Code of Federal Regulations (Last Updated: November 8, 2024) |
Title 48 - Federal Acquisition Regulations System |
Chapter 9 - Department of Energy |
SubChapter I - Agency Supplementary Regulations |
Part 970 - DOE Management and Operating Contracts |
Subpart 970.31 - Contract Cost Principles and Procedures |
§ 970.3102-13 - Precontract costs.
Latest version.
-
Precontract costs are those incurred prior to the effective date of the contract directly pursuant to the negotiation and in anticipation of the award of the contract, where such incurrence is necessary to comply with the proposed contract delivery schedule. Such costs are allowable to the extent that they would have been allowable if incurred after effective the date of the contract. They do not include costs of preparing bids or of participation in the negotiation. The allowability of precontract costs is dependent upon appropriate coverage in the contract.