96-16257. Federal Operating Permits Program  

  • [Federal Register Volume 61, Number 127 (Monday, July 1, 1996)]
    [Rules and Regulations]
    [Pages 34202-34249]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-16257]
    
    
    
    [[Page 34201]]
    
    
    _______________________________________________________________________
    
    Part IV
    
    
    
    
    
    Environmental Protection Agency
    
    
    
    
    
    _______________________________________________________________________
    
    
    
    40 CFR Parts 9, 55 and 71
    
    
    
    Federal Operating Permits Program; Final Rule
    
    Federal Register / Vol. 61, No. 127 / Monday, July 1, 1996 / Rules 
    and Regulations
    
    [[Page 34202]]
    
    
    
    ENVIRONMENTAL PROTECTION AGENCY
    
    40 CFR Parts 9, 55 and 71
    
    [FRL-5526-7]
    RIN 2060-AD68
    
    
    Federal Operating Permits Program
    
    AGENCY: Environmental Protection Agency (EPA).
    
    ACTION: Final rule.
    
    -----------------------------------------------------------------------
    
    SUMMARY: This action promulgates regulations setting forth the 
    procedures and terms under which the Administrator will administer 
    programs for issuing operating permits to covered stationary sources, 
    pursuant to title V of the Clean Air Act as amended in 1990 (Act). 
    Although the primary responsibility for issuing operating permits to 
    such sources rests with State, local, and Tribal air agencies, EPA will 
    remedy gaps in air quality protection by administering a Federal 
    operating permits program in areas lacking an EPA-approved or 
    adequately administered operating permits program. Federally issued 
    permits will clarify which requirements apply to sources and will 
    enhance understanding of and compliance with air quality regulations.
    
    EFFECTIVE DATE: July 31, 1996.
    
    FOR FURTHER INFORMATION CONTACT: Candace Carraway (telephone 919-541-
    3189) or Kirt Cox (telephone 919-541-5399), U. S. Environmental 
    Protection Agency, Office of Air Quality Planning and Standards, 
    Information Transfer and Program Integration Division, Mail Drop 12, 
    Research Triangle Park, North Carolina 27711.
    
    SUPPLEMENTARY INFORMATION:
    
    Docket
    
        Supporting information used in developing the promulgated rules is 
    contained in Docket No. A-93-51. Supporting information used in 
    developing 40 CFR part 70 is contained in Dockets No. A-90-33 and No. 
    A-93-50. These dockets are available for public inspection and copying 
    between 8:30 a.m. and 3:30 p.m. Monday through Friday at EPA's Air 
    Docket, Room M-1500, Waterside Mall, 401 M Street SW, Washington, D.C. 
    20460. A reasonable fee may be charged for copying.
    
    Background Information Document
    
        A background information document (BID) for the promulgated rule 
    may be obtained from the docket. Please refer to ``Federal Operating 
    Permits Program - Response to Comments.'' The BID contains a summary of 
    the public comments made on the proposed Federal Operating Permits 
    Program rule and EPA responses to the comments.
    
    Regulated Entities
    
        Entities potentially regulated by this action are major sources, 
    affected sources under title IV of the Act (acid rain sources), solid 
    waste incineration units required to obtain a permit under section 129 
    of the Act, and those areas sources subject to a standard under section 
    111 or 112 of the Act which have not been exempted or deferred from 
    title V permitting requirements. Regulated categories and entities 
    include:
    
    ------------------------------------------------------------------------
                 Category                  Examples of regulated entities   
    ------------------------------------------------------------------------
    Industry..........................  Major sources under title I or      
                                         section 112 of the Act; affected   
                                         sources under title IV of the Act  
                                         (acid rain sources); solid waste   
                                         incineration units required to     
                                         obtain a permit under section 129  
                                         of the Act; area sources subject to
                                         new source performance standards or
                                         national emission standards for    
                                         hazardous air pollutants that are  
                                         not exempted or deferred from      
                                         permitting requirements under title
                                         V.                                 
    ------------------------------------------------------------------------
    
        This table is not intended to be exhaustive, but rather provides a 
    guide for readers regarding entities likely to be regulated by this 
    action. This table lists the types of entities that EPA is now aware 
    could potentially be regulated by this action. Other types of entities 
    not listed in the table could also be regulated. To determine whether 
    your facility is regulated by this action, you should carefully examine 
    the applicability criteria in section 71.3(a) of the rule. If you have 
    questions regarding the applicability of this action to a particular 
    entity, consult the person listed in the preceding FOR FURTHER 
    INFORMATION CONTACT section or the EPA Regional Office that is 
    administering the part 71 permit program for the State or area in which 
    the relevant source or facility is located.
        Outline. The information presented in this preamble is organized as 
    follows:
    
    I. Background
    II. Summary of Promulgated Rule
    III. Significant Changes to the Proposed Rule
    IV. Administrative Requirements
        A. Docket
        B. Executive Order 12286
        C. Regulatory Flexibility Act
        D. Paperwork Reduction Act
        E. Unfunded Mandates Reform Act
    
    I. Background
    
    A. Background of EPA's Development of the Proposed Part 71 Rule
    
        Title V of the Act requires that if a permits program meeting the 
    requirements of title V has not been approved for any State by November 
    15, 1995, EPA must promulgate, administer, and enforce a Federal title 
    V program for that State (42 U.S.C. section 7661a(d)(3)). Thus, from 
    the date of enactment of the 1990 Amendments to the Act, EPA was 
    subject to a 5-year deadline to establish a Federal program for States 
    that do not obtain EPA approval of their State programs within that 
    time. The Act had also placed EPA under a 1-year deadline to promulgate 
    regulations establishing the minimum elements of approvable State 
    permit programs (42 U.S.C. section 7661a(b)). The EPA promulgated its 
    regulations establishing these criteria, codified at 40 CFR part 70 
    (the part 70 rule), on July 21, 1992 (57 FR 32250). States were then to 
    submit their title V programs for EPA review by November 15, 1993, and 
    EPA was to approve or disapprove those submitted programs within 1 year 
    of receiving them (42 U.S.C. section 7661a(d)(1)). Thus, under the 
    temporal scheme of title V, EPA was to approve or disapprove timely 
    submitted State title V programs by November 15, 1994, exactly 1 year 
    before EPA's duty to establish a Federal program for unapproved States 
    would ripen.
        Almost immediately upon promulgation of part 70, numerous industry, 
    State and local government, and environmentalist petitioners challenged 
    EPA's final rule in litigation in the Court of Appeals. See Clean Air 
    Implementation Project v. EPA, No. 92-1303 (D.C. Cir.). Petitioners 
    identified dozens of issues to which they objected in the part 70 rule, 
    and EPA decided to conduct broad-based settlement discussions with all 
    petitioners concerning these issues. These discussions occurred for 
    over a year following the commencement of the litigation, and resulted 
    in EPA, with the consultation of all of the litigants, developing 
    proposed revisions to many provisions in the part 70 rule. These 
    provisions mainly concerned the flexibility provisions of part 70, 
    which governed when permits would need to be revised to reflect changes 
    in operation at sources, and the procedures by which permits would be 
    revised. On August 29, 1994, EPA published proposed substantial 
    revisions to part 70 reflecting the outcome of these discussions (59 FR 
    44460) (hereafter ``August 1994 proposed revisions to part 70''). That 
    proposal reflected EPA's
    
    [[Page 34203]]
    
    most current thinking at the time concerning the proper implementation 
    of title V, and departed in numerous respects from positions taken in 
    the existing promulgated part 70 rule.
        When EPA began developing part 71 in the fall of 1993, settlement 
    discussions concerning part 70 were still ongoing and were yielding 
    what appeared to be fruitful results. The Agency believed at the time 
    that any needed revisions to part 70 would be finalized well in advance 
    of the deadline for establishing any necessary Federal programs, and so 
    decided to develop part 71 based on contemplated proposed revisions to 
    part 70, as EPA wished to model part 71 on its long-term implementation 
    goals for title V, rather than on provisions of a part 70 rule that EPA 
    did not believe would remain as promulgated in the current rule.
        When EPA published its proposed revisions to part 70 in August 
    1994, the Agency still believed that the revisions would be finalized 
    in time for EPA to base its part 71 Federal program rule on the revised 
    part 70. Consequently, when EPA published its proposed part 71 
    regulations on April 27, 1995, the proposal was based on the August 
    1994 proposed revisions to part 70 (60 FR 20804; hereafter, ``part 71 
    proposal''). The part 71 proposal thus contained provisions concerning 
    critical definitions under title V, the scope of applicability of the 
    program to sources, requirements governing applications and permit 
    content, and, most significantly, operational flexibility and permit 
    revisions that departed from the current part 70 rule's corresponding 
    provisions. In the proposal notice, the Agency specifically solicited 
    comment on whether the Agency had appropriately based part 71 upon the 
    relevant provision of the existing part 70 rule and the recently 
    proposed revision to part 70. See 60 FR at 20805.
        At the time of proposal of part 71, the Agency was aware of many 
    adverse comments on the August 1994 proposed revisions to part 70, and 
    EPA had engaged in discussions with stakeholders to obtain 
    recommendations for publishing a supplemental proposal to revise the 
    flexibility provisions of part 70. See 60 FR at 20805, 20817. The part 
    71 proposal notice indicated that the Agency believed it might not be 
    possible to promulgate final permit revision procedures for part 71, in 
    light of the ongoing discussions to develop part 70 permit revision 
    procedures in time to meet the statutory deadline for establishing 
    Federal programs in States lacking approved part 70 programs. As a 
    result, the notice suggested that EPA may have to finalize the part 71 
    rule in two phases, the first without any provisions for revising 
    permits, which would be addressed in a later supplemental proposal. Id. 
    Indeed, EPA's supplemental proposal for both parts 70 and 71, published 
    on August 31, 1995, described how part 71's future permit revision 
    procedures would be modelled upon the part 70 procedures for permit 
    revisions proposed in that notice (60 FR 45530; hereafter, ``August 
    1995 supplemental proposal'').
    
    B. The Need for Part 71 To Facilitate Transition
    
        In the part 71 proposal notice, EPA stressed the need for 
    implementation of part 71 to facilitate a smooth transition to State 
    implementation of title V through approved part 70 programs. See 60 FR 
    at 20805, 20816. The EPA continues to believe that Congress envisioned 
    that States would have primary responsibility for implementing title V, 
    just as they do for implementing much of the rest of the Act. See, for 
    example, section 101(a)(3) of the Act, in which Congress found that air 
    pollution prevention and air pollution control at its source is the 
    primary responsibility of States and local governments (42 U.S.C. 
    section 7401(a)(3)). Note also that under title V of the Act, Congress 
    gave States the initial opportunity to develop and administer title V 
    programs, while directing EPA to function as a backstop if States are 
    unable to adopt provisions under State law to take on title V 
    responsibilities, rather than directing EPA to establish the Federal 
    program first and then allowing States to apply to take over title V 
    administration, as under prior permitting programs such as the 
    prevention of significant deterioration (PSD) and the national 
    pollutant discharge elimination system (NPDES) under the Clean Water 
    Act.
        The EPA believes that granting States primary responsibility to 
    implement title V makes good policy sense. States are far better 
    positioned than EPA to administer permitting programs covering their 
    resident sources for several reasons. First, States are more familiar 
    with the operational characteristics of resident sources, and with the 
    applicable requirements to which they are subject. In having had the 
    lead on developing State implementation plans (SIP's) and implementing 
    other provisions of the Act that apply to these sources, States have 
    developed substantial expertise in, among other things, running air 
    permit programs that govern new construction and changes in emissions 
    of air pollutants such as the new source review (NSR) and PSD programs. 
    States have developed enforcement programs based on this structure, and 
    are able to coordinate their permitting programs with the goals and 
    needs of their overall air pollution control programs. Finally, 
    compared to EPA Regional offices, States are simply closer to their 
    sources, have greater resources, and are better able to respond to the 
    regulated community and its needs for expeditious permit processing.
        In light of this, EPA has repeatedly stated its belief that 
    federally-implemented part 71 programs would be of short duration, 
    lasting only until the few remaining States that have not developed 
    approvable part 70 programs are able to submit title V programs that 
    meet the requirements of the Act. Rather than viewing part 71 only as a 
    means of exerting leverage in States that have not yet adopted adequate 
    part 70 programs, EPA has also viewed part 71 as an opportunity to aid 
    States in taking up responsibility to implement title V. To this end, 
    EPA has attempted to structure the rule so that States in which part 71 
    programs are established will be able to use the program as an aid to 
    adopting and implementing their own part 70 programs. For example, 
    today's rule provides that States can take delegation of administration 
    of the Federal program in their States. If a State that for whatever 
    reason has not been successful in developing its own statutes and 
    regulations to implement title V is nevertheless capable of running a 
    Federal program, EPA sees no reason not to offer the State the 
    opportunity to more efficiently run the permit program than EPA 
    believes the Agency could. The EPA also believes that the experience of 
    running the Federal program may assist States in overcoming any 
    remaining hurdles that have so far prevented them from adopting 
    adequate title V programs under State law.
    
    C. Basing Part 71 on the Part 70 Program
    
        In the part 71 proposal notice, EPA stated its view that it is 
    appropriate to model part 71 procedures on those required by part 70, 
    in order to promote national consistency between title V programs that 
    are administered throughout the country. See 60 FR at 20816. Such 
    national consistency would ensure that sources are not faced with 
    substantially different programs simply because EPA, as opposed to 
    State agencies, is the relevant title V permitting authority, would 
    promote uniformity in affected State and public participation, and 
    would provide a level playing field for sources. Basing part 71 on part 
    70 would also encourage States
    
    [[Page 34204]]
    
    that are still developing their title V programs to take delegation of 
    the part 71 program, as it would be more consistent with the programs 
    they are preparing to implement under State law. States taking 
    delegation would in turn ensure smoother transition to State 
    administration of part 70 programs, as sources would have already 
    become familiar with the State as the title V permitting authority and 
    would not need to restart their permit application process anew when 
    the State program receives EPA approval.
        Since at the time the part 71 proposal was being developed it 
    appeared to EPA that part 70 would soon be revised in many significant 
    respects, EPA chose to base the proposal upon the recent proposed 
    revisions to part 70, rather than on the existing promulgated rule. 
    This was due in part to the fact that the August 1994 proposed 
    revisions to part 70 addressed a number of basic issues under title V 
    that necessarily would govern how those issues are addressed in part 71 
    (such as the definition of major source and the necessary provisions to 
    implement section 502(b)(10) of the Act), and in part to the Agency's 
    wish to provide in the Federal rule many of the benefits of the August 
    1994 proposed revisions to part 70. As noted above, however, EPA 
    specifically asked commenters to address whether EPA had 
    inappropriately either followed or departed from the approaches taken 
    in both the current part 70 rule and its proposed revisions.
        Echoing their comments on the August 1994 proposed revisions to 
    part 70, industry commenters unanimously argued that the permit 
    revisions procedures contained in the part 71 proposal were too complex 
    and confusing and would hinder sources' abilities to make rapid changes 
    in response to market needs. In addition, most industry commenters 
    presented three general arguments in response to EPA's proposal to 
    establish a uniform national part 71 rule based on the August 1994 
    proposed revisions to part 70. The first type of argument was that EPA 
    should not promulgate a uniform national part 71 rule at all, but 
    rather should develop part 71 programs case-by-case, taking into 
    account the specific characteristics of the State's existing air 
    program, and basing the State's part 71 program as much as possible on 
    the State's part 70 program that it has developed to date and that EPA 
    had not found to be inadequate. According to this argument, the best 
    way to facilitate transition from Federal to State implementation of 
    title V is to make sure the Federal and State programs are virtually 
    identical in each relevant State, even if that means the Federal 
    programs would differ from State to State. It would follow that EPA 
    should approve whatever adequate elements a State had adopted for its 
    title V program, and then only fill the remaining gaps with Federal 
    provisions as necessary. This argument also held that section 502 of 
    the Act actually requires a case-by-case approach to developing part 71 
    programs for States, and that the Act does not authorize EPA to 
    promulgate a nationally uniform rule.
        While EPA agrees that in theory the smoothest transition from 
    Federal to State implementation might occur where the Federal program 
    is identical to the State's, the Agency does not agree that it is 
    inappropriate to promulgate a nationally uniform rule for part 71. At 
    the outset, EPA disagrees with the assertion that the Agency lacks 
    legal authority to establish a nationally uniform rule for part 71. 
    While section 502(d)(3) of the Act does require EPA to promulgate, 
    administer and enforce a title V program ``for'' any State that does 
    not obtain part 70 approval, 42 U.S.C. section 7661a(d)(3), that 
    language does not compel a separate State-by-State approach to 
    establishing a Federal title V program; nor does it compel a Federal 
    program that is based on the State's existing but as yet unapproved 
    State program. Indeed, EPA would be hard-pressed to base a Federal 
    program on a State program where no State program has ever been adopted 
    or submitted for EPA evaluation. Even if a State had adopted and 
    submitted a program, EPA stresses that the Agency can only evaluate the 
    adequacy of State programs through notice and comment rulemaking, which 
    might not occur before a Federal program is due. The EPA believes 
    Congress must have recognized the possibility that EPA would be called 
    upon to establish a Federal program even where a State has never 
    adopted any State program of its own or where a program had not been 
    submitted in time for EPA to find it adequate; in such situations, it 
    would be impossible for EPA to base the Federal program on the State's. 
    The EPA also believes that the resource burden of establishing and 
    implementing different case-by-case programs for States would overwhelm 
    EPA Regional offices and establishing a generic template for part 71 is 
    a far more efficient use of Agency resources to get the Federal program 
    up and running. The EPA has consequently concluded that a nationally 
    uniform regulation is necessary for purposes of carrying out the 
    Agency's functions under title V. Section 301(a)(1) of the Act 
    authorizes EPA to prescribe such regulations as are necessary to carry 
    out the Administrator's functions under the Act (42 U.S.C. section 
    7601(a)(1)). Thus, EPA believes it has ample statutory authority to 
    establish the most efficient and nationally consistent part 71 
    regulation possible. Finally, EPA notes that EPA's other permitting 
    programs under its environmental statutes, such as the NPDES program 
    and the PSD program, are governed by nationally uniform regulations, 
    implementation of which have been very successful. The EPA sees no 
    reason to depart from this established approach for purposes of running 
    Federal title V programs, especially since Congress clearly did 
    anticipate that EPA would first address title V through establishing 
    regulations that would govern the minimum elements of title V programs 
    to be administered by any air pollution control agency. See section 
    502(b) of the Act, 42 U.S.C. section 7661a(b).
        The second type of industry argument in response to basing the part 
    71 proposal on the proposed revisions to part 70 stressed that EPA 
    should delay promulgation of any part 71 rule until the revisions to 
    part 70 are finalized. This argument pointed out that promulgating part 
    71 based on the August 1994 proposed revisions to part 70 would result 
    in the part 71 rule being based on an approach that the Agency itself 
    had begun to revise in developing the supplemental proposed revisions 
    to part 70 (which were eventually published just 4 months after the 
    date of the part 71 proposal). The argument noted that since EPA is 
    envisioning substantial changes to the part 70 rule, the part 71 rule 
    should not finalize title V issues that will remain in transition until 
    the part 70 rule is finally revised. This argument also specifically 
    responded adversely to EPA's statement in the proposal that it may be 
    necessary to split finalization of part 71 into two phases in which the 
    operational flexibility and permit revision procedures would remain 
    reserved until a second phase. In the view of these commenters, such 
    provisions are critical components of any part 71 rule that is adopted, 
    and it would not be appropriate to leave them out of part 71 for any 
    unspecified time. This argument also stated that finalizing part 71 now 
    based upon the proposed revisions to part 70 would actually impede 
    transition to approved State part 70 programs, since the Federal 
    program, and the approved State program based on the current part 70 
    that replaces it, would take very different approaches to such 
    fundamental issues as applicability of the program, operational 
    flexibility
    
