§ 952.211-73 - Cost and schedule control systems criteria.  


Latest version.
  • Certain DOE projects are of such significance and magnitude that responsible management calls for enhanced visibility of contractor cost and schedule performance as well as more formalized data to document their progress and to aid in decisions regarding their continuation. Any contract with a total estimated cost in excess of $50 million shall require full implementation of the DOE Cost and Schedule Control Systems Criteria. Selected projects between $2 million and $50 million may benefit from modified implementation of such a control system. In those instances where the DOE Cost and Schedule Control System Criteria are to be utilized, the contracting officer shall provide for this by including the “Cost and Schedule Control Systems Criteria for Contract Performance Measurement—Implementation Guide,” in the solicitation and shall include the following clause in the contract.

    Cost and Schedule Control Systems (JUN 1996)