Exhibit A to Subpart A of Part 1924 - Estimated Breakdown of Dwelling Costs for Estimating Partial Payments  


Latest version.
  • Exhibit A to Subpart A of Part 1924 - Estimated Breakdown of Dwelling Costs for Estimating Partial Payments

    [In percent]

    With slab on grade With crawl space With basement
    1. Excavation 3 5 6
    2. Footings, foundations columns 8 8 11
    3. Floor slab or framing 6 4 4
    4. Subflooring 0 1 1
    5. Wall framing, sheathing 7 7 6
    6. Roof and ceiling framing, sheathing 6 6 5
    7. Roofing 5 5 4
    8. Siding, exterior trim, porches 7 7 6
    9. Windows and exterior doors 9 9 8
    10. Plumbing - roughed in 3 2 3
    11. Sewage disposal 1 1 1
    12. Heating - roughed in 1 1 1
    13. Electrical - roughed in 2 2 2
    14. Insulation 2 2 2
    15. Dry wall or plaster 8 8 7
    16. Basement or porch floor, steps 1 1 6
    17. Heating - finished 3 3 3
    18. Flooring 6 6 5
    19. Interior carpentry, trim, doors 6 6 5
    20. Cabinets and counter tops 1 1 1
    21. Interior painting 4 4 3
    22. Exterior painting 1 1 1
    23. Plumbing - complete fixtures 4 4 3
    24. Electrical - complete fixtures 1 1 1
    25. Finish hardware 1 1 1
    26. Gutters and downspouts 1 1 1
    27. Grading, paving, landscaping 3 3 3
    Total 100 100 100