    [[Page 34205]]
    
    and permit revision procedures. Finally, this argument offered a theory 
    that title V actually does not require EPA to adopt part 71 programs 
    for States until May 15, 1997; under this theory, a commenter argued 
    that the Act actually gives States until May 15, 1995, rather than 
    November 15, 1993, to submit initial title V programs, since States 
    have 18 months following the first ``due date'' to submit any remedies 
    to deficient programs and avoid sanctions that would fall after that 
    18-month period. The commenter would interpret the date on which the 
    18-month period expires as the date referred to in section 502(d)(3) 
    and argues that EPA is not required to promulgate a Federal program 
    until 2 years after the expiration of the 18-month period.
        First, EPA is not persuaded by the commenter's argument that part 
    71 programs are not due until May 15, 1997. Section 502(d)(1) of the 
    Act clearly provides that States are to submit their title V programs 
    ``[n]ot later than 3 years after the date of enactment of the Clean Air 
    Act Amendments of 1990,'' 42 U.S.C. section 7661a(d)(1), which occurred 
    on November 15, 1990. Moreover, section 502(d)(3) clearly refers to 
    ``the date required for submission of such a program under paragraph 
    (1) (of section 502),'' 42 U.S.C. section 7661a(d)(3), as the trigger 
    for the 2-year period after which EPA must establish Federal programs. 
    There is no reference to any 18-month grace-period in section 
    502(d)(3), and EPA disputes the assertion that the date on which a 
    sanctions clock expires under section 502(d)(2) can be viewed as the 
    ``real'' deadline for submission of State programs in the face of the 
    plain language of section 502(d)(1) and section 502(d)(3)'s reference 
    to the deadline in section 502(d)(1). Thus, while EPA is sympathetic to 
    concerns that finalizing part 71 in advance of the Agency finally 
    revising part 70 could result in the Agency promulgating provisions 
    that are essentially moving targets in the Federal rule, EPA does not 
    believe it has the authority to delay issuance of part 71 beyond the 
    deadline prescribed by Congress. Moreover, as a policy matter, EPA 
    believes it is necessary to put part 71 in place to aid States that to 
    date have unsuccessfully struggled to develop approvable title V 
    programs, as it is a potential vehicle for State administration of 
    title V (through delegation of part 71) even where obstacles remain 
    that block certain States from obtaining part 70 approval. The EPA does 
    not believe that the environmental benefits of title V should be 
    delayed simply due to the fact that some States have not been 
    successful at developing title V programs. Moreover, EPA does not feel 
    it would be appropriate to attempt to justify delaying promulgation and 
    implementation of the Federal program because of the continuing 
    difficulties in revising the part 70 rule. However, EPA is persuaded by 
    commenters that the part 71 rule should not contain gaps to be filled 
    in at a second stage for provisions for operational flexibility and 
    permit revisions, and is sympathetic to concerns that basing these 
    provisions on the August 1994 proposed revisions to part 70 might even 
    interfere with transition to State programs approved under the current 
    part 70 rule. These latter points are discussed in more detail below.
        The third general type of industry argument in response to basing 
    part 71 on the August 1994 proposal was that if EPA must establish a 
    Federal program now, it should do so based on the existing part 70 
    rule, and revise the program later when part 70 is revised. This 
    argument recognized that EPA may simply be unable in certain cases to 
    base a State-specific part 71 program on an existing State program, but 
    stressed the fact that any program that the State is still struggling 
    to adopt would be based on the existing part 70 rule, rather than on 
    the proposed revisions thereto. The argument pointed out the fact that 
    under the August 1994 proposed revisions to part 70, EPA planned to 
    allow States several years following final promulgation before States 
    would be expected to implement new part 70 programs based on the 
    revised rule. Thus, commenters observed, States would likely be 
    developing and implementing part 70 programs based on the July 1992 
    rule for considerable time. In light of this, it would actually 
    interfere with smooth transition from Federal to State implementation 
    to base part 71 on the future part 70 rule, especially in light of the 
    fact that at this point how part 70 will be ultimately revised is only 
    speculative; rather, transition could be facilitated only where the 
    Federal rule resembles the model that the State rule is expected to 
    follow. States might be less inclined to take delegation of a Federal 
    rule that does not resemble existing part 70 and the State analogues 
    that are being developed, and thus sources would be more likely to be 
    faced with different permitting authorities under part 71 and part 70 
    programs. Moreover, the relevant guidance that EPA had issued to date 
    to aid implementation of the current rule, such as the Agency's ``White 
    Paper for Streamlined Development of Part 70 Permit Applications'' 
    (herein referred to as the ``first white paper'') and the March 5, 1996 
    guidance document entitled ``White Paper Number 2 for Improved 
    Implementation of the Part 70 Operating Permits Program, could be less 
    valuable as an aid in implementing a Federal rule that is not based on 
    the current part 70, and both sources and part 71 permitting 
    authorities could be forced to start somewhat from scratch in 
    implementing the program.
        The EPA agrees that the most appropriate course of action is to 
    promulgate, on an interim basis, part 71 based on the current part 70 
    rule. In reaching this conclusion, EPA was persuaded by concerns about 
    impeding transition to part 70 approval under the current rule and by 
    industry concerns about issuing a rule containing gaps regarding 
    operational flexibility and permit revisions. Moreover, as many issues 
    in part 70 are still outstanding following the August 1994 and August 
    1995 proposals, and as many of those issues concern key definitions and 
    procedures under title V, it would be premature for EPA to finalize 
    part 71 based upon the proposed revisions to part 70 until it makes 
    final decisions on these issues in part 70. Thus, the only way EPA can 
    fulfill its mandate to step in as the title V permitting authority for 
    States that have not obtained part 70 approval at this time, and to do 
    so by establishing a complete part 71 program that provides the 
    flexibility needed by industry and mandated by title V, is to 
    promulgate the rule based upon the current part 70 regulation. The EPA 
    stresses, however, that by finalizing this interim approach in part 71, 
    the Agency does not preclude itself from revising part 71 in the future 
    as based on appropriate aspects of either the August 1994, April 1995, 
    or August 1995 proposals for parts 70 and 71. In fact, EPA intends to 
    issue a second round of final rulemaking for part 71 (hereafter ``phase 
    II rulemaking) in the future once the Agency has resolved with relevant 
    stakeholders the outstanding issues and is prepared to promulgate final 
    revisions to part 70. As a general matter, EPA stresses that the most 
    current reflection of the Agency's intended policy regarding many of 
    these provisions is the August 31, 1995 supplemental proposal. 
    Consequently, while the provisions adopted today in part 71 that relate 
    to outstanding issues under the definitions, applicability, permit 
    application, permit content, permit revisions and reopenings, and 
    affected State and EPA review sections are consistent with the 
    corresponding
    
    [[Page 34206]]
    
    provisions in the existing part 70 rule, rather than with provisions in 
    the proposals mentioned above, it should be expected that EPA will 
    issue a second final rulemaking, without a second round of proposal, to 
    conform part 71 to the revised part 70 rule when the Agency is prepared 
    to issue it.
        The EPA believes that this approach is a logical outgrowth of the 
    part 71 proposal issued in April 1995. While that proposal only 
    contained regulatory provisions based on the August 1994 proposed 
    revisions to part 70, EPA explicitly solicited comment on whether the 
    proposal was in any way inappropriately inconsistent with the current 
    part 70 rule. Clearly, the commenters noted such inconsistencies, and 
    the proposal facilitated meaningful comment on what approach the Agency 
    should take in promulgating part 71 vis-a-vis the outstanding issues in 
    the part 70 revision process. As discussed above, the proposal enabled 
    industry commenters to fall into three basic categories in response to 
    the proposal--in fact, many commenters advanced more than one of the 
    basic types of arguments in their comments, realizing that the 
    different arguments might have different force depending upon the 
    extent to which States had actually developed and submitted their own 
    programs. The approach adopted today was urged by numerous industry 
    commenters as the most reasonable in light of the need to issue a part 
    71 program now, as opposed to leaving gaps to be filled in later at a 
    second stage of final rulemaking. In addition, today's rule is 
    consistent with the existing part 70 rule under which States continue 
    to submit programs, and under which EPA continues to approve those 
    programs. Thus, EPA does not believe that a second round of proposed 
    rulemaking is necessary before finalizing part 71 to conform to the 
    Agency's currently effective regulation implementing title V, part 70.
        In the following sections of this notice, the specific provisions 
    that are being finalized based upon current part 70 rather than upon 
    the provisions of the part 71 proposal are identified and further 
    discussed. For each of them, the general governing principle is that 
    while the Agency has proposed to revise part 70 to modify many of the 
    provisions corresponding to the part 71 provisions adopted today, EPA 
    is not yet prepared to adopt final positions on those issues and so, in 
    the interests of promoting smooth transition from Federal to State 
    implementation of title V, is choosing to issue, on an interim basis, a 
    part 71 rule that matches as closely as possible the existing part 70 
    rule. The EPA's finalization of those provisions today in no way 
    reflects the Agency's ultimate decision to renounce any of the 
    positions articulated in the proposed revisions to part 70 or the 
    corresponding proposals for part 71.
    
    II. Summary of Promulgated Rule
    
    A. Applicability
    
        The Federal operating permits program requires all part 71 sources 
    to submit permit applications to the permitting authority no later than 
    within 1 year of the effective date of the program. The operating 
    permit program applies to the following sources:
        1. Major sources, defined as follows:
        a. Air toxics sources, as defined in section 112 of the Act, with 
    the potential to emit 10 tons per year (tpy), or more, of any hazardous 
    air pollutant (HAP) listed pursuant to 112(b); 25 tpy, or more, of any 
    combination of HAP listed pursuant to 112(b); or a lesser quantity of a 
    given pollutant, if the Administrator so specifies (501(2)(A)).
        b. Sources of air pollutants, as defined in section 302, with the 
    potential to emit 100 tpy, or more, of any pollutant (501(2)(B)).
        c. Sources subject to the nonattainment area provisions of title I, 
    part D, with the potential to emit, depending on the nonattainment area 
    designation 10 or more tpy of volatile organic compound (VOC) or oxides 
    of nitrogen, 50 or more tpy of carbon monoxide, and seventy or more tpy 
    of particulate matter (501(2)(B)).
        2. Any other sources subject to a standard under section 111 or 
    112.
        3. Sources subject to the acid rain program (501(1)).
        4. Any source subject to the PSD program or the NSR program under 
    title I, part C or D.
        5. Any other stationary source in a category EPA designates, in 
    whole or in part, by regulation, after notice and comment.
        For purposes of determining applicability, a source's total 
    emissions of a pollutant are found by summing the potential emissions 
    of that pollutant from all emissions units under common control at the 
    same plant site. If a source is a major source, even if only due to the 
    total emissions from one pollutant, then a source must submit (with few 
    exceptions) a permit application that includes all emissions of all 
    regulated air pollutants from all emissions units located at the plant.
        Part 71 follows the approach of part 70 in deferring nonmajor 
    sources from permitting requirements. The permitting requirements for 
    nonmajor sources subject to a standard under section 111 or 112 of the 
    Act prior to July 21, 1992 are deferred for 5 years from the effective 
    date of the first approved part 70 program that deferred nonmajor 
    sources. The EPA may determine on a case-by-case basis permitting 
    requirements for nonmajor sources when they become subject to new 
    section 111 or 112 standards. Sources subject to the new source 
    performance standard for new residential wood heaters or the national 
    emission standards for hazardous air pollutants for asbestos as it 
    applies to demolition and renovation activities are permanently exempt 
    from permitting requirements.
    
    B. Program Implementation
    
        The EPA will administer a part 71 program for those portions of a 
    State that lack EPA approval for its operating permits program or for a 
    State that fails to adequately administer and enforce an approved 
    program. However, the requirement that EPA establish a Federal program 
    for States lacking a fully approved program is suspended if a State 
    program is granted interim approval. The EPA will also administer part 
    71 programs in Tribal areas. Should a part 71 program become effective 
    prior to the issuance of part 70 permits to all sources (under an 
    approved part 70 program), EPA will require part 71 permit applications 
    from sources that have not received part 70 permits. Applications shall 
    be due within a year of the effective date of the part 71 program. The 
    EPA will take final action on at least one-third of the applications 
    annually.
        Section 71.4 also establishes procedures that would be used for 
    issuing permits to certain sources located on the Outer Continental 
    Shelf (OCS) and after EPA objects to a proposed or issued State permit.
        The EPA may also delegate the responsibility for administering the 
    part 71 program to the State or eligible Tribe if the requirements of 
    section 71.10 have been met. However, delegation will not constitute 
    approval of a State or Tribal operating permits program under part 70.
        The EPA will suspend the issuance of part 71 permits upon 
    publication of notice of approval of a State or Tribal operating 
    permits program under part 70. The EPA or the delegate agency will 
    continue to administer and enforce part 71 permits until they are 
    replaced by permits issued under the approved part 70 program.
        The EPA will publish a notice in the Federal Register informing the 
    public of the effective dates or delegation of any part 71 programs for 
    States, Tribal areas,
    
    [[Page 34207]]
    
    and OCS sources. Where practicable, EPA will also publish notice in a 
    newspaper of general circulation within the area subject to the part 71 
    program and will notify the affected government.
    
    C. Permit Applications
    
        Each source meeting the applicability criteria of this part is 
    required to submit timely and complete information on standard 
    application forms provided by the permitting authority. Streamlined 
    forms for electronic formats may be provided.
        An initial part 71 permit application is required within 12 months 
    of the later of:
        1. The effective date of this part in a State, Tribal area, or OCS 
    area where a source is located, unless the source has an existing part 
    70 permit;
        2. The expiration of any deferral for a nonmajor source;
        3. The date a source commences operation; or
        4. The date a source meets any of the applicability criteria of 
    section 71.3.
        Sources with part 70 permits in force at the time part 71 becomes 
    effective in the area where they are located would not have to apply 
    for a part 71 permit until their part 70 permit expires. Prior to its 
    expiration, the part 70 permit may be modified by EPA.
        Sources would be notified of the requirement to submit an 
    application at least 180 days prior to when the application is due.
        The permitting authority will perform a completeness determination 
    within 60 days of receipt of an application, or the application will be 
    deemed complete by default. A complete application would contain all 
    the information needed to begin processing the permit application, 
    including, at a minimum, a completed standard application form (or 
    forms) and a compliance plan.
        The compliance plan describes how the source plans to maintain or 
    to achieve compliance with all applicable air quality requirements 
    under the Act. This plan must include a schedule of compliance and a 
    schedule for the source to submit progress reports to the permitting 
    authority. Each source must submit a compliance certification report in 
    which it certifies its status with respect to each requirement, and the 
    method used to determine the status.
        Each operating permit application, report, or compliance 
    certification submitted pursuant to part 71 must include a 
    certification signed by a responsible official attesting to the truth, 
    accuracy, and completeness of the information submitted.
        Applicants may be required to update information in the application 
    after the filing date and prior to the release of the draft permit.
    
    D. Permit Content
    
        Part 71 permits must meet all applicable requirements of the Act 
    and, among other things, must contain:
        1. A 5-year term for acid rain sources, up to a 12-year term for 
    certain municipal waste combustors, and up to a 5-year term for all 
    other sources.
        2. Limits and conditions to assure compliance with all applicable 
    requirements under the Act.
        3. A schedule of compliance, where applicable.
        4. Inspection, entry, monitoring, compliance certification, 
    recordkeeping, and reporting requirements to assure compliance with the 
    permit terms and conditions.
        5. A provision describing permit reopening conditions.
        6. Provisions under which the permit can be revised, terminated, 
    modified, or reissued for cause.
        7. Provisions ensuring operational flexibility so that certain 
    changes can be made within a permitted facility without a permit 
    revision.
        8. A provision that nothing in the permit or compliance plan 
    affects allowances under the acid rain program.
        All terms and conditions in a part 71 permit, including any 
    provisions designed to limit a source's potential to emit, are 
    enforceable by the Administrator and citizens under the Act.
        Like part 70, part 71 would allow sources to apply for a permit 
    shield, i.e., a provision in the permit that states that if the source 
    complies with terms and conditions of the permit, the source shall be 
    deemed in compliance with any applicable requirements reflected in the 
    permit as of the date of permit issuance.
    
