![]() |
Title 48 - Federal Acquisition Regulations System |
![]() |
Chapter 9 - Department of Energy |
![]() |
SubChapter B - Competition Acquisition Planning |
![]() |
Part 907 - [Reserved] |
![]() |
Subpart 907.3 - Contractor Versus Government Performance |
§ 907.307 - Appeals.
Latest version.
-
An appeal of a decision to convert to contract or to continue in-house performance may be made by an affected party. Appeals shall be made in writing, be based only on specific alleged material deviation (or deviations),from OMB Circular A-76, and be supported by appropriate documentation. Appeals must be delivered within 15 working days of the announced decision, to the contracting officer. The contracting officer shall process any such appeal in accordance with internal Departmental procedures.