§ 970.15407-2-2 - Requirements.
-
(a)
Development of program-specific make-or-buy criteria. DOE program offices responsible for the work conducted at the facility or site shall develop program specific make-or-buy criteria. Program specific make-or-buy criteria are those factors that reflect specific mission or program objectives (including operational efficiency, contractor diversity, environment, safetyand health, work force displacement and restructuring, and collective bargaining agreements) and that, upon their application to a specific work effort, would override a decision based on a purely economic rationale. These criteria are to be used to assess each work effort identified in a facility's or site's make-or-buy plan to determine the appropriateness of a contractor's make-or-buy decisions. Program specific make-or-buy criteria shall be provided to the contractor for use in developing a make-or-buy plan for the facility, site, or specific program, as appropriate. (b)
Make-or-buy plan property and services. Supplies or services estimated to cost less than one (1) percent of the estimated total operating cost for a year or $1 million for the same year, whichever is less, need not be included in the contractor's make-or-buy plan. However, adjustments may be made to these thresholds where programmatic or cost considerations would indicate that a particular supply or service should be included in the make-or-buy plan.(c)
Competitive solicitation requirements. (1) To the extent practicable, a competitive solicitation for the management and operation of a Department of Energy facility or site should:(i) Identify those programs, projects, work areas, functions or services that the Department intends for the successful offeror to include in any make-or-buy plan; and
(ii) Require the submission of a preliminary make-or-buy plan for the period of performance of the contract from each offeror as part of its proposal submitted in response to the competitive solicitation.
(2) If the requirement for each offeror to submit a preliminary make-or-buy plan as part of its proposal is impractical or otherwise incompatible with the acquisition strategy, consideration should be given to structuring the evaluation criteria for the competitive solicitation in such a manner as to permit the evaluation of an offeror's approach to conducting its make-or-buy program within the context of the contractual requirements.
(3) The successful offeror's preliminary make-or-buy plan shall be submitted for final approval within 180 days after contract award, consistent with the requirements of 48 CFR 970.5204-76(c), Make-or-buy Plan.
(d)
Evaluation of the contractor's make-or-buy plan. In evaluating the contractor's make-or-buy plan, the contracting officer shall consider the following factors:(1) The program specific make-or-buy criteria (such as operational efficiency, contractor diversity, environment, safety and health, work force displacement and restructuring, and collective bargaining agreements) with particular attention to the effect of a “buy” decision on the contractor's ability to maintain core competencies needed to accomplish mission-related program and projects;
(2) The impact of a “make” or “buy” decision on contract cost, schedule, and performance and financial risk;
(3) The potential impact of a “make” or “buy” decision on known future mission or program activities at the facility or site;
(4) Past experience at the facility or site regarding “make-or-buy” decisions for the same, or similar, supplies or services;
(5) Consistency with the contractor's approved subcontracting plan, as required by the clause entitled “Small, Small Disadvantaged and Women-Owned Small Business Subcontracting Plan” (FAR 52.219-9), of the contract and implementation of Section 3021 of the Energy Policy Act of 1992.
(6) Local market conditions, including contractor work force displacement and the availability of firms that can meet the work requirements with regard to quality, quantity, cost, and timeliness;
(7) Where the construction of new or additional facilities is required, that the cost of such facilities is in the Government's best interest when compared to subcontracting or privatization alternatives; and
(8) Whether all relevant requirements and costs of performing the work by the contractor and through subcontracting are considered and any different requirements for the same work are reconciled.
(e)
Approval. The contracting officer shall approve all plans and revisionsthereto. Once approved, a make-or-buy plan shall remain effective for the term of the contract (up to a period of five years), unless circumstances warrant a change. (f)
Administration. The contractor's performance against the approved make-or-buy plan shall be monitored to ensure that:(1) The contractor is complying with the plan;
(2) Items identified for deferral decisions are addressed in a timely manner; and
(3) The contractor periodically updates the make-or-buy plan based on changed circumstances or significant new work.