    E. Permit Issuance and Review
    
        Regulations concerning the processes for permit issuance, review, 
    renewal, revision, and reopening are found in sections 71.7 and 71.11. 
    Briefly, these include:
    1. Action on Applications for Permit Issuance and Permit Renewal
        Section 71.7(a) describes the conditions that must be satisfied 
    before EPA or a delegate agency may issue a permit. These include 
    receipt of a complete application, compliance with public participation 
    requirements, and notification of affected States, Indian Tribes, and 
    EPA (if the program has been delegated). Except during the initial 
    phase-in of the program, the permitting authority is required to act on 
    permit applications within 18 months after receiving a complete 
    application.
        The timely submittal of a complete application and any additional 
    required information creates a ``shield'' against enforcement for 
    failure to have a part 70 or part 71 permit. Permits being renewed are 
    subject to the same procedural requirements that apply to initial 
    permit issuance, as provided in section 71.7(c). The administrative 
    procedures for permit issuance are contained in section 71.11 and are 
    generally based on analogous provisions governing other EPA permitting 
    programs at 40 CFR part 124.
    2. Permit Revisions
        Sections 71.7 (d) and (e) outline the mechanisms for permit 
    modification and administrative amendments that are needed to revise 
    part 71 permits to accommodate changes that would otherwise violate 
    terms and conditions of the permit.
        Administrative amendments can be accomplished by the permitting 
    authority without public or EPA review. These permit revisions include 
    correction of typographical errors, changes in address or source 
    ownership, as well as incorporation of requirements established under 
    State preconstruction review that meet certain procedural and 
    compliance requirements.
        If a change is not prohibited or addressed by the permit, the 
    permittee may make the change after submitting a notice, and the permit 
    is revised at renewal.
        The regulations establish minor and significant permit modification 
    procedures for changes that go beyond the activities allowed in the 
    original permit or that increase the total emissions allowed under the 
    permit.
        Minor permit modifications reflect increases in permitted emissions 
    that do not amount to modifications under any requirement of title I 
    and that do not meet certain other requirements. Minor permit 
    modification procedures require a source to provide advance notice of 
    the proposed change, but allow a change to take effect prior to the 
    conclusion of the revision procedures.
        A source that makes a change before the minor permit modification 
    has been issued does so at its own risk. It is not protected from 
    underlying applicable requirements by any shield. It is only afforded a 
    temporary exemption from the formal requirement that it operate in 
    accordance with the permit terms that it seeks to change in its 
    modification application. Should the proposed permit modification be 
    rejected, the source would be subject to enforcement
    
    [[Page 34208]]
    
    proceedings for any violation of these requirements.
        Significant permit modifications are inherently more complex, and 
    will require additional time to accomplish. Permitting authorities will 
    initiate their review of the proposed changes after receipt of an 
    application.
        Sources subject to requirements of the acid rain program must hold 
    allowances to cover their emissions of sulfur dioxide (SO2). 
    Allowance transactions registered by the Administrator will be 
    incorporated into the source's permit as a matter of law, without 
    following either the permit modification or amendment procedures 
    described above.
    3. Reopening for Cause
        The permitting authority may terminate, modify, or revoke and 
    reissue a permit for cause. Reopening and reissuing procedures follow 
    the same procedures as apply to initial issuance. Advance notice is 
    required before permit reopenings may be initiated.
        Section 71.7(f) requires that permits issued to major sources with 
    3 or more years remaining in the permit's term be reopened to 
    incorporate applicable requirements which are promulgated after the 
    issuance of the permit. Revisions must be made as expeditiously as 
    practicable, but no later than 18 months after the promulgation of such 
    additional requirements.
    4. Permit Notification to EPA and Affected States
        Consistent with 40 CFR section 70.8(b), EPA or the delegate agency 
    would be required to provide notice of draft permits to all affected 
    States and to certain Indian Tribes.
        Affected States are those whose air quality may be affected and 
    that are contiguous to the State in which the source is located, or 
    that are within 50 miles of the source. The permitting authority must 
    give affected States an opportunity to submit written recommendations 
    for the permit and notify any affected State in writing of any refusal 
    to accept all of its recommendations.
        Although Indian Tribes are not considered affected States unless 
    they establish their compliance with criteria for being treated in the 
    same manner as States pursuant to section 301(d) of the Act, the Agency 
    believes federally recognized Tribes should be given notice of draft 
    permits that may be issued to sources that could affect Tribal air 
    quality. The regulation requires that the permitting authority send 
    such notices.
        The Act authorizes EPA to object to any permit that would not be in 
    compliance with the applicable requirements of the Act. In the case of 
    a delegated program, the permitting authority may not issue a part 71 
    permit if the Administrator has objected to its issuance in writing 
    within 45 days of receipt of the proposed permit.
    5. Administrative and Judicial Review
        After the close of the public comment period on a draft permit, the 
    permitting authority will issue a final permit decision. Within 30 days 
    of the final permit decision, anyone who filed comments on the draft 
    permit or participated in the public hearing may petition the 
    Environmental Appeals Board (EAB) to review any condition of the 
    permit. In general, the objections in the petition must have been 
    raised during the public participation period on the permit. The 
    petition will stay the effectiveness of the specific terms of the 
    permit which are the subject of the request for review, pending 
    conclusion of the appeal proceedings.
        The EAB will issue an order either granting or denying the petition 
    for review. To the extent review is denied, the conditions of the final 
    permit decision become final agency action and are subject to judicial 
    review in the United States Court of Appeals under section 307(b) of 
    the Act. The decision of the EAB to issue or deny the permit is also 
    subject to judicial review.
        Interested persons (including permitees) are authorized to petition 
    the Administrator to reopen an already issued permit for cause. 
    Petitions would be required to be in writing and to contain facts or 
    reasons supporting the request.
    
    F. Permit Fees
    
        Section 71.9 establishes the Federal operating permits program fee 
    requirements for owners or operators of part 71 sources. The fees must 
    be sufficient to cover the permits program costs, including the 
    following:
        1. Reviewing and acting on any permit, permit revision, or permit 
    renewal, and processing permit reopenings.
        2. Administering the permit program.
        3. Implementing and enforcing the terms of any part 71 permit.
        4. Monitoring, modeling, manipulating, and tracking emissions.
        5. Providing support to small business stationary sources.
        Consistent with the two-phased approach to part 71 promulgation 
    described in this notice, EPA is today implementing a two-phased 
    approach to part 71 fee requirements. Phase I fee collection will be 
    sufficient to cover Phase I costs. Since Phase II fee collection is 
    associated with permit revision procedures, a fee amount for Phase II 
    cannot be finalized in today's rule. The Phase II fee will add the 
    costs for the permit revision procedures that are finalized in that 
    rulemaking.
        The dollar per ton fee will vary depending on the implementation 
    mechanism EPA uses to administer a part 71 program. A program that is 
    administered completely by EPA would charge $32 per ton per year (ton/
    yr). Permit fees for a program for which EPA relies on contractor 
    assistance to the greatest extent possible would be approximately $57 
    per ton/yr. Program costs (and fees) would vary among part 71 programs 
    depending on the hourly rate paid to the contractor for its work on the 
    particular State's part 71 program. The costs of a program that is 
    staffed in part by EPA employees and in part by contractors or by the 
    delegate agency would vary in accordance with the percentage of 
    personnel time allocated to non-EPA staff and the hourly rate paid to 
    the contractor for its work on the State's part 71 program.
        The EPA may suspend collection of part 71 fees for part 71 programs 
    which are fully delegated to States and for which EPA incurs no 
    administrative costs.
        The EPA may promulgate a separate fee schedule for a particular 
    part 71 program if the Administrator determines that the fee schedule 
    in the rule does not adequately reflect the cost of administering the 
    program.
        Sources are required to submit fee calculation worksheets and fees 
    at the same time as their initial permit applications are due and 
    thereafter on an annual basis.
        Part 71 program costs and permit fees will be reviewed by the 
    Administrator at least every 2 years, and changes will be made to the 
    fee schedule as necessary to reflect permit program costs.
    
    G. Federal Oversight of Delegated Programs
    
        Section 71.10 establishes the procedures EPA would follow when 
    delegating the authority to administer a part 71 program to a State, 
    eligible Indian Tribe, or other air pollution control agency. The EPA 
    will delegate authority to run the program where possible in order to 
    take advantage of existing expertise of the delegate agency or where it 
    seems probable that the delegate agency's submitted part 70 program 
    will be approved within a short time by EPA, provided in both cases 
    that the delegate agency has the authority to administer the program 
    that would be delegated.
    
    [[Page 34209]]
    
        A delegate agency must submit a formal request for delegation and 
    other documentation that shows the agency or eligible Tribe has 
    adequate legal authority and capacity to administer and enforce the 
    part 71 program. If the request for delegation is accepted, EPA and the 
    delegate agency will enter into an agreement that sets forth the terms 
    and conditions of the delegation.
        As part of its oversight of delegated programs, EPA would review 
    copies of applications, compliance plans, proposed permits and final 
    permits that the delegate agency would be required to send to EPA. The 
    EPA would have 45 days in which to review proposed permits. If EPA 
    objects to the issuance of a permit within that time, the delegate 
    agency would be required to revise and resubmit the proposed permit to 
    EPA.
        Delegation of a part 71 program would not relieve a State of its 
    obligation to submit an approvable part 70 program, nor from any 
    sanctions that the Administrator may apply for the State's failure to 
    have an approved part 70 program.
    
    H. Enforcement
    
        The Federal enforcement authority available under section 113 of 
    the Act for violations of title V and the regulations thereunder 
    provides broader enforcement authority than States are required to have 
    under the part 70 regulations. Examples of the Federal enforcement 
    authorities available under the Act include, but are not limited to, 
    the authority to: (1) restrain or enjoin immediately any person by 
    order or by suit in court from engaging in any activity in violation of 
    the Act that is presenting an imminent and substantial endangerment to 
    the public health or welfare, or the environment; (2) seek injunctive 
    relief in court to enjoin any violation of the Act; (3) issue 
    administrative orders that assess civil administrative penalties; (4) 
    assess and recover civil penalties; and (5) assess criminal fines.
    
    III. Significant Changes to the Proposed Regulations
    
    A. Section 71.2--Definitions
    
        The Agency has adopted definitions in today's rulemaking that are 
    consistent with and are mainly modelled on corresponding definitions in 
    the current part 70 rule, rather than on the part 71 proposal. 
    Consequently, many of the definitions adopted today differ from those 
    contained in the part 71 proposal which were largely based upon the 
    August 1994 proposed revisions to corresponding definitions in part 70 
    which the Agency is not yet prepared to finalize.
        Several definitions found in the proposed section 71.2 have been 
    revised to conform more closely to the definitions used in the current 
    part 70 rule. These include ``affected State,'' ``applicable 
    requirements,'' ``final permit,'' ``major source,'' ``permit 
    revision,'' ``permitting authority,'' and ``responsible official,'' 
    each of which is discussed briefly below. Similarly, EPA adopted 
    definitions for ``permit modification'' and ``section 502(b)(10) 
    change'' from the current part 70 rule, because these terms are 
    integral parts of today's rulemaking, which is based on the existing 
    part 70 regulations. Also, several definitions in the part 71 proposal 
    describe terms and concepts that the Agency has concluded are either 
    not necessary or are not ready to be finalized in today's rulemaking. 
    The terms for which EPA has not adopted a definition include 
    ``insignificant activity or emissions,'' ``major new source review,'' 
    ``minor new source review,'' ``potential to emit,'' ``title I 
    modification,'' and ``Tribal area.'' To the extent these proposed terms 
    were based on the August 1994 proposed revisions to part 70, EPA will 
    finally address them in the Phase II rulemaking.
        In addition, the Agency has retained several definitions found in 
    the part 71 proposal that are not found in the current part 70 rule, 
    but are needed for part 71. These include definitions for ``delegate 
    agency,'' ``part 71 permit,'' ``part 71 program,'' and ``part 71 
    source.'' The Agency has also adopted definitions for ``eligible Indian 
    Tribe,'' ``Federal Indian reservation,'' and ``Indian Tribe,'' which 
    were added to clarify which Tribes would be eligible to receive 
    delegation of the part 71 program and to be considered ``affected 
    States.''
        The part 71 proposal and the August 1995 supplemental proposal 
    reflect the Agency's position on what definitions would be appropriate 
    in conjunction with the permit revision procedures, operational 
    flexibility provisions, and other provisions that have been proposed 
    for finalization in the Phase II rulemaking. Subsequent to reviewing 
    all of the comments on both of these proposals, EPA may finalize 
    definitions that differ from those adopted today.
    1. Affected States
        a. Indian Tribes. The EPA received numerous comments from Indian 
    Tribes suggesting that federally recognized Indian Tribes should be 
    considered to be ``affected States'' if their air quality may be 
    affected or the Tribal area is contiguous to the State in which the 
    permittee is located or is within 50 miles of the permittee. They 
    contended that Tribes should not have to meet any type of eligibility 
    criteria in order to be considered an ``affected State.'' Contrary to 
    the view of these commenters, the EPA interprets section 301(d)(2) of 
    the Act as authorizing the Agency to treat Indian Tribes in the same 
    manner as a State for purposes of being an ``affected State'' only when 
    EPA has determined that the Indian Tribe has demonstrated that it has 
    met the eligibility criteria of section 301(d)(2) of the Act. The 
    second paragraph of the proposed definition of ``affected State'' was 
    inconsistent with this interpretation in that it would have treated 
    Tribes in the same manner as States if the permitting action concerned 
    a source located in a Tribal area, regardless of the Tribe's 
    eligibility status. Therefore, EPA has amended this paragraph to 
    include the same eligibility requirement as the first paragraph. That 
    is, that the Indian Tribe must have demonstrated that it has met the 
    eligibility criteria of section 301(d)(2). However, in the interest of 
    furthering government-to-government relationships with Tribes, EPA has 
    adopted a provision in section 71.8 that requires the part 71 
    permitting authority to provide notice of draft permits to any 
    federally recognized Indian Tribe whose air quality may be affected by 
    the permitting actions and whose reservation or Tribal area is 
    contiguous to the jurisdiction in which the part 71 permit is proposed 
    or is within 50 miles of the permitted source. (See discussion at 
    section III.G. of this notice.)
        b. Local agencies. The proposed definition of ``affected State'' in 
    the part 71 proposal added language not found in the current part 70 
    definition of ``affected State'' to the effect that, when a part 71 
    permit, permit modification, or permit renewal is proposed for a source 
    located within the jurisdiction of a local agency, that agency would be 
    considered an affected State. Today's rulemaking retains this approach 
    because it pertains to a situation which is unique to part 71, i.e., 
    when EPA administers a part 71 program in an area where the local 
    agency would normally be the permitting authority of record under an 
    approved part 70 program. The proposal also differed from today's 
    rulemaking in that under the proposal, local agencies would not 
    otherwise be considered affected States. Since the approach taken to 
    such jurisdictions is an issue for both parts 70 and 71, it will be 
    addressed in the Phase II rulemaking. In the interim, the proposed 
    language has been deleted to comport with the current part 70 
    definition.
    
    [[Page 34210]]
    
    2. Applicable Requirements
        The part 71 proposal expanded the part 70 definition of 
    ``applicable requirement'' to include the provision that any 
    requirement enforceable by the Administrator and by citizens under the 
    Act which limits emissions for the purpose of creating offset credits 
    or avoiding any applicability requirement is itself an applicable 
    requirement. This addition, while helpful for understanding what 
    constitutes an applicable requirement, was based on the August 1994 
    proposed revisions to part 70, which EPA is not yet prepared to finally 
    promulgate. As such, EPA believes it is not appropriate to finalize 
    this change for purposes of part 71 at this time, but intends to 
    address this issue in the Phase II rulemaking. It was therefore deleted 
    to comport with the current part 70 definition.
        The definition of ``applicable requirement'' in the part 71 
    proposal also differed from the definition in the current part 70 rule 
    in that it limited the title VI requirements that would have to be 
    included in a title V permit. This proposed language, while consistent 
    with the August 1994 proposed revisions to part 70, which, again, EPA 
    is not yet prepared to finalize, was removed so that the definition 
    would conform to the definition in the current part 70 regulation.
    3. Final Permit
        The proposal contained a proposed definition of ``final action or 
    final permit action.'' The final rule changes this term to ``final 
    permit'' in order to better harmonize the definition with the term 
    ``final permit'' in the current part 70 regulation promulgated at 
    section 70.2.
    4. Major Source
        The proposed part 71 rule contained a definition of ``major 
    source'' that was based on the proposed change to the term contained in 
    the August 1994 proposed revisions to part 70. Since publication of the 
    part 71 proposal, EPA has also proposed additional changes to the term 
    in the August 1995 supplemental proposal for parts 70 and 71. The EPA 
    is currently in the process of reviewing, evaluating and developing 
    positions in response to comments on this very important term and other 
    issues raised in the August 1995 proposal. Consequently, EPA is not yet 
    prepared to promulgate part 71 in general, or the major source 
    definition in particular, as based on the August 1994, April 1995 or 
    August 1995 proposals. The only exception to this approach is in regard 
    to source categories for which fugitive emissions are to be counted in 
    determining whether a source is a major source under section 302 of the 
    Act.
        Consistent with PSD and nonattainment NSR, current part 70 requires 
    the counting of fugitive emissions from source categories which have 
    been listed pursuant to section 302(j) in major source applicability 
    determinations. See the definition of ``major source'' at 40 CFR 
    section 70.2. The one difference, however, between the list of source 
    categories under PSD and nonattainment NSR and current part 70 is in 
    regard to the 27th category of sources that are required to count 
    fugitive emissions. In parts 51 and 52, the 27th category is stated as 
    follows:
    
        Any other stationary source category which, as of August 7, 
    1980, is being regulated under section 111 or 112 of the Act.
    
        In current part 70, the 27th category reads as follows:
    
        All other stationary source categories regulated by a standard 
    promulgated under section 111 or 112 of the Act, but only with 
    respect to those air pollutants that have been regulated for that 
    category;
    
        As can be seen from the above, one of the principal differences 
    between these two paragraphs is the date of August 7, 1980, which is 
    specified in the PSD and nonattainment NSR regulations, but is absent 
    from the current part 70 regulation. The result of this difference is 
    that part 70 literally requires sources to count fugitives even where 
    those sources are not required to do so in determining whether they are 
    major for purposes of PSD or nonattainment NSR. As stated in the 
    preamble to the August 1994 part 70 proposal, EPA acknowledges that it 
    did not follow the procedural steps necessary under section 302(j) to 
    expand the scope of sources in this category for which fugitives must 
    be counted in part 70 major source determinations. See memorandum of 
    June 2, 1995, entitled ``EPA Reconsideration of Application of 
    Collocation Rules to Unlisted Sources of Fugitive Emissions for 
    Purposes of Title V Permitting,'' from Lydia Wegman, Deputy Director, 
    Office of Air Quality Planning and Standards, to Regional Air 
    Directors. Instead of perpetuating this problem by following this 
    aspect of current part 70, and even though the Agency is not yet ready 
    to finalize the approach taken in the August 1995 supplemental proposal 
    for parts 70 and 71, EPA believes that an appropriate interim solution 
    is to finalize this category similar to how it was proposed in the 
    April 1995 part 71 proposal and consistent with the provisions in the 
    PSD and nonattainment NSR regulations. As a result, the 27th category 
    will read as follows:
    
        Any other stationary source category which, as of August 7, 
    1980, is being regulated under section 111 or 112 of the Act.
    
