§ 915.972 - Special considerations for cost-plus-award-fee contracts.  


Latest version.
  • (a) When a contract is to be awarded on a cost-plus-award-fee basis in accordance with 916.404-2, several special considerations are appropriate. Fee objectives for management and operating contracts, including those using the Construction or Construction Management fee schedules from section 915.971-5, shall be developed pursuant to the procedures set forth in section 970.1509-8. Fee objectives for other cost-plus-award-fee contracts shall be developed as follows:

    (1) The base fee portion of the fee objective of an award fee contract may range from 0% up to the 50% level of the fee amount for a Cost-Plus-Fixed-Fee (CPFF) contract, arrived at by using the weighted guidelines or other techniques (such as those provided in 915.971 for construction and construction management contracts). However, the base amount should not normally exceed 50% of the otherwise applicable fixed fee. In the event this 50% limit is exceeded, appropriate documentation shall be entered into the contract file. In no event shall the base fee exceed 60% of the fixed fee amount.

    (2) The base fee plus the amount included in the award fee pool should normally not exceed the fixed fee (as subjectively determined or as developed from the fee schedule) by more than 50%. However, in the event the base fee is to be less than 50% of the fixed fee, the maximum potential award fee may be increased proportionately with the decreases in base fee amounts.

    (3) The following maximum potential award fees shall apply in award fee contracts: (percent is stated as percent of fee schedule amounts).

    Base fee percentAward fee percentMaximum total percentage50100150401201603014017020160180101801900200200

    (b) Prior approval of the Procurement Executive, is required for total fee (base plus award fee pool) exceeding the guidelines in 915.972(a)(3). Additionally, in the event use of the award fee guidelines exceeds the statutory limitations discussed in FAR 15.903(d)(1) (i), (ii) and (iii), prior approval of the Procurement Executive shall also be required.