§ 1703.107 - Reporting and oversight requirements.  


Latest version.
  • § 1703.107 Reporting and oversight requirements.

    (a) A project performance activity report will be required of all recipients on an annual basis until the project is complete and the funds are expended by the applicant.

    (b) A final project performance report must be provided by the recipient. It must provide an evaluation of the success of the project in meeting the objectives of the program. The final report may serve as the last annual report.

    (c) RUS will monitor recipients, as it determines necessary, to assure that projects are completed in accordance with the approved scope of work and that the financial assistance is expended for approved purposes.

    (d) Recipients shall diligently monitor performance to ensure that time schedules are being met, projected work by time periods is being accomplished, and other performance objectives are being achieved. Recipients are to submit an original and one copy of all project performance reports, including, but not limited to, the following:

    (1) A comparison of actual accomplishments to the objectives established for that period;

    (2) A description of any problems, delays, or adverse conditions which have occurred, or are anticipated, and which may affect the attainment of overall project objectives, prevent the meeting of time schedules or objectives, or preclude the attainment of particular project work elements during established time periods. This disclosure shall be accompanied by a statement of the action taken or planned to resolve the situation; and

    (3) Objectives and timetable established for the next reporting period.