    Use of the above language best ensures that, until EPA is prepared to 
    finalize part 70's proposed revisions, there will be no discrepancy 
    between the treatment of fugitive emissions under PSD and nonattainment 
    NSR and the corresponding provision in this phase I part 71 rule. This 
    language further ensures that sources which are considered major 
    sources under PSD and nonattainment NSR are also major sources under 
    part 71. This consistency is compelled by section 501(2) which requires 
    any stationary source to be considered major under title V if it is a 
    major source under section 112 or a major stationary source under 
    section 302 or part D of title I.
        It is important to remember that EPA has proposed additional 
    modifications to the list of source categories, including this 27th 
    category, in the August 1995 proposal for parts 70 and 71. However, as 
    EPA is currently in the process of reviewing and evaluating comments 
    regarding these revisions, EPA cannot at this time finalize any of 
    these proposed modifications.
        The EPA stresses that the definition of major source in today's 
    rulemaking does not constitute a decision to reject other proposed 
    changes to the term contained in the recent proposals. Rather, EPA 
    expects the Phase II part 71 rulemaking to make whatever changes to the 
    term are necessary in order to maintain harmonization with part 70, if 
    the part 70 definition of major source is ultimately revised as the 
    Agency intends. In the meantime, however, in order to avoid delay in 
    fulfilling the Agency's responsibilities under title V, and in order to 
    avoid repeating a procedural mistake that occurred in the development 
    of the first part 70 rule, EPA has concluded, in response to the 
    commenters, that at this point it is most reasonable to promulgate a 
    definition that is consistent with the major source definition 
    contained in the current part 70 rule, except for the 27th category of 
    sources listed pursuant to section 302(j). As EPA has already told 
    States that they may receive interim approval of their State programs 
    even if they do not literally match with current part 70's 27th 
    category, due to EPA's concession that the Agency did not take the 
    procedural steps necessary in part 70 to constitute a section 302(j) 
    rulemaking, EPA believes it is reasonable to take this limited 
    departure from part 70. The EPA will respond to specific comments on
    
    [[Page 34211]]
    
    the major source definition as proposed in April 1995 and August 1995 
    in the context of finalizing the Phase II part 71 rule.
    5. Permit Modification and Permit Revision
        For the purposes of this rulemaking, EPA adopted the definition of 
    permit modification in the current part 70 regulation and revised the 
    definition of ``permit revision'' to be consistent with the current 
    part 70 definition.
    6. Permitting Authority
        The final rule changes the proposed definition of ``permitting 
    authority'' to more closely match the definition of the term currently 
    promulgated at section 70.2.
    7. Potential to Emit
        Today's rule does not include a final regulatory definition of the 
    term ``potential to emit.'' The part 71 proposal contained a proposed 
    definition of potential to emit that was based on the August 1994 
    proposed revisions to part 70. The current part 70 definition of the 
    term provides that physical or operational limits on a source's 
    capacity to emit an air pollutant shall be considered part of the 
    source's design if the limitation is enforceable by the Administrator. 
    Under the proposed definition, the phrase ``and by citizens under the 
    Act'' would have been added. The EPA is still in the process of 
    evaluating comments on the proposed revisions to part 70 with respect 
    to this issue, and is not yet prepared to adopt the revision to the 
    definition into a final rule. Consequently, it is premature to adopt 
    this change into the final part 71 rule at this time.
        In addition, EPA also received substantial adverse comment on the 
    proposed requirement that limitations on potential to emit be 
    enforceable by the Administrator (i.e., ``federally enforceable''). 
    Industry commenters noted that EPA's policy on Federal enforceability 
    was the subject of several pending lawsuits against the Agency in the 
    Court of Appeals. These commenters have long held that emissions 
    limitations enforceable under State law should not have to be federally 
    enforceable in order to be considered part of a source's physical or 
    operational design and a valid limit on potential to emit. These 
    commenters also urged EPA to codify the Agency's January 25, 1995, 
    memorandum in which EPA stated it would not require certain sources 
    that otherwise have the potential to emit an air pollutant in major 
    amounts to obtain permits under state part 70 programs. See, memorandum 
    of January 25, 1995, entitled ``Options for Limiting the Potential to 
    Emit (PTE) of a Stationary Source Under Section 112 and Title V of the 
    Clean Air Act (Act),'' from John Seitz, Director, Office of Air Quality 
    Planning and Standards, to Regional Air Division Directors (hereafter 
    ``January 25, 1995 memorandum from John Seitz'').
        Since the close of the comment period, the U.S. Court of Appeals 
    for the District of Columbia Circuit has ruled on two occasions that 
    EPA in two separate regulations had failed to explain why the Agency 
    had adopted a restrictive interpretation of ``potential to emit.'' See 
    National Mining Association v. EPA, 59 F.3d 1351 (D.C. Cir. July 21, 
    1995), and Chemical Manufacturers Association v. EPA, No. 89-1514 (D.C. 
    Cir. Sept. 15, 1995). In response to these rulings, EPA has begun a 
    rulemaking effort that would consistently apply to all of its 
    regulations and programs that base applicability on sources' potential 
    to emit. This rulemaking will address potential to emit not only in the 
    regulations that were the subject of the two court rulings (EPA's 
    ``General Provisions'' regulations under section 112 of the Act 
    promulgated at 40 CFR part 63, and the NSR and PSD regulations at parts 
    51 and 52), but also to parts 70 and 71.
        In the meantime, however, the Agency believes it would not be 
    appropriate to delay issuance of the part 71 regulation (and 
    implementation of the Federal operating permit program in States that 
    have not yet obtained part 70 approval) due to the pendency of the 
    Agency's general potential to emit rulemaking. At the same time, EPA 
    does not believe it would be appropriate to merely recodify the part 70 
    definition of potential to emit in this Phase I part 71 rule, in light 
    of the recent court decisions concerning the section 112 and NSR and 
    PSD regulations. Consequently, for this interim part 71 rule, EPA is 
    not adopting a regulatory definition of potential to emit for purposes 
    of part 71. This definition will be added to part 71 at a later time, 
    when the Agency completes its general rulemaking to define potential to 
    emit for its various stationary source programs under the Act.
        Nevertheless, the absence of a regulatory definition of potential 
    to emit in today's rule should not prevent sources from being able to 
    determine whether they are subject to the part 71 program because they 
    are major sources. The EPA stresses that the term ``major source'' is 
    already defined as a statutory matter in title V at section 501(2) of 
    the Act to mean a major source as defined in section 112 and a major 
    stationary source as defined in section 302 or part D of title I of the 
    Act. Moreover, the definition of major source adopted today also tracks 
    these statutory provisions, and, as discussed in the recent memorandum 
    entitled ``Interim Policy on Federal Enforceability Requirement for 
    Limitations on Potential to Emit,'' from John Seitz, Director, Office 
    of Air Quality Planning and Standards (hereafter January 22, 1996 
    memorandum from John Seitz), most current regulatory requirements and 
    policies regarding potential to emit, including the interim policy 
    discussed in the January 25, 1995 Seitz memorandum, remain in effect 
    while EPA conducts expedited rulemaking to address these issues in 
    detail. Consequently, in determining whether a source is major, the 
    part 71 permitting authority and source operator should look to the 
    regulatory definition of major source adopted in today's rule and the 
    statutory definitions in section 112, section 302, and part D of title 
    I (as those provisions are implemented by applicable regulations 
    thereunder) as controlling for purposes of this Phase I part 71 rule.
        In National Mining Association v. EPA, 59 F.3d 1351 (D.C. Cir. July 
    21, 1995), the Court dealt with the potential to emit definition under 
    the hazardous air pollutant programs promulgated pursuant to section 
    112. In this decision, the Court agreed with EPA that only 
    ``effective'' State-issued controls should be cognizable in limiting 
    potential to emit. In addition, the Court did not question the validity 
    of current federally enforceable mechanisms in limiting potential to 
    emit. However, the Court found that EPA had not adequately explained 
    why only federally enforceable measures should be considered in 
    assessing the effectiveness of State-issued controls. Accordingly, the 
    Court remanded the section 112 General Provisions regulation to EPA for 
    further proceedings. Thus, EPA must either provide a better explanation 
    as to why Federal enforceability promotes the effectiveness of State 
    controls, or remove the exclusive Federal enforceability requirement. 
    The Court did not vacate the section 112 regulations, and they remain 
    in effect pending completion of EPA rulemaking proceedings in response 
    to the Court's remand.
        The EPA reiterates that independent from the decision in National 
    Mining, current EPA policy already recognizes State-enforceable 
    potential to emit limits under section 112 and title V in many 
    circumstances under the
    
    [[Page 34212]]
    
    transition policy discussed in the January 25, 1995 John Seitz 
    memorandum, as recently revised by the January 22, 1996 John Seitz 
    memorandum. In recognition of the absence in some States of suitable 
    federally enforceable mechanisms to limit potential to emit applicable 
    to sources that might otherwise be subject to section 112 major source 
    requirements or to title V, EPA's policy provides for the consideration 
    of State-enforceable limits as a gap-filling measure during a 
    transition period that extends until January 1997. Under this policy, 
    restrictions contained in State permits issued to sources that actually 
    emit more than 50 percent, but less than 100 percent, of a relevant 
    major source threshold are treated by EPA as acceptable limits on 
    potential to emit, provided that the permit and the restriction in 
    particular are enforceable as a practical matter. In addition, sources 
    with consistently low levels of actual emissions relative to major 
    source thresholds can avoid section 112 major source requirements even 
    absent any permit or other enforceable limit on potential to emit. 
    Specifically, the policy provides that sources which maintain their 
    emissions at levels that do not exceed 50 percent of any applicable 
    major source threshold are not treated as major sources and do not need 
    a permit to limit potential to emit, so long as they maintain adequate 
    records to demonstrate that the 50 percent level is not exceeded.
        Under today's Phase I part 71 rule, sources that are not treated as 
    major under this policy would also not be treated as major for purposes 
    of part 71. However, if a source would be treated as major under the 
    applicable regulations implementing section 112 and this policy, the 
    source would be required to obtain a part 71 permit. The EPA notes that 
    this policy is to end in January 1997. In conjunction with the general 
    rulemaking on potential to emit, EPA will consider whether it is 
    appropriate to extend the transition period beyond January 1997.
        In Chemical Manufacturers Association v. EPA, No. 89-1514 (D.C. 
    Cir. Sept. 15, 1995), the Court addressed the potential to emit 
    definition in the PSD and NSR programs. Specifically, this case 
    challenged the June 1989 rulemaking in which EPA reaffirmed the 
    requirement for Federal enforceability of potential to emit limits 
    taken to avoid major source permitting requirements in these programs. 
    In a briefly worded judgment, the Court, in light of National Mining, 
    remanded the PSD and NSR regulations to EPA. In addition, in contrast 
    to its disposition of the section 112 regulations in National Mining, 
    the Court in Chemical Manufacturers vacated the federal enforceability 
    requirement of the potential to emit definitions in the PSD and NSR 
    regulations.
        The EPA interprets the Court's decision to vacate the PSD/NSR 
    Federal enforceability requirement as causing an immediate change in 
    how EPA regulations should be read, although EPA expects that the 
    effect of this change will be limited. Specifically, regarding 
    provisions of the definitions of potential to emit and related 
    definitions requiring that physical or operational changes or 
    limitations be ``federally enforceable'' to be taken into account in 
    determining PSD/NSR applicability, the term ``federally enforceable'' 
    should now be read to mean ``federally enforceable or legally and 
    practically enforceable by a State or local air pollution control 
    agency.''
        However, the effects of the vacatur will be limited during the 
    period prior to completion of new EPA rulemaking on this issue. Thus, 
    during this interim period, Federal enforceability is still required to 
    create ``synthetic minor'' new and modified sources in most 
    circumstances pending completion of EPA rulemaking. This is because EPA 
    interprets the order vacating certain provisions of the PSD/NSR 
    regulations as not affecting the provisions of any current State or 
    Federal implementation plan (SIP or FIP), or of any permit issued under 
    any current SIP or FIP. Thus, previously issued federally enforceable 
    permits issued under such programs remain in effect.
        Moreover, new or modified sources that seek to lawfully avoid 
    compliance with the major source requirements of PSD or nonattainment 
    NSR by limiting potential to emit to achieve synthetic minor status 
    must still obtain a general or ``minor'' NSR preconstruction permit 
    under section 110(a)(2)(C) of the Act and 40 CFR section 52.23. (This 
    requirement was not at issue in the Chemical Manufacturers case, and is 
    unaffected by the Court's ruling.) Every SIP contains a minor NSR 
    program that applies generally to new or modified sources of air 
    pollutants, and permits issued under such programs are, like all other 
    SIP measures, federally enforceable. In sum, the precise impact of the 
    vacatur on PSD/NSR applicability in any State, and hence the 
    applicability of part 71 under the section 302 and part D of title I 
    prongs of the definition of major source adopted in part 71, can be 
    definitively established only by reviewing the provisions of the 
    particular SIP or FIP to which the source is subject.
    8. Regulated Air Pollutant
        In the August 1995 supplemental proposal, EPA proposed a less 
    inclusive definition than is currently promulgated in part 70 or was 
    proposed for part 71 in the April 1995 notice. However, for purposes of 
    today's rulemaking, EPA is retaining the definition in the part 71 
    proposal, which is consistent with the current part 70 definition. The 
    EPA intends to take final action on the term as proposed in the 
    supplemental proposal in the Phase II rulemaking.
    9. Responsible Official
        Although EPA has proposed, in the August 1994 proposed revisions to 
    part 70, to clarify that the criteria for selecting the designated 
    representative is the same at an affected source as at other sources, 
    the Agency has adopted a definition of this term for purposes of 
    today's rulemaking that is consistent with the definition in current 
    part 70. The EPA will take final action in Phase II consistent with the 
    Agency's final resolution of this issue in response to comments on the 
    August 1994 notice.
    10. Section 502(b)(10) Changes
        The part 71 proposal, in omitting the definition of ``section 
    502(b)(10) changes'' from section 71.2, followed the approach used in 
    the August 1994 proposed revisions to part 70. The Agency's reasons for 
    the omission are articulated in that proposal at 59 FR 44467-8. As 
    indicated in the August 1995 supplemental proposal, this is still the 
    Agency position. However, EPA will not adopt a final position on 
    proposed revisions regarding operational flexibility for part 70 or 71 
    until the Phase II rulemaking. For purposes of today's rulemaking, EPA 
    has adopted a definition of the section 502(b)(10) changes that 
    comports with the current part 70 regulation, in order to better 
    harmonize the Phase I part 71 rule and the current part 70 regulation.
    11. Title I Modification
        The part 71 proposal, based on the August 1994 proposed revision to 
    part 70, contained a proposed definition of the phrase ``Title I 
    modification or modification under any provision of title I of the 
    Act.'' Subsequently, EPA issued a revised proposed definition in the 
    August 1995 supplemental proposal for parts 70 and 71. The EPA is in 
    the process of reviewing and developing a position in response to the 
    comments on the several proposals with respect to this issue, and is 
    not yet prepared to define the term in a final rule. The EPA will add a 
    definition in the Phase II rulemaking that is consistent with how
    
    [[Page 34213]]
    
    EPA ultimately defines the term under part 70.
        A detailed discussion of the history of this definition is 
    contained in the preamble to the August 1995 part 70 proposal (60 FR 
    45545). At issue is whether the phrase ``modifications under any 
    provision of title I'' as used in section 502(b)(10) of the Act 
    includes not only modifications subject to major NSR requirements of 
    parts C and D of title I but also modifications subject to minor NSR 
    programs established by the States pursuant to section 110(a)(2)(C).
        In August 1994, EPA proposed to interpret the title I modification 
    language of part 70 to include minor as well as major NSR modifications 
    (55 FR 44527). The EPA received many comments from industry and States 
    contesting this interpretation. The commenters argued that EPA had 
    defined title I modification in the preamble to the May 1991 proposed 
    part 70 rule to exclude minor NSR (56 FR 21746-47 and footnote 6) and 
    did not redefine it in the final July 1992 rule. As a result, they 
    argued that they were relying on the current rule to be interpreted 
    consistent with the proposed rule preamble and that EPA could not 
    change its interpretation without undertaking further rulemaking.
        Based in part on the arguments raised by commenters, EPA revised 
    its proposed interpretation of the definition of title I modification 
    in the August 1995 supplemental notice to exclude modifications subject 
    to minor NSR. In addition, EPA proposed regulatory language defining 
    title I modification which excluded the reference to section 110(a)(2) 
    of the Act.
        While EPA is not yet prepared to adopt a final definition for the 
    term, in implementing the Phase I part 71 program EPA will treat the 
    issue consistently with the approach the Agency has advised States to 
    take under the current part 70 regulation. Consequently, it will not 
    consider title I modifications to include changes subject to State 
    minor NSR programs.
    
    B. Section 71.3--Sources Subject to Permitting Requirements
    
        The final rule promulgates provisions regarding applicability of 
    the program at section 71.3. These provisions are based on their 
    counterparts in the currently promulgated part 70 rule at section 70.3. 
    Consequently, in several aspects, they differ from section 71.3 as 
    proposed, which was based on the August 1994 proposed revisions to 
    section 70.3 which the Agency is not yet prepared to finalize.
        Paragraph (a)(1) of the part 71 proposal contained an exemption 
    from title V for major sources that would be subject to title V only if 
    they have the potential to accidentally release pollutants listed 
    pursuant to section 112(r)(3) in major amounts. This exemption has been 
    deleted, even though it garnered reviewer support, consistent with the 
    decision to match the part 70 requirements except where unique 
    circumstances make a change necessary. If EPA ultimately revises part 
    70 to add the deleted language, the Agency would intend to revise part 
    71 consistently.
        Proposed section 71.3(a)(4) which was modelled upon the August 1994 
    proposed revisions to part 70 and would have stated that any source 
    subject to title I parts C or D would be required to obtain a permit 
    was also deleted from the final regulation to comport with the part 70 
    regulation. The purpose of this provision was to ensure that all 
    sources subject to preconstruction permitting as major sources under 
    parts C or D of the Act are also subject to title V permitting. Again, 
    if part 70 is ultimately revised to add this provision, EPA would 
    intend to revise part 71 to add it as well.
        Similarly, paragraph (b)(2) has been changed to conform with 
    section 70.3(b)(2), which addresses applicability for sources subject 
    to section 111 or 112 standards promulgated after July 21, 1992. 
    Proposed section 71.3(b)(2) differed from both existing section 
    70.3(b)(2) and the August 1994 proposed revisions thereto. If section 
    70.3(b)(2) is ultimately revised, EPA would expect to revise section 
    71.3(b)(2) to harmonize it with part 70.
        Paragraphs (c) and (d) of this section, found in the proposal at 
    sections 71.6(a)(1)(iv) and 71.5(f)(3)(i), respectively, were moved to 
    this section for compatibility with the current part 70 provisions at 
    sections 70.3 (c) and (d).
    
    C. Section 71.4--Program Implementation
    
        The major issues raised by commenters on proposed section 71.4 
    related to the need to base part 71 on finalized (as opposed to 
    proposed) provisions of part 70, how the part 71 program should be 
    customized to fit the unique needs of the State or area for which the 
    program is administered, and jurisdictional issues with respect to 
    programs on Tribal lands. The Agency's approach to the first issue is 
    discussed at length in section II of this document. This section 
    addresses the second and third issues in addition to several minor 
    changes to the proposed rule that were adopted today.
    1. National Template Approach
        With respect to the second issue, EPA received divergent comments. 
    For example, commenters suggested that a national template should be 
    flexible, that a national template should be used only to fill in the 
    gaps of deficient State programs, and that there should be no national 
    template because title V does not authorize EPA to develop such a rule.
        The Agency carefully considered the statutory framework for the 
    program and interprets title V as authorizing a national template 
    approach. For a further discussion of this issue, see section II of 
    this document. The EPA chose a national template approach because EPA 
    believes the national template is flexible enough to be an effective 
    program in nearly all areas, and individual rulemakings for each area 
    that has a part 71 program would be needlessly burdensome on the 
    Agency. Since the national template will serve the needs of most areas, 
    it is more efficient to promulgate the program once while allowing for 
    separate rulemakings, as needed, in some areas. The EPA recognizes the 
    desirability of providing a flexible approach to administering the 
    program, as the commenters have suggested, when the national template 
    does not adequately fit the unique State or Tribal situation. Such 
    flexibility is already contained in section 71.4. When EPA determines 
    that the national template rule is not appropriate for a State, EPA may 
    adopt, through a separate rulemaking, appropriate portions of a State 
    or Tribal program in combination with provisions of part 71 in order to 
    craft a suitable part 71 program, as provided in section 71.4(f). 
    Furthermore, section 71.9(c)(7) provides that when the national fee 
    structure would not reflect the cost of administering a part 71 
    program, the Administrator shall through a separate rulemaking set an 
    appropriate fee. Finally, as provided in section 71.5 and as discussed 
    in section III.D of this document, EPA has designed part 71 to provide 
    significant flexibility to accommodate the localized air quality 
    issues. For example, EPA will use State application forms whenever 
    possible and will try to match the list of trivial activities which may 
    be left off application forms to the lists established in the State 
    operating permit program.
    2. Part 71 Programs in Tribal Areas
        The EPA is deferring promulgation of regulations that would 
    describe how the Agency would determine the boundaries of a part 71 
    program for a
    
    [[Page 34214]]
    
    Tribal area. The EPA has published a proposed rule, pursuant to section 
    301(d)(2) of the Act, specifying the provisions of the Act for which 
    EPA believes it is appropriate to treat Indian Tribes in the same 
    manner as States and outlining the Agency's position on the authority 
    of Indian Tribes to administer air programs under the Act. See 59 FR 
    43956 (Aug. 25, 1994)(``Indian Tribes: Air Quality Planning and 
    Management,'' hereafter ``proposed Tribal rule''). As indicated in the 
    part 71 proposal, EPA intends to follow the approach of the Tribal rule 
    with respect to issues of jurisdiction and resolution of jurisdictional 
    disputes. The EPA agrees that it would be more practical to defer 
    addressing jurisdictional issues until the promulgation of the Tribal 
    rule. The Agency will finalize an approach to jurisdiction as well as a 
    definition of Tribal area in the Phase II rulemaking or in conjunction 
    with finalizing the Tribal rule. In the interim, the Agency will not be 
    able to implement part 71 programs in Tribal areas unless it completes 
    a rulemaking that establishes the boundaries of the part 71 program in 
    the Tribal area. Rulemakings for the Tribal rule and Phase II will be 
    completed well in advance of the November 1997 deadline for EPA to 
    implement part 71 programs on Tribal lands. Therefore, EPA does not 
    expect that the deferral of jurisdictional issues will delay 
    implementation of the part 71 program. Although part 71 contains no 
    definition of ``Tribal area,'' EPA will provide (and will require 
    delegate agencies to provide) notice of proposed permitting actions 
    pursuant to section 71.8(d) even prior to the Phase II rulemaking. In 
    the interim, federally recognized Indian Tribes will receive notice 
    with respect to permitting actions related to sources whose emissions 
    may affect Tribal air quality and that are located in contiguous 
    jurisdictions or are within 50 miles of the exterior boundaries of the 
    reservation.
    3. Expiration of Part 71 Permits
        The Agency received comments suggesting that part 71 permits should 
    be rescinded automatically, without the Agency taking any action, when 
    they are replaced by a part 70 permit. The EPA agrees that no separate 
    agency action should be required when a part 71 permit is replaced by a 
    part 70 permit issued under the approved part 70 program because unless 
    the rescission happens simultaneously with the issuance of the part 70 
    permit, a source could be subject to a part 70 and a part 71 permit 
    which may contain different requirements. Accordingly, EPA has deleted 
    proposed section 71.4(l)(3) which provided that the Administrator would 
    rescind part 71 permits when they were replaced with part 70 permits. 
    Further, the EPA has adopted section 71.6(a)(11) which provides that 
    part 71 permits shall contain a provision to ensure that a part 71 
    permit will expire when the source is issued a part 70 permit.
    4. Suspension of Issuance of Part 71 Permits
        The EPA revised the first paragraph of proposed section 71.4(l) to 
    clarify, consistent with EPA's original intent, that EPA may suspend 
    issuance of part 71 permits whenever the Agency has granted full or 
    interim approval to a State part 70 program. Section 502(e), which 
    addresses suspension of the issuance of part 71 permits, provides that 
    the triggering event for suspension is publication of notice of 
    approval. Thus, there is no statutory requirement that a State program 
    must ``fully'' meet the requirements of part 70 or be fully approvable 
    in order for EPA to suspend permit issuance. The Agency believes it is 
    appropriate to suspend issuance of part 71 permits when a State program 
    substantially meets the requirements of part 70 and has received 
    interim approval because it would be confusing and burdensome to have 
    two title V permit programs operating simultaneously in the same 
    jurisdiction. Therefore, EPA has deleted the word ``fully'' from the 
    first paragraph of proposed section 71.4(l).
    5. Delegation Agreements
        The final rule makes a minor change to proposed section 71.4(j) in 
    parallel with a change to proposed section 71.10(b) to reflect the fact 
    that under the final rule, EPA will not publish its delegation 
    agreement with a delegate agency. Therefore, section 71.4(j) provides 
    that the roles of the delegate agency and EPA in administering the part 
    71 program will be defined in a delegation agreement, not in a Federal 
    Register notice. The EPA will follow the procedures for delegation 
    agreements established for the PSD program under which EPA does not 
    publish its delegation agreements. Delegation agreements reflect the 
    understanding of EPA and the delegate agency as to their respective 
    responsibilities and are not subject to any notice requirement. This 
    approach allows EPA and the delegate agency to modify their agreement 
    as circumstances change, without the burden of publishing a Federal 
    Register notice.
    6. Early Reductions Permits
        The Agency retained in section 71.4(i)(3) the requirement that the 
    permitting authority take action on complete permit applications 
    containing an early reduction demonstration within 12 months of receipt 
    of the complete application. Although the current part 70 regulation 
    sets a 9 month deadline for State action, EPA Regional offices are 
    allowed 12 months to take action on the permit applications submitted 
    under the interim permitting rule for early reduction sources that EPA 
    adopted prior to the approval of any State part 70 programs. See 40 CFR 
    section 71.26(a)(2). The Agency believes that this time frame is 
    reasonable given the effort required to process the permits and the 
    need for sources qualifying for a compliance extension under the Early 
    Reductions Rule to obtain a permit prior to certain deadlines set by 
    the rule.
    
    D. Section 71.5--Permit Applications
    
        The part 71 proposal addressed permit applications at proposed 
    section 71.5 (a) through (i). This proposed section was based upon a 
    combination of corresponding provisions in the existing part 70 rule 
    and in the August 1994 proposed revisions to part 70, and was presented 
    in a slightly different structure from the part 70 rule. In light of 
    EPA's decision to promulgate part 71 on an interim basis, more 
    consistently with the existing part 70 rule, the provisions based upon 
    the August 1994 proposal are not being adopted today. Moreover, in 
    order to facilitate transition from implementing part 71 to part 70 
    programs, the final rule is being adopted in a structure that is more 
    consistent with that of the current part 70 rule.
    1. Timely Application
        Under section 71.5(b)(1) of the proposal all initial permit 
    applications would have to be submitted within 12 months or an earlier 
    date after the source becomes subject to part 71. The proposal would 
    have required that the permitting authority provide notice of the 
    earlier date to the source and that this notice would be given at least 
    120 days in advance of the application submittal date.
        Several commenters argued that the 120 days (4 months) minimum 
    notice would not give sources sufficient time to prepare an 
    application. They also argued that 4 months was insufficient time for 
    sources to submit their applications early for purposes of addressing 
    deficiencies and ensuring they receive the application shield.
        In response to these comments, EPA has lengthened the notice period 
    from 4
    
    [[Page 34215]]
    
    months to 6 months. Section 503(c) of the Act requires the submittal of 
    all applications within 12 months of the effective date of a permit 
    program or such earlier date as the permitting authority may establish 
    and that one-third of these applicants be issued permits in this first 
    year. In order to issue one-third of the permits in the first year, EPA 
    must receive at least one-third of the applications prior to 12 months 
    after the effective date of the program.
        The EPA considered and rejected commenters' suggestions for 8 to 12 
    months' advance notice because they would interfere with EPA's 
    requirement to issue one-third of the permits in the first year. The 
    EPA believes that the 6 month alternative will allow EPA enough time to 
    process and issue permits. The EPA believes that 6 months is sufficient 
    time for sources to prepare applications for several reasons that had 
    not been announced at time of proposal. First, on July 10, 1995, EPA 
    issued the first white paper that examines options for simplifying part 
    70 permit applications and sets minimum expectations concerning how 
    much information must be included in order for the application to be 
    found complete. In today's notice EPA announces its intention to 
    implement both of the white papers for part 71 program purposes. 
    Second, EPA has revised the rule to clarify that part 71 permit 
    application forms may be developed by the delegate agency or the EPA 
    allowing a part 71 application form to be based on a State form 
    developed for part 70 purposes, as long as the form meets the minimum 
    requirements of part 71 (discussed in more detail below). Third, 
    because the final rule more closely follows the part 70 program upon 
    which most State operating programs are based, sources will be familiar 
    with most part 71 permit application requirements.
        In addition, proposed sections 71.5(b) (2) and (3) have been 
    deleted because they referred to off-permit changes and a four-track 
    permit revision system which the Agency is not finalizing today.
    2. Complete Applications
        The final rule adopts the language from the current part 70 rule 
    concerning complete applications. However, EPA believes that several 
    clarifications will help applicants understand the flexibility 
    available for submitting simplified permit applications that can be 
    found complete. The terms ``simplified permit application'' or 
    ``streamlined permit application'' refer to applications that require 
    less information.
        In the part 71 proposal, EPA proposed to adopt language from the 
    August 29, 1994 part 70 revision notice (59 FR 44518) that would have 
    clarified that an application would be found complete if it contained 
    information ``sufficient to begin processing the application.'' As 
    stated previously, today's rulemaking is based on provisions of current 
    part 70; therefore, this language does not appear in today's 
    rulemaking. However, EPA believes, as stated more fully in the first 
    white paper, that considerable flexibility already exists in the part 
    70 rule to find simplified permit applications complete. Since the 
    white papers will be implemented for part 71 purposes, this flexibility 
    also exists in the part 71 permit program.
        Furthermore, the proposed revisions to part 70 (August 29, 1994) 
    and the part 71 proposal discussed several additional options currently 
    available to States for developing simplified permit applications and 
    finding them complete, and did not propose any rule changes necessary 
    to implement these options. These options were: (1) a two-step 
    application completeness determination process for simplified 
    applications and (2) simplified application content requirements for 
    applicable requirements with future compliance dates. After the 
    publication of these proposal notices, the first white paper included 
    these two flexibility options, as well as many additional options, and 
    reaffirmed EPA's interpretation that implementation of these options 
    does not depend on making changes to the part 70 rule or State part 70 
    programs.
        The EPA believes this approach will provide flexibility for sources 
    to prepare simplified permit applications and for permitting 
    authorities to find them complete. This approach will also promote 
    consistency between the part 71 and part 70 programs, which in turn, 
    will provide for a smoother transition between the programs. Guidance 
    on the implementation of the white papers and other flexibility options 
    for completeness determinations for a part 71 program implemented in a 
    particular State may be provided by the EPA or delegate agency soon 
    after the program takes effect.
        Additionally, proposed section 71.5(d), concerning the treatment of 
    business confidential information, has been revised in the final rule. 
    The language of the proposal discussed the responsibilities of 
    permitting authorities to process requests for confidential treatment 
    and included a general reference to 40 CFR part 2. Considering the 
    structure of these regulations and this section's position in these 
    regulations, the Agency believes that the promulgated language 
    clarifies the procedures that applicants must follow to request 
    confidential treatment for business information in applications, 
    provides a more precise cross-reference to those procedures, and does 
    not add any new requirements regarding the treatment of confidential 
    information not intended by the proposal.
        Note also that certain technical changes are being made to part 
    71's completeness provisions as a result of the final rule's greater 
    harmonization with the existing part 70 rule. First, the completeness 
    criteria are being promulgated at section 71.5(a)(2) while the proposal 
    addressed completeness at section 71.5(c). In addition, the final rule 
    references section 71.5(c) as the provision setting out required 
    information in permit applications, while the proposal referenced 
    proposed section 71.5(f). Moreover, the final rule cites section 
    71.5(d) as the provision concerning certification by a responsible 
    official, while the proposal cited proposed section 71.5(i). Finally, 
    the citation in the proposal to section 71.7(a)(3) has been changed in 
    the final rule to section 71.7(c)(4) as a result of the changes to 
    section 71.7.
    3. Standard Application Form and Required Application
        Proposed section 71.5(f) would have required part 71 sources to 
    submit ``applications provided by the permitting authority, or if 
    provided by the permitting authority, an electronic reporting method'' 
    and did not include any preamble discussion of the interpretation of 
    this phase. One commenter on the proposal encouraged EPA to use 
    existing State forms in States where EPA assumes part 71 authority. 
    Final section 71.5(c) has been revised to more closely follow the 
    corresponding language of section 70.5(c). The EPA agrees with the 
    commenter and will provide forms developed by delegate agencies 
    (States), or the EPA, including electronic application methods, for 
    purposes of applying for part 71 permits. This approach to application 
    development is possible because ``permitting authority'' is defined in 
    section 71.2 as including the EPA or the delegate agency. This approach 
    to providing part 71 forms will lead to less disruption and a smoother 
    transition for sources preparing initial part 71 applications because, 
    in many cases, sources will be familiar with the State form on which 
    the part 71 form is based. For example, sources may already be 
    collecting information and drafting an operating permit using the State 
    form in expectation of part 70 program approval by EPA. In addition, 
    commenters asked
    
    [[Page 34216]]
    
    that EPA clarify and simplify the requirements for emissions-related 
    information in part 71 applications consistent with EPA's guidance in 
    the first white paper. In response to these comments, EPA intends to 
    implement the white paper guidance with respect to the collection and 
    reporting of emission-related information and EPA believes that no 
    changes to part 71 are necessary to do so.
        Numerous technical changes have been made to the final rule 
    regarding information to be required in permit applications to better 
    match the current part 70 rule. In the proposal, information 
    requirements were addressed at proposed sections 71.5(f) through (i), 
    while the final rule follows part 70 by covering these requirements in 
    sections 71.5(c) and (d). New citations to other provisions of part 71 
    are also due to the final rule's harmonization with part 70.
    4. Insignificant Activities and Emission Levels
        Extensive comments were received on the proposed insignificant 
    activity and emission levels provisions of proposed section 71.5(g). 
    Commenters argued, in part, that activities subject to applicable 
    requirements should be eligible for the exemption for insignificant 
    activities and emission levels, that the requirement that applications 
    not exclude information needed to determine whether a source is subject 
    to the requirement to obtain a part 71 permit would be too restrictive, 
    that the list of insignificant activities in the final rule should be 
    expanded, that the list of trivial activities in the first white paper 
    should be codified in part 71, that the exemption for mobile sources as 
    insignificant activities should be removed, that the single emissions 
    unit emissions thresholds for insignificant emissions should be raised, 
    and that the aggregate source-wide emission thresholds for 
    insignificant emissions should be deleted.
        a. Eligibility for Insignificant Treatment and Information Required 
    in Applications. Section 71.5(c) of the final rule addresses, in part, 
    information that must not be omitted from permit applications. These 
    requirements have special relevance for applicants when determining 
    what information must be included in applications for emission units 
    that are eligible for insignificant treatment. To be consistent with 
    current part 70, final section 71.5(c) deletes certain proposed 
    provisions that do not follow the corresponding language of section 
    70.5(c) and that were based upon the proposed revisions to part 70 
    published in August 1994. Accordingly, deleted from final section 
    71.5(c) is the proposed language that would have not allowed the 
    application to omit information needed to: (1) Determine whether a 
    source is major, and (2) determine whether a source is subject to the 
    requirement to obtain a part 71 permit. Notwithstanding these 
    deletions, EPA continues to believe that the definition of major source 
    at section 71.2 controls the determination of which units are counted 
    for major source applicability purposes and that emissions of units 
    that qualify for insignificant treatment in the application are not 
    exempt from these determinations. Consistent with the Agency's approach 
    in implementing the current part 70 rule, the EPA is reversing its 
    interpretation, first expressed in the proposed preamble, that would 
    have excluded the eligibility of activities for treatment as 
    insignificant when such activities are subject to applicable 
    requirements. The EPA believes that no change to the final rule is 
    necessary to implement this new interpretation.
        Industry commenters were particularly concerned that EPA's 
    interpretation that proposed section 71.5(g) would not allow activities 
    with applicable requirements to be eligible for insignificant treatment 
    would render the insignificant activity and emissions level provisions 
    meaningless because few sources would be eligible for streamlined 
    treatment in the application.
        The EPA now believes that it was overly broad in stating that 
    emission units were precluded from eligibility as ``insignificant'' if 
    such units would be subject to applicable requirements. As discussed 
    below, EPA believes there are circumstances in which an emission unit 
    or activity can be treated as ``insignificant'' under a Federal 
    operating permits program, even if it is subject to an applicable 
    requirement. However, a title V application must still contain 
    information needed to determine the applicability of or to impose any 
    applicable requirement or any required fee and a permit must still meet 
    the requirements of section 71.6 for all emission units subject to 
    applicable requirements, including those eligible for insignificant 
    treatment.
        Both sections 71.5(c) and 71.5(c)(3)(i) require sufficient 
    information to verify the requirements applicable to the source and to 
    collect appropriate permit fees.
        This means that some of the information required by sections 
    71.5(c) (3) through (9) may be needed in the permit application for 
    insignificant activities in order for the permitting authority to draft 
    an adequate operating permit. As an example, where an insignificant 
    activity is not in compliance with an applicable requirement at the 
    time of permit issuance, the permit application would need to contain a 
    compliance plan, including a compliance schedule, for achieving 
    compliance with the applicable requirement. As another example, if a 
    source has some insignificant activities within a category that are 
    subject to an applicable requirement and some within that same category 
    that are not subject to that applicable requirement because the 
    applicability criteria for the applicable requirement are different 
    from the applicability criteria for insignificant activities, the 
    permit application would generally be required to include sufficient 
    information on the insignificant activity for the permitting authority 
    to determine which units are subject to the applicable requirement and 
    to include that applicable requirement in the permit for the subject 
    insignificant activity. The EPA believes that a part 71 permit 
    application may simply list the applicable requirements that apply to 
    insignificant activities generally, rather than requiring the permit 
    application to explicitly identify which insignificant activities are 
    subject to which applicable requirements. The permitting authority 
    would then issue a permit imposing the applicable requirements in the 
    permit, but not specifically identifying which insignificant activities 
    are subject to those applicable requirements. (For a more detailed 
    discussion, see the first white paper and the proposed interim approval 
    and proposed notice of correction for the State of Washington's part 70 
    program, 60 FR 50166 (September 28, 1995).)
        b. Insignificant Activity Lists. Section 70.5(c), in part, allows 
    States to develop lists of insignificant activities and emission levels 
    that need not be included in applications and requires activities (or 
    equipment) exempted due to size or production rate to be listed in the 
    application. State part 70 program submittals were approved by EPA that 
    implement this provision in a variety of ways. The structure of the 
    proposed regulations was based on the structure of these State 
    implementing regulations, and included a short list of insignificant 
    activities and provisions setting insignificant emissions levels. The 
    proposed list of insignificant activities, section 71.5(g)(1), included 
    a list of specific source categories, activities, or equipment that 
    could be left off the application. The proposed insignificant
    
    [[Page 34217]]
    
    emissions provisions, section 71.5(g)(ii), allowed sources the 
    flexibility to treat additional source categories, equipment, or 
    activities as insignificant, provided certain eligibility criteria were 
    met, including not exceeding certain emissions levels, and provided 
    that the activities were listed in the application. The EPA believed 
    that the proposed insignificant emissions approach was flexible enough 
    that extensive lists of insignificant activities would not be needed in 
    the final rule. The EPA reasoned that no list of insignificant 
    activities would ever be so inclusive as to list every type of activity 
    potentially eligible for insignificant treatment at industrial sources, 
    and therefore, additions to the list would require resource-intensive 
    notice and comment rulemaking on an ongoing basis. The proposal asked 
    for comment on its approach and asked whether the proposed approach 
    would be compatible with approaches developed by States.
        Numerous industry commenters argued, in general, that the proposed 
    part 71 list was not extensive enough to provide meaningful relief for 
    industry from the administrative burdens associated with submitting 
    detailed information for emission units or activities that pose little 
    or no environmental risk and that the part 71 list was not as extensive 
    as lists developed by States for their part 70 programs.
        The EPA is finalizing the proposed list of insignificant activities 
    with one revision. The EPA believes that the commenters' concerns that 
    there be more opportunities for streamlining the information required 
    by part 71 permit applications is best addressed by implementing the 
    white papers for part 71 purposes, and that no changes to the final 
    rule are necessary to implement this approach. The EPA believes that 
    the white papers provide for application streamlining that is 
    comparable and, in many ways, superior to approaches based on omitting 
    certain emission unit or activities from the application only when 
    eligibility for insignificant treatment is established in a rule. In 
    general, the white papers allow sources to provide little or no 
    detailed source-specific information for emissions units or activities 
    where the information is not reasonably available and to the extent the 
    information is not needed to resolve disputed questions of major source 
    status, applicability of requirements, compliance with applicable 
    requirements, or needed to calculate fees.
        For example, section B.3. Insignificant Activities of the first 
    white paper allows trivial activities to be completely omitted from 
    applications. The white paper defines trivial activities as activities 
    without specific applicable requirements (although they may have 
    ``generic'' applicable requirements, explained below) and with 
    extremely small emissions and included a list of trivial activities in 
    Appendix A. Many of the trivial activities identified in the first 
    white paper are common to State lists of insignificant activities. 
    Under part 71, sources may rely on this list, and EPA or the delegate 
    agency may add to it without the need for Federal rulemaking. This 
    allows EPA to expand the list of trivial activities for a part 71 
    program in a specific location, consistent with trivial activity lists 
    established in the State operating permit program, thus tailoring the 
    program for a specific program implemented in a State.
        Also providing considerable streamlining is section B.4 Generic 
    Grouping of Emission Units and Activities of the first white paper 
    which allows emissions units or activities with ``generic'' applicable 
    requirements to be omitted from the application, independent of 
    eligibility for insignificant treatment. Under this section, sources 
    may provide little or no detailed source-specific information, even for 
    units with ``generic'' requirements, provided that the ``generic'' 
    requirements are described in the application such that their scope and 
    manner of enforcement are clear. ``Generic'' requirements are certain 
    broadly applicable requirements that apply and are enforced in the same 
    manner for all subject units or activities and that are often found in 
    the SIP. Examples of such requirements include requirements that apply 
    identically to all emissions units at a facility (e.g., source-wide 
    opacity limits), general housekeeping requirements, and requirements 
    that apply identical emissions limits to small units (e.g., certain 
    process weight requirements). Where the applicable requirement is 
    amenable to this approach, part 71 permitting authorities may follow 
    this approach regardless of whether subject activities have been listed 
    as trivial or insignificant. A lengthy list of the types of 
    requirements suitable for this treatment is not possible here because, 
    among other reasons, the examples of which EPA is aware are SIP 
    requirements, and so vary from State to State. The EPA or delegate 
    agency will decide which SIP requirements can be treated in this 
    generic fashion for specific locations where part 71 programs are 
    implemented.
        The EPA has determined that the insignificant activity exemption 
    for air-conditioning units used for human comfort at final section 
    71.5(c)(11)(i)(B) should be changed to clarify that substances other 
    than class I or II substances may be regulated under title VI of the 
    Act. This change is necessary because effective November 15, 1995, 
    title VI requires recycling or recovery of substitute refrigerants 
    regardless of whether or not they are ozone depleting substances (Class 
    I and Class II substances) unless EPA makes a refrigerant-specific 
    decision that the substitute will not harm human health or the 
    environment and can, therefore, be vented.
        c. Insignificant Emissions Levels. In response to comments, EPA has 
    revised proposed section 71.5(g)(2)(i), which is section 
    71.5(c)(11)(ii)(A) of the final rule, to increase the insignificant 
    emissions threshold for regulated air pollutants other than (HAP) from 
    a single emissions unit from 1 tpy to 2 tpy and to delete the 1,000 
    pounds (lb) per year threshold in extreme ozone nonattainment areas. 
    The EPA believes this decision is appropriate since, as commenters 
    pointed out, EPA has previously stated in part 70 approval notices that 
    insignificant emissions thresholds set at 2 tpy would be approvable in 
    most locations. The EPA believes that due to the similarity between 
    part 70 and part 71 programs it can logically conclude that this level 
    is also appropriate for a part 71 program, regardless of where it is 
    located. This level will provide a measure of additional flexibility 
    for sources to exempt insignificant activities, thus simplifying the 
    application, with little additional risk that significant emission 
    units will be excluded from the application. As further discussed 
    below, there are several safeguards available in the final rule that 
    should ensure that significant units are not excluded from applications 
    due to their eligibility for insignificant treatment. In addition, EPA 
    is deleting the proposed 1,000 lb per year threshold for extreme ozone 
    nonattainment areas. This will simplify the rule by setting the same 
    tpy emission thresholds for attainment and nonattainment pollutants, 
    while requiring the thresholds in relative terms to be no more than 20 
    percent of the major source threshold for nitrogen oxides and VOC and 2 
    percent of the major source threshold for the remaining criteria 
    pollutants. Two tpy is considered trivial by EPA for all pollutants 
    other than HAP in relation to major source thresholds in all attainment 
    or
    
    [[Page 34218]]
    
    nonattainment areas and will not prevent the EPA from collecting 
    information of a consequential or significant nature. In addition, 
    these levels are more commonly found in State part 70 programs and 
    therefore should help to ease the transition from part 71 to part 70 
    operating permit programs.
        In response to comments, EPA has decided to delete the aggregate 
    source-wide emissions criteria for insignificant emissions of regulated 
    air pollutants (sections 71.5(c)(11)(ii) (A) and (B) of the final 
    rule). The EPA proposed these aggregate source-wide emissions criteria 
    as an additional means to ensure that emissions that might otherwise 
    trigger the applicability of applicable requirements or major source 
    status would not be excluded from applications. However, EPA now 
    believes that the proposed aggregate emissions thresholds would have 
    significantly limited the value of the insignificant emissions 
    provisions for most medium to large sources. This deletion should not 
    impede the permitting authority's ability to write permits which assure 
    compliance with applicable requirements and the requirements of part 
    71. The EPA also believes that the utility of aggregate plant-wide 
    thresholds is negligible because of various other safeguards already 
    provided in the rule; in particular, section 71.5(c)(11) requires 
    applications to not exclude information needed to determine the 
    applicability of, or to impose, any applicable requirement. In 
    addition, the requirement of section 71.5(c)(11)(ii) that units or 
    activities with insignificant emissions be listed in the application 
    provides an opportunity for the permitting authority to review the 
    source's decision to treat emissions as insignificant, while the 
    single-unit emissions thresholds of sections 71.5(c)(11)(ii) (A) and 
    (B) limit the size of emissions to levels that would normally ensure 
    that the units are not covered by extensive control requirements.
    5. Compliance Certification
        The part 71 proposal would have required sources to submit 
    certifications that they were in compliance with all applicable 
    requirements. Commenters requested further clarification of the 
    certification requirements and argued that it was not clear exactly 
    what efforts a source was required to make to determine its compliance 
    status prior to certifying that it was in compliance with all 
    applicable requirements, and that it was unclear whether or not a 
    source was obliged to reconsider past applicability determinations 
    prior to making such a certification. The EPA does not believe that any 
    revisions to the rule are necessary to address the commenters' points. 
    This is true because the white papers for part 70 address these issues 
    and sources may follow that guidance for purposes of completing part 71 
    permit applications.
    
    E. Section 71.6--Permit Content
    
        Today's permit content provisions more closely track the provisions 
    contained in current 70.4 and 70.6 than did those in the proposal. 
    Thus, the order of the paragraphs in section 71.6 is more similar to 
    the permit content section of current part 70 than to the part 71 
    proposal. For example, the provisions dealing with the permitting 
    authority's duty to address emissions units in the permit has been 
    moved from section 71.6(a)(iv) to section 71.3(c), consistent with 
    current part 70. In addition, using current part 70 as the template for 
    permit content means that the provisions for ``off-permit'' contained 
    in today's rulemaking mirror those found at section 70.4(b), while the 
    off-permit provisions of the proposed rule tracked those contained in 
    the August 1994 proposed revisions to part 70. Similarly, today's 
    rulemaking adopts the requirements for emissions trading and 
    operational flexibility that are found in current part 70.
        In addition, EPA retains a provision related to the prompt 
    reporting of deviations from permit conditions from the part 71 
    proposal. Current part 70 requires States to define ``prompt'' in their 
    own programs, and today's rulemaking defines the term for the part 71 
    program and closes this gap in the proposed rule. Today's rulemaking 
    also establishes a part 71 permit expiration date.
        The EPA reiterates that today's rulemaking finalizes provisions for 
    permit content on an interim basis in order to better facilitate smooth 
    transition from implementation of part 71 to approved State programs 
    established pursuant to the current part 70 rule. With respect to 
    permit content provisions, the April 1995 and August 1995 proposals 
    contain provisions which reflect the Agency's current best thinking, 
    and subsequent to reviewing all of the comments on both proposals, EPA 
    may finalize provisions for permit content that differ from those 
    adopted today consistent with the approaches EPA eventually takes in 
    promulgating final revisions to part 70.
    1. Off-permit Operations
        Under today's rulemaking, sources are allowed to make changes at a 
    facility that are not addressed or prohibited by the permit terms, 
    provided they meet the requirements of section 71.6(a)(12). The 
    provision adopted today is patterned on 70.4(b) (14) and (15), the 
    analogous provisions in current part 70. Like part 70, part 71 requires 
    that the source provide the permitting authority with contemporaneous 
    written notification for these types of changes, that these changes be 
    incorporated into the permit at renewal, and that the source keep 
    certain records of these changes. Consistent with current part 70, 
    section 71.6(a)(12) limits off-permit changes to those that do not 
    constitute title I modifications, are not subject to any requirements 
    under title IV of the Act, and meet all applicable requirements of the 
    Act. In applying this provision, the Agency will use the interpretation 
    of the term ``title I modification'' that States are allowed to use 
    under the current part 70 rule. EPA expects that allows a significant 
    number of minor NSR changes, to the extent that they are not prohibited 
    by the title V permit, to qualify for off-permit treatment.
        Like part 70, part 71 does not allow off-permit changes to alter 
    the permitted facility's obligation to comply with the compliance 
    provisions of its title V permit and does not grant the permit shield 
    to off-permit changes. For a more thorough discussion of the concept of 
    off-permit changes, see the rationale for part 70's off-permit 
    provision found at 57 FR 32269.
        The part 71 proposal contained a modified off-permit provision at 
    proposed section 71.6(q) that was designed in light of the four-track 
    permit revision procedures contained in the proposal and modeled on the 
    off-permit provision contained in the August 1994 proposed revisions to 
    part 70. Proposed section 71.6(q) would have allowed certain changes to 
    remain off-permit but would have required the source to submit an 
    application to revise its permit to reflect that change within 6 months 
    of commencing operation of that change. In the August 1995 supplemental 
    proposal to parts 70 and 71, the Agency indicated that off-permit 
    provisions may be unnecessary if the streamlined permit revisions 
    procedures for parts 70 and 71 are adopted as proposed therein. After 
    reviewing comments on both proposals, EPA will decide whether to retain 
    an off-permit provision in the Phase II rulemaking, consistent with the 
    approach EPA takes in finalizing permit revisions procedures. Off-
    permit treatment is available in the interim, consistent with that 
    provided by current part 70, but EPA does not believe that many permits
    
    [[Page 34219]]
    
    will be issued prior to the Phase II rulemaking and that the off-permit 
    provision therefore will not be greatly utilized.
    2. Operational Flexibility
        Under the rule adopted today, sources will enjoy the same 
    operational flexibility as is provided to part 70 sources under current 
    part 70. Section 502(b)(10) of the Act requires that the minimum 
    elements of an approvable permit program include provisions to allow 
    changes within a permitted facility without requiring a permit 
    revision. In the current part 70 rule at section 70.4(b)(12) (i)-(iii), 
    and the rule adopted today, there are three different methods for 
    implementing this mandate. Accordingly, section 71.6(a)(13)(i) provides 
    for sources to make certain changes within a permitted facility that 
    contravene specific permit terms without requiring a permit revision, 
    as long as the source does not exceed the emissions allowable under the 
    permit and the change is not a title I modification. Under the 
    interpretation of the term ``title I modification'' that EPA is 
    allowing States to take under the current part 70 rule, section 
    502(b)(10) changes may include changes subject to minor NSR, provided 
    the change does not exceed the emissions allowable under the permit. 
    Section 71.6(a)(13)(ii) also allows emissions trading at the facility 
    to meet limits in the applicable implementation plan when the plan 
    provides for such trading on 7-days notice in cases where trading is 
    not already provided for in the permit. Additionally, section 
    71.6(a)(13)(iii) allows emissions trading for the purpose of complying 
    with a federally-enforceable emissions cap that is established in the 
    permit independent of otherwise applicable requirements. For a thorough 
    discussion of the flexibility allowed under the analogous part 70 
    provisions, see 57 FR 32266.
        The part 71 proposal contained an approach to operational 
    flexibility that was modeled on the August 1994 proposed revisions to 
    part 70, not current part 70. The August 1995 supplemental proposal 
    suggested further refinements to the concept. After reviewing comments 
    on both proposals, EPA may adopt an approach to operational flexibility 
    that is different from the one found in today's rulemaking, consistent 
    with the approach EPA takes in finally revising part 70. While the 
    approach adopted today differs significantly from that of the proposal, 
    the Agency is adopting it on an interim basis in order to better 
    facilitate transition to the State part 70 programs that are similarly 
    based on the provisions governing operational flexibility under the 
    current part 70 rule.
    3. Affirmative Defense
        In order to remain consistent with current part 70, EPA is adopting 
    a provision from the part 71 proposal that would allow sources to 
    assert an affirmative defense to an enforcement action based on 
    noncompliance with certain requirements due to an emergency. Such a 
    defense would be independent of any emergency or upset provision 
    contained in an applicable requirement. See section 71.6(g). This 
    provision is consistent with that found in the current part 70 rule at 
    section 70.6(g).
        As a result of concerns identified in legal challenges to part 70, 
    the Agency, in the August 1995 supplemental proposal, solicited comment 
    on the need for, scope and terms of an emergency affirmative defense 
    provision. The Agency is reviewing those comments, but has not yet made 
    a decision on whether or not to modify or remove this additional 
    affirmative defense provision from part 70. The Agency will make part 
    71 consistent with the decision reached for part 70 in the part 71 
    Phase II promulgation. In the interim, sources may rely on the 
    affirmative defense offered by section 71.6(g).
    4. Definition of Prompt Reporting
        The proposal contained provisions concerning prompt reporting of 
    deviations from permitting requirements at proposed sections 71.6(f) 
    (3) and (4). The final rule at section 71.6(a)(3)(iii) requires that 
    each permit contain provisions for prompt notification of deviations.
        Two commenters requested that the prompt reporting deadlines in 
    part 71 be adjusted to reflect other environmental regulation timelines 
    or to reflect State program guidelines that have been approved by the 
    Agency for part 70 programs. The Agency disagrees with the request. 
    Section 503(b)(2) of the Act requires permittees to promptly report any 
    deviations from permit requirements to the permitting authority. Since 
    individual permitting authorities are responsible for having programs 
    to attain and/or maintain air quality within their geographical 
    boundaries, they are obligated under the operating permits program to 
    determine, among other things, what constitutes a prompt notification. 
    Included as factors in determining prompt notification would be 
    elements such as pollutant concentration, deviation duration, and 
    authority response time. Because sources and pollutants of concern vary 
    among permitting authorities, States have adopted differing prompt 
    reporting schedules. The Agency has reviewed its obligation to protect 
    air quality on a national level, and has determined that its prompt 
    reporting deadline is appropriate for this obligation. Therefore the 
    deadlines contained in part 71 remain unchanged from the proposal.
        Two commenters requested that part 71 clarify prompt reporting 
    requirements for deviations other than those associated with hazardous, 
    toxic, or regulated air pollutants, as described in sections 
    71.6(a)(3)(iii)(B)(1) and (2). The Agency believes that the requirement 
    contained in section 71.6(a)(3)(iii)(A), in which sources are to report 
    all instances of deviations from permit requirements at least every 6 
    months, provides the basis for prompt reporting of all other 
    deviations. However, the Agency is willing to clarify this reporting 
    requirement and has modified section 71.6(a)(3)(iii)(B) by adding a 
    statement that directs sources to submit all other deviation reports in 
    accordance with the timeframe given in section 71.6(a)(3)(iii)(A).
    5. Inclusion of Federally Enforceable Applicable Requirements in 
    Permits
        Two commenters requested that EPA include in part 71 the analogue 
    to section 70.6(b)(2), a provision that requires the permitting 
    authority to identify in the permit any applicable requirements that 
    are not federally enforceable. The EPA disagrees with this request 
    because part 71 permits will not include any non-federally enforceable 
    applicable requirements; therefore, a requirement for the Agency to 
    identify such terms as non-federally enforceable would be moot, and a 
    part 71 analogue to section 70.6(b)(2) is not needed. Part 71 differs 
    from part 70 in this respect. However, section 71.6(b) is consistent 
    with the first paragraph of section 70.6(b), which provides that part 
    70 permit terms and conditions are to otherwise be federally 
    enforceable.
    6. General Permits
        The proposal contained provisions at proposed section 71.6(l) 
    addressing general permits, which were based on the proposed revisions 
    to the general permits provisions in the August 1994 notice. Under part 
    70, the EPA afforded other permitting authorities the choice of 
    utilizing general permits, and the Agency intended to provide this 
    flexibility to itself. The Agency believes that general permits offer 
    cost-effective means of issuing permits for certain
    
    [[Page 34220]]
    
    source categories. The Agency has not yet decided on the proper 
    approach concerning opportunities for public review and judicial review 
    associated with general permits, and in the interim, has decided to 
    remain consistent with the current part 70 rule. Therefore, under 
    today's notice, EPA's authorization to allow a source to operate 
    pursuant to a general permit may proceed without public notice and does 
    not constitute final permit action for judicial review purposes. 
    Today's part 71 general permit provisions are found at section 71.6(d) 
    and are patterned after the analogous provisions at current section 
    70.6(d). In the Phase II rulemaking, EPA intends to revise the part 71 
    general permit provisions if necessary to remain consistent with the 
    approach the Agency ultimately takes in the final revisions to part 70.
    7. Permit Expiration
        The proposed rule contained a provision for rescinding part 71 
    permits at proposed section 71.4(l)(3). Under today's rulemaking at 
    section 71.6(a)(11), part 71 permits would contain a provision that 
    automatically cancels the part 71 permit upon expiration of the initial 
    permit term or upon issuance of a part 70 permit, without the need for 
    separate action to rescind the permit. The Agency believes that a clear 
    expiration date is necessary in order to avoid potential confusion over 
    which title V permit terms and conditions are valid. The majority of 
    permitting authorities are moving towards final approval of part 70 
    programs. In those few instances where a particular permitting 
    authority may not have final part 70 program acceptance by the deadline 
    for implementation of part 71, the Agency expects that final program 
    approval will occur well before the 5-year part 71 permit term (12 
    years for certain municipal waste combustors) has expired. Once the 
    part 70 program is approved, sources and permitting authorities may 
    desire to begin implementation as soon as possible. The Agency has no 
    desire to be a stumbling block in those efforts, nor does the Agency 
    wish to promote confusion over which permit (part 71 or 70) would be in 
    effect at a particular time.
        One of the purposes of title V was to provide sources with 
    certainty as to their applicable requirements. Part 71 and part 70 
    permits will be similar, but not necessarily congruent, e.g., part 71 
    permits would contain only federally-enforceable requirements, 
    insignificant activities could differ, and reporting provisions would 
    differ. In order to prevent the potential confusion stemming from an 
    unexpired part 71 permit remaining in effect concurrent with a part 70 
    permit, the Agency has decided to preclude the event from occurring. No 
    such comparable provisions are needed in part 70 because that program 
    provides just one title V permit per source. Consequently, section 
    71.6(a)(11) provides that a part 71 permit automatically expires upon 
    the earlier of the expiration of its term or the issuance of a part 70 
    permit to the source.
    
    F. Section 71.7--Permit Review, Issuance, Renewal, Reopenings, and 
    Revisions
    
        As discussed above, EPA is, on an interim basis, promulgating final 
    regulations regarding permit issuance, renewal, reopenings, and 
    revisions for part 71 that are based upon the existing provisions 
    governing State title V programs at 40 CFR, section 70.7. Consequently, 
    the provisions adopted today differ from those contained in the part 71 
    proposal, which were based upon the August 1994 proposed revisions to 
    part 70. The EPA is still in the process of adopting revisions to part 
    70, and thus is not able at this time to base part 71's provisions on 
    the expected future changes to part 70. As a result, EPA has concluded, 
    in response to comments, that the most reasonable approach is to model 
    part 71's permit issuance, renewal, reopenings, and revisions 
    procedures on the corresponding provisions in the existing part 70 
    rule. These changes from the proposal, in addition to other changes in 
    response to comments, are identified below.
    1. Permitting Authority's Action on Permit Application
        First, the organization of the paragraphs has been changed from the 
    proposal to be consistent with 40 CFR section 70.7(a). In addition, in 
    section 71.7(a)(1), the word ``modification'' is now used in place of 
    the word ``revisions,'' which was used in the proposal. This is a 
    technical change to the rule to make it conform with the language used 
    in corresponding provisions in the current part 70 rule. Also, section 
    71.7(a)(1)(ii) has been changed to track section 70.7(a)(1)(ii) by 
    explicitly providing that changes subject to minor permit modification 
    procedures need not comply with the public participation requirements 
    of sections 71.7 and 71.11. This change from the proposal is a result 
    of the Agency's adoption in today's rule of permit revision procedures 
    modelled on those contained in the existing part 70 rule. Moreover, 
    section 71.7(a)(1)(iv) has been adopted without the language providing 
    that, in some cases, the terms of the permit need not provide for 
    compliance with all applicable requirements that are in force as of the 
    date of permit issuance. Again, this change is necessary to make 
    section 71.7(a)(1)(iv) consistent with the corresponding provision at 
    section 70.7(a)(1)(iv), which does not contain the proposal's language. 
    That language was first proposed in the August 1994 proposed revisions 
    to part 70, and the Agency is not yet prepared to adopt it into a final 
    title V rule. Likewise, section 71.7(a)(1)(v) is being promulgated 
    without references to the administrative amendment and de minimis 
    permit revision procedures contained in the proposal in order to better 
    match the current part 70 provisions at section 70.7(a)(1)(v).
        Section 71.7(a)(2) is being adopted without the language in the 
    proposal which would have required permitting authorities to take final 
    action within 12 months after receipt of a complete application for 
    early reductions permits under section 112(i)(5) of the Act because 
    regulatory language addressing this requirement was moved to section 
    71.4(i)(3). Furthermore, this provision is being adopted without the 
    language in the proposal that would have allowed permitting authorities 
    to delay final action where an applicant fails to provide additional 
    information in a timely manner as requested by the permitting 
    authority, as section 70.7(a)(2) currently does not provide such 
    authority.
        A new section 71.7(a)(3) is being promulgated to require the 
    permitting authority to ensure that priority is given to taking action 
    on applications for construction or modification under title I of the 
    Act. This change is made to make part 71 consistent with the 
    corresponding provision in current part 70 at section 70.7(a)(3).
        Section 71.7(a)(4) (section 71.7(a)(3) in the proposal) deletes the 
    references in the proposal to the proposed regulatory provisions 
    addressing administrative amendments, de minimis permit revisions, and 
    minor permit revisions, and tracks current section 70.7(a)(4) by 
    providing that permitting authorities need not make completeness 
    determinations for applications for minor permit modifications. This 
    change is a result of EPA's basing section 71.7 on the current section 
    70.7. In addition, sections 71.7(a) (5) and (6) (sections 71.7(a) (4) 
    and (5) in the proposal) are renumbered in order to track existing 
    sections 70.7(a) (5) and (6).
    
    [[Page 34221]]
    
        The proposal contained a provision at proposed section 71.7(a)(6) 
    addressing how draft and final permits may be issued with respect to 
    applicable requirements that are approved or promulgated by EPA during 
    the permit process. This provision was proposed in the August 1994 
    proposed revisions to part 70 and is not contained in the current part 
    70 rule. For the reasons stated above, EPA is not yet prepared to adopt 
    it into part 71, and so is deleting the proposed provision from today's 
    final rule.
    2. Requirement To Apply for a Permit
        One commenter suggested revising 71.7(b) regarding the application 
    shield to say that the permitting authority must set a reasonable 
    deadline for the submission of additional information, and commented 
    that EPA should not be able to request information that is ``needed to 
    process the application'' but only that which is ``reasonable and 
    necessary to issue the permit''. The Agency disagrees that the 
    regulation should set a specific deadline for the submission of 
    additional information because the determination of what is a 
    reasonable time will vary depending on the information requested. Also, 
    EPA disagrees that there is a distinction between information needed to 
    process the application and information that is reasonable and 
    necessary to issue the permit.
        One commenter suggested revising section 71.7(b) to allow sources 
    to operate subsequent to submission of a complete, but late, 
    application or application for renewal. The Agency believes that 
    extending an application shield to sources that fail to submit timely 
    applications is inconsistent with the Act. The proposal for part 70 
    contained a provision that would have provided a grace period of up to 
    three months to submit applications after the required submittal date. 
    The EPA deleted this provision from the final part 70 rule because 
    extending the application shield to sources that did not submit a 
    timely application would have been inconsistent with section 503(c) of 
    the Act. The Agency is promulgating section 71.7(b) to closely track 
    the corresponding provision at current section 70.7(b). Consequently, 
    the references in proposed section 71.7(b) to the proposed provisions 
    addressing administrative amendments, de minimis permit revisions, and 
    minor permit revisions have been deleted and replaced by references to 
    provisions addressing section 502(b)(10) changes and minor permit 
    modifications. In addition, the proposal's reference to section 
    71.7(a)(3) has been replaced with a reference to section 71.7(a)(4), 
    due to the restructuring of section 71.7(a).
    3. Permit Renewal and Expiration
        Section 71.7(c) is being promulgated to more closely match the 
    corresponding provision under current section 70.7(c) than did the 
    proposal. The references in proposed section 71.7(c)(2) to proposed 
    sections 71.5(b) and 71.5(c) have been replaced by a reference to 
    section 71.5(a)(1)(iii), due to the restructuring of section 71.5. 
    Moreover, section 71.7(c)(2) (section 71.7(c)(3) in the proposal) is 
    being promulgated without the language that would have provided that, 
    where the permitting authority fails to act on a timely renewal 
    application before the end of the term of title V permit, the permit 
    shall remain in effect until the permitting authority does take final 
    action. Instead that language (which is based upon the existing section 
    70.4(b)(10) of the current part 70 rule) is being promulgated at 
    section 71.7(c)(3).
    4. Permit Revisions
        Commenters remarked that the Federal title V permit program as 
    proposed in April 1995 would establish a new, added layer of permitting 
    which would add unacceptably to the amount of time needed before a 
    source could implement process changes. They suggested that even though 
    the April 1995 permit revision tracks attempt to build on existing 
    preconstruction programs, they still pose substantial new requirements 
    (e.g., new criteria for adequate prior review in NSR). These commenters 
    opined that if EPA believes that insufficient public review is afforded 
    by existing programs, the Agency should address those shortcomings, not 
    start a new process. Another commenter suggested that clerical changes 
    should be handled through notification of the change by an amendment 
    letter to the permitting authority that would then be attached to the 
    permit without any EPA review until permit renewal. The commenter 
    further suggested that all minor source changes which do not violate 
    any permit term and do not render the source newly subject to an 
    applicable requirement should be allowed to follow this amendment 
    procedure. Other commenters opined that the April 1995 proposed four 
    track permit revision procedures were fundamentally flawed and must be 
    replaced with simpler procedures. One commenter suggested that EPA 
    Regions, not just delegated States, should be authorized to conduct 
    ``merged processing'' to add NSR or section 112(g) terms to title V 
    permits, if such processing is retained in the final rule. Some 
    suggested that EPA promote consistency between part 70 and part 71 
    permit programs to reduce confusion for sources that have to make a 
    transition between different regulatory programs.
        In light of these and other comments, EPA proposed in August 1995 a 
    revised permit revision process, developed with extensive stakeholder 
    input, which proposes several ways of streamlining permit revisions, 
    particularly for those changes subject to prior State review (e.g., NSR 
    changes). In the interim, as discussed earlier in this preamble, rather 
    than adopting the four-track permit revision system that the Agency 
    proposed for part 71 on April 25, 1995, the EPA has decided to adopt, 
    for the first phase of part 71, the permit revision system in the 
    current (July 1992) part 70 rule. Current part 70 provides three ways 
    to revise a permit: the administrative amendment process, the minor 
    permit modification process and the significant permit modification 
    process. The specific regulatory changes to proposed part 71 taken to 
    adopt these procedures are described below.
        One commenter requested that EPA not follow the approach to ``title 
    I Modification'' in the August 1994 proposed revisions to part 70 in 
    defining the term for part 71. In implementing the current part 70 
    permit revision procedures during the interim period, EPA would apply 
    the interpretation of ``title I modifications'' that States are allowed 
    to apply under the current part 70 rule. Under this interpretation, 
    minor NSR actions may be incorporated into the title V permit using the 
    minor permit modification procedures of current part 70, or 
    alternatively, may be made as off-permit changes if they are eligible.
        a. Rationale for Providing Interim Permit Revision Procedures. The 
    proposal indicated that due to the ongoing discussions with 
    stakeholders regarding permit revision procedures under title V, EPA 
    was considering finalizing part 71 in the interim without provisions 
    for permit revision procedures. Several commenters suggested that EPA 
    not finalize any portion of part 71 until permit revision procedures 
    are finalized because they will influence how sources design their 
    initial permit applications. The commenters argued that sources will 
    need the ability to obtain expeditious revisions to permits, and that 
    there is thus a need for provisions governing modifications. As 
    discussed previously, EPA has decided to include the permit revision 
    procedures of current part 70 in
    
    [[Page 34222]]
    
    this interim part 71 rule, while reserving the right to adopt 
    procedures based upon future changes to part 70, when part 70 revisions 
    are promulgated and Phase II of this rule is completed.
        The EPA agrees with commenters that including current part 70 
    revision procedures is most appropriate for several reasons. First, EPA 
    believes that it is premature to adopt the procedures proposed in April 
    1995 for part 71, or in August 1995 for part 70, because both of these 
    proposals involve outstanding issues. Although the August 1995 proposal 
    contains the latest thinking on streamlined permit revision procedures, 
    it would be inappropriate to rush to promulgate a proposed system 
    before the Agency has taken time to consider comments on the August 
    1995 proposal and arrive at a final position. In the meantime, the 
    Agency has at its disposal the permit procedures of the current part 70 
    rule under which the Agency continues to approve State programs.
        Second, industry commenters note that a clear understanding of 
    permit revision procedures is important as sources prepare their part 
    71 permit applications. The revision procedures of part 70 are more 
    clearly understood than any proposed procedures, having been 
    promulgated by EPA and adopted by many State programs. Third, adopting 
    the existing part 70 permit revision procedures insures a smooth 
    transition from a Federal operating permits program to a State program 
    due to the similarity between the two programs.
        Finally, the Agency does not believe that many permit revisions 
    will occur during Phase I of this program. The timing of permit 
    issuance under part 71 is such that the Agency believes that few part 
    71 permits will be issued and fewer will need to be revised before 
    States receive part 70 approval or before Phase II of part 71 is 
    promulgated. Permit revision procedures in Phase I of the part 71 rule 
    become more essential the longer part 71 programs are in place without 
    a Phase II rule, which is possible if the Phase II rulemaking is 
    delayed.
        b. Description of Permit Revision Procedures. The part 71 proposal 
    addressed permit revisions at proposed sections 71.7(d)-(h) using 
    proposed provisions from the August 1994 part 70 notice. Proposed 
    section 71.7(d) would have defined when a permit revision is necessary; 
    proposed section 71.7(e) would have addressed administrative 
    amendments; proposed sections 71.7 (f) and (g) would have addressed de 
    minimis permit revisions and minor permit revisions, respectively; and 
    proposed section 71.7(h) would have covered significant permit 
    revisions. All of these provisions have been deleted in today's rule, 
    and replaced with new provisions at sections 71.7 (d) and (e) that 
    track the corresponding provisions in the current part 70 rule 
    governing administrative amendments, minor permit modifications, and 
    significant permit modifications. The EPA directs interested persons to 
    the preamble to the final part 70 rule, 57 FR 32250 (July 21, 1992) for 
    a detailed description of these permit revision procedures.
        Under section 71.7(d), changes eligible to be processed as 
    administrative amendments include administrative changes such as 
    correction of typographical errors, changes in mailing address, 
    ownership of the source (or part of the source) unless restricted by 
    title IV, contact persons, and changes in individuals who have assigned 
    responsibilities, (including the responsibility to sign permit 
    applications). Administrative permit amendments can be handled by 
    direct correspondence from the permitting authority to the facility 
    after the appropriate information related to the changes has been 
    supplied by the facility. As under current part 70, administrative 
    amendments could also be used to address ``enhanced NSR'' changes, to 
    which the permitting authority could also extend the permit shield. 
    Sections 71.7(e) (1) and (2), which address minor permit modification 
    procedures, are designed for small changes at a facility which will not 
    involve complicated regulatory determinations. A source may make a 
    change immediately upon filing an application for a minor permit 
    modification, prior to the time the permitting authority, affected 
    States, and EPA (in the case of a program delegated pursuant to section 
    71.10) review the application. Eligible changes could be processed 
    individually or in groups, but the permit shield may not extend to 
    these changes. Section 71.7(e)(3) covers significant modifications. In 
    this track, the public, the permitting authority, affected States, and 
    EPA (in the case of a program delegated pursuant to section 71.10) will 
    review the modification in the same manner as review during permit 
    issuance. The permit shield may extend to changes processed under this 
    track.
    5. Permit Reopenings
        The proposal addressed permit reopenings at proposed 71.7 (i) and 
    (j). These provisions were modeled on the existing provisions at 
    section 70.7 (f) and (g), as proposed to be revised in the August 1994 
    notice. One of the features of that approach was a specific provision 
    for reopening permits to incorporate new maximum achievable control 
    technology (MACT) standards promulgated under section 112 of the Act. 
    As part 70 has not yet been finally revised to adopt this approach, it 
    is premature at this time to adopt it for part 71. Consequently, in 
    order to more closely track the current part 70 rule and promote 
    consistency with State programs developed and approved under the 
    current rule, the part 71 provisions for permit reopenings adopted 
    today at sections 71.7 (f) and (g) are modeled on the existing 
    provisions at sections 70.7 (f) and (g), and do not include the 
    proposed provisions concerning reopening permits to incorporate new 
    MACT standards.
    
    G. Section 71.8--Affected State Review
    
        The provisions of section 71.8 differ from provisions proposed in 
    the part 71 proposal in several respects. First, because today's 
    rulemaking adopts permit revision procedures based on the current part 
    70 rule, rather than those that were proposed in April, the cross 
    references to section 71.7 were changed and the reference to de minimis 
    permit revisions has been deleted. In addition, the final rule 
    specifically provides, consistent with part 70, that timing of notice 
    to affected States of major permit modifications is not tied to the 
    timing of notice to the public.
        Second, section 71.8(b) is being adopted to more consistently 
    follow section 70.8(b)(2) in providing that where EPA delegates 
    administration of a part 71 program, the permitting authority shall 
    transmit notice of refusal to accept recommendations of an affected 
    State as part of the permitting authority's submittal of the proposed 
    permit to EPA.
        Third, as discussed in section III.B of this document, a new 
    paragraph (d) has been added to section 71.8 that requires that part 71 
    permitting authorities provide notice of certain permitting actions to 
    federally recognized Indian Tribes. While this is a departure from what 
    part 70 currently requires of State permitting authorities, EPA agrees 
    with commenters who suggested that federally recognized Indian Tribes 
    should not be required to establish compliance with any eligibility 
    criteria in order to be entitled to notice of Federal permitting 
    decisions that may affect Tribal air quality. One commenter suggested 
    that applying for treatment in the same manner as a State was a time 
    consuming and burdensome process for Indian Tribes and urged the 
    elimination of that requirement for Tribes to receive notice of 
    permitting actions. Consistent
    
    [[Page 34223]]
    
    with the Agency's policy of maintaining government-to-government 
    relationships with Indian Tribes, EPA (and delegate agencies) will 
    notify federally recognized Indian Tribes of draft permits that may be 
    issued to sources that could affect Tribal air quality, including all 
    draft permits issued by EPA for the Tribal area and all draft permits 
    for sources that are within 50 miles of the reservation boundary or the 
    Tribal area. Accordingly, the Agency has added a new paragraph that 
    provides that the part 71 permitting authority shall send notices of 
    draft permits to federally recognized Indian Tribes whose air quality 
    may be affected by the permitting action. The EPA is imposing upon 
    itself this responsibility in order to further its government-to-
    government relationship with Tribes.
    
    H. Section 71.9--Permit Fees
    
    1. Two-Phase Promulgation of Fee Requirements
        Consistent with the two-phased approach to part 71 promulgation 
    described in this notice, EPA is today adopting a two-phased approach 
    to part 71 fee requirements. Upon Phase I promulgation, collection of 
    fees should be sufficient to cover the anticipated program costs of 
    Phase I. On the other hand, because the cost of Phase II is tied to 
    procedures which will not be finalized until the Phase II rulemaking 
    (i.e., revised and streamlined permit revision procedures), a fee 
    amount for Phase II cannot be finalized in today's rule. Thus, the 
    Phase I fee covers all program costs except those associated with 
    permit revisions which are excluded because the Phase II rulemaking 
    will finalize streamlined permit revision procedures that will 
    ultimately differ substantially from those contained in today's rule. 
    Instead, the Phase II rulemaking will add to the fee the costs for the 
    new permit revision procedures when they are finalized. More 
    information on the determination of specific activities and costs 
    associated with each phase is contained in the document entitled 
    ``Federal Operating Permits Program Costs and Fee Analysis (Revised),'' 
    which is contained in the docket for this rulemaking.
        The two-phased approach to fee requirements will not impact the 
    ultimate fee amount owed by a source. For the majority of sources, EPA 
    expects that the part 71 application and associated fee submittal will 
    occur after the Phase II rulemaking. For these sources, the fee will be 
    paid all at once. Sources that submit their applications prior to the 
    Phase II rulemaking will pay a Phase I fee in full at the time of 
    application. The balance of the fee necessary to cover the costs of the 
    Phase II provisions will be collected once the Phase II rule is 
    promulgated. The specific timing and amount of the Phase II fee 
    collection will be discussed in the Phase II rulemaking.
        The EPA fully expects that the Phase II rulemaking finalizing 
    permit revision procedures will be completed before any part 71 permits 
    are issued and that no program costs will be incurred in the interim 
    period as a result of permit revisions. However, EPA recognizes that in 
    the unlikely event that a part 71 permit is both issued and revised 
    (under the interim revision procedures in today's rule) fees will not 
    have yet been collected to cover the cost of the revision and that if 
    the Phase II fee is finalized based on a streamlined permit revision 
    process, there may be a shortfall in revenue. However, the alternative 
    would be to finalize today a Phase I fee based on the interim revision 
    procedures that potentially overcharges sources and would necessitate, 
    if and when the permit revision procedures are streamlined as expected, 
    a refund. The EPA wishes to avoid this unnecessary and burdensome 
    process.
    2. Fee Amount
        The part 71 proposal proposed a base fee amount of $45 per ton/year 
    which was based on a fee analysis which projected EPA's direct and 
    indirect costs for implementing the part 71 program nationwide and 
    dividing that by the total emissions subject to the fee. A detailed 
    discussion of this methodology is found in ``Federal Operating Permits 
    Program Costs and Fee Analysis,'' which is contained in the docket for 
    this rulemaking. Using the same basic methodology as the original fee 
    analysis, EPA has calculated the costs of Phase I and has set the base 
    Phase I fee amount at $32 per ton/year to cover these costs. The 
    determination of this amount is contained in the report entitled, 
    ``Federal Operating Permits Program Costs and Fee Analysis (Revised)'' 
    (hereafter ``Revised Fee Analysis''), which is contained in the docket 
    for this rulemaking. As proposed, the fee will be adjusted based on the 
    level of contractor support needed for those programs where it is 
    necessary for EPA to use contractors.
        One commenter suggested that the $3 per ton surcharge to cover EPA 
    oversight of contractor and delegated programs should be eliminated, 
    noting that EPA does not charge oversight fees for State part 70 
    programs. The EPA agrees and believes that such a surcharge would be 
    inconsistent with the approach taken in part 70. A full evaluation of 
    the April 1995 comments was made after the development of the August 
    1995 proposal, in which EPA proposed to eliminate the surcharge. This 
    evaluation of comments confirmed the direction EPA took in the August 
    1995 proposal. Therefore, today's action both responds to the April 
    comments and is consistent with the August 1995 proposal. Accordingly, 
    EPA is today deleting the surcharge provisions from sections 71.9(c)(2) 
    and (3). The EPA will continue to consider any comments received on the 
    supplemental proposal, and, if necessary, will take any additional 
    action on the surcharge in the Phase II rulemaking.
        For reasons similar to those described in the preceding paragraphs 
    on the surcharge, the EPA is deleting ``preparing generally applicable 
    guidance regarding the permit program or its implementation or 
    enforcement'' from the list of activities in section 71.9(b) whose 
    costs are subject to fees. The EPA believes that this category 
    partially duplicates the fourth category under section 71.9(b), general 
    administrative costs. To the extent that it is not duplicative, it 
    refers to guidance that is issued before an individual part 71 program 
    is in place. The EPA does not require that States charge fees for these 
    activities for part 70 programs, and the Agency does not believe that 
    such costs should be included in part 71 fees. This change does not 
    result in a change in the fee structure because costs of activities 
    which occur before the effective date of the part 71 program were not 
    included in the original fee analysis. This change simply adjusts the 
    list of activities in section 71.9(b) to more accurately reflect the 
    activities whose costs were included in the fee analysis. Consistent 
    with the deletion of the surcharge, the EPA is taking this action based 
    on comments received on the part 71 proposal. If adverse public comment 
    is received regarding this change as proposed in the August 1995 
    supplemental proposal, the EPA will take additional action as necessary 
    in the Phase II rulemaking.
    3. Fees for Delegated Programs
        As discussed in the part 71 proposal, EPA intends to allow 
    delegation of part 71 programs to States in many cases. Originally, EPA 
    envisioned funding these delegated part 71 programs with revenue 
    generated from part 71 fees. However, EPA is aware that many delegate 
    agencies have the authority under State or local law to collect fees 
    adequate to fund delegated part 71 programs. In some cases, these 
    agencies could continue to collect fees even
    
    [[Page 34224]]
    
    though EPA would be collecting part 71 fees. Several commenters pointed 
    out that this would result in the undesirable situation of paying fees 
    to two permitting authorities. On the other hand, one commenter noted 
    that if a delegate agency, in deference to part 71, rescinds its 
    authority to collect fees, funding for the Small Business Assistance 
    Program (SBAP) in that State could be adversely affected.
        The EPA believes that the best way to address both of these 
    situations is to suspend collection of part 71 fees for part 71 
    programs which are fully delegated to States and for which the State 
    has adequate authority under State law to fund fully-delegated part 71 
    activities with fees collected from part 71 sources. This ensures that 
    State revenue is available to administer the program, including the 
    SBAP, while addressing the commenters' concerns about double fees. 
    However, EPA cannot suspend fee collection for partially delegated part 
    71 programs, since in those situations EPA will still incur substantial 
    administrative costs. Suspension of EPA fee collection does not 
    constitute approval of the State's fee structure for part 70 purposes. 
    Rule language codifying this approach has been added to section 
    71.9(c)(2).
        The suspension of part 71 fees for delegated programs was proposed 
    in the August 1995 supplemental proposal. While the timing of today's 
    promulgation has not allowed thorough evaluation of comments on that 
    proposal, the EPA agrees with the concerns about duplicate fees and the 
    SBAP which were raised in reference to the part 71 proposal. A full 
    evaluation of these comments was made after the development of the 
    August 1995 proposal on this issue. This evaluation confirmed the 
    direction EPA had taken in the August 1995 proposal. Therefore, today's 
    action both responds to the April comments and is consistent with the 
    August proposal. Furthermore, today's action is consistent with EPA's 
    position that its fees be based on program costs, because EPA will not 
    incur any program costs after it fully delegates a part 71 program. The 
    EPA will still evaluate all comments received on the August 1995 
    proposal and will take any necessary additional regulatory action on 
    the suspension of part 71 fees for delegated programs in the Phase II 
    rulemaking.
        For part 71 programs that are delegated but for which EPA does not 
    waive fee collection, EPA's policy will be to continue to collect part 
    71 fees itself. The proposed fee amount for part 71 programs was based 
    on the assumption that certain activities would be more costly for EPA 
    to implement than for States due to increased travel, unfamiliarity 
    with individual sources, etc. However, commenters pointed out that when 
    a program is delegated, this assumption is not applicable. The EPA 
    agrees with this comment, and is today promulgating language 
    establishing a lower part 71 fee for delegated programs which omits the 
    increased cost assumption made for EPA-administered part 71 programs. 
    Where EPA continues to collect part 71 fees for a fully-delegated 
    program, the Phase I part 71 fee amount will be $24 per ton/year. The 
    determination of this amount is contained in the Revised Fee Analysis. 
    Furthermore, for partially delegated programs, the part 71 fee that EPA 
    collects will be lower than the fee for an EPA-administered program 
    because the fee will be adjusted to account for the proportion of 
    effort performed by the delegate agency at a lower cost. For these 
    programs, the Administrator will determine the fee according to the 
    formula in section 71.9(c)(4).
    4. Timing of Fee Payment
         The part 71 proposal provided that sources submitting their 
    initial fee calculation worksheets must pay one-third of the initial 
    fee upon submittal, and must pay the balance of the fee within 4 
    months. However, EPA believes that two changes discussed in today's 
    preamble make this installment approach to fee payment infeasible. 
    First, EPA is promulgating a later due date for permit applications, 
    which would mean that under the proposed installment approach, receipt 
    of two-thirds of the fee revenues would be delayed until the end of the 
    first year of the program, which would not provide adequate funding for 
    initial program activities. Second, EPA is promulgating a two-phased 
    approach to fee collection. The EPA believes that it would be 
    unnecessarily complicated and potentially confusing to provide for 
    installment payment of the fee for one or both phases. For these 
    reasons, EPA is promulgating language at section 71.9(e)(1) which 
    clarifies that payment of the full fee amount for the first year is due 
    upon submittal of the initial fee calculation worksheet.
        In addition, because today's rule changes the due date for permit 
    applications, a change must also be made to the deadlines for the 
    initial part 71 fee calculation worksheets in the event that EPA 
    withdraws approval of a part 70 program. The proposal contained a 
    schedule for submission of the fee calculation worksheet based on SIC 
    code. The due dates ranged from 4 to 7 months after the effective date 
    of the part 71 program. Changes to section 71.9(f)(1) adjust the fee 
    calculation worksheet due dates to range from 6 to 9 months after the 
    part 71 effective date, depending on SIC code.
    5. Computation of Emissions Subject to Fees
         A commenter pointed out that the rule language in proposed section 
    71.9(c)(5)(ii) inadvertently limits the 4000 ton cap on emissions 
    subject to fees solely to programs administered by EPA, not delegated 
    or contractor-administered programs. Accordingly, the EPA has amended 
    this paragraph to clarify that the 4000 ton cap applies to all types of 
    part 71 programs.
    6. Penalties
        The part 71 proposal contained a penalty charge of 50 percent of 
    the fee amount if the fee is not paid within 30 days of the due date. 
    In addition, the proposal assessed a penalty of 50 percent on 
    underpayments with the 50 percent penalty assessed on the amount by 
    which the source underpaid the fee owed. The proposal also provided 
    relief from the penalty for certain underpayments where the source is 
    making an initial fee calculation based on estimated rather than actual 
    emissions. The proposal provided that where the underpayment results 
    from an underestimate of future emissions and where the underpayment 
    does not exceed 20 percent of the fee amount (i.e., where the source 
    pays more than 80 percent of the fee owed), no penalty would be 
    assessed.
        Some industry commenters were concerned that establishing a penalty 
    for underpayment for a source that underpays by as little as 20 percent 
    would be too harsh in light of the uncertainty in making emissions 
    estimates. Although title V requires a penalty to be assessed for 
    failure to pay any fee lawfully imposed by the Administrator, the EPA 
    agrees that there is a degree of uncertainty in estimating emissions, 
    particularly for HAP sources, which are often smaller, and for which 
    emission factors are not well-defined.
        Upon consideration of comments and evaluation of the relative 
    uncertainty of emission estimates for HAP listed pursuant to section 
    112(b) of the Act, the EPA is today promulgating in section 71.9(l)(4) 
    an underpayment penalty which differs slightly from the proposal. For 
    sources who base their initial fee calculation worksheet on estimated 
    rather than actual emissions, the EPA will, for HAP emissions, apply 
    the penalty to an underpayment of 50 percent or more. The penalty will 
    still apply to an underpayment of 20 percent
    
    [[Page 34225]]
    
    or more for non-HAP emissions. If a source is subject to fees for both 
    HAP and non-HAP emissions, the underpayment which would trigger a 
    penalty will be prorated based on what portion of the source's 
    emissions are HAP versus non-HAP. Thus, to determine whether an 
    underpayment would incur a penalty, such a source's HAP emissions would 
    be multiplied by the 50 percent rate, and its non-HAP emissions would 
    be multiplied by the 20 percent rate. The sum of these emissions rates 
    determines the level of underpayment which, if exceeded, would incur 
    the underpayment penalty. The EPA believes that this approach offers 
    significant relief to sources faced with difficulty in accurately 
    estimating their emissions, while still ensuring that adequate fee 
    revenues can be collected in a fair and timely manner.
    7. Certification Requirement
        The EPA believes that the correct interpretation of the part 71 
    certification requirement at section 71.5(d) is that it applies to all 
    fee calculation documents. However, for clarity, EPA is today adding a 
    requirement to sections 71.9(e) and (h) which requires certification of 
    the fee calculation worksheets by a responsible official. The added 
    language in section 71.9 is simply a cross reference to the language in 
    section 71.5(d).
    
    I. Section 71.10--Delegation of Part 71 Program
    
    1. Delegation of Authority Agreement
        With respect to the content of Delegation of Authority Agreements, 
    EPA wishes to clarify that the adequacy of State permit fees must be 
    addressed when EPA waives collection of part 71 permit fees. As 
    described in section III.F.3 of this preamble, when EPA has determined 
    that a delegate agency has raised adequate fee revenue from sources 
    subject to title V to administer a fully-delegated part 71 program 
    absent any financial assistance from EPA, then EPA will waive 
    collection of part 71 fees. In such a case, the Delegation of Authority 
    Agreement would specify that the delegate agency has sufficient revenue 
    and will collect sufficient revenue from sources subject to title V to 
    administer all of its duties as outlined in the Agreement. The EPA will 
    not waive fees when the part 71 program is partially delegated or when 
    the delegate agency lacks sufficient revenue to fund the delegated part 
    71 program.
    2. Appeal of Permits
        The Agency has revised proposed section 71.10(i), which addresses 
    the petition process for permits issued by delegate agencies. In lieu 
    of restating which persons and parties may submit petitions to the 
    Environmental Appeal Board pursuant to section 71.11(l)(1), section 
    71.10(i) provides that the appeals of permits under delegated program 
    shall follow the procedures of section 71.11(l)(1).
    3. Transmission of Information to EPA, Prohibition of Default Issuance, 
    and EPA Objections
        The final rule also makes certain changes to the proposed 
    provisions addressing transmission of information to the Administrator, 
    the prohibition of default issuance of permits, and EPA objections to 
    proposed permits at sections 71.10(d), (f) and (g). Essentially, these 
    changes are being made today in order to better harmonize the final 
    rule with corresponding provisions in the currently promulgated part 70 
    rule at 70.8(a), (c) and (e). Regarding transmission of information to 
    EPA, the reference in proposed section 71.10(d)(1) to proposed section 
    71.7(a)(1)(v) has been rewritten, and proposed paragraphs (2) and (3) 
    have been merged into it in order to more closely track part 70. New 
    paragraph (2) has been adopted in order to achieve consistency with 
    section 70.8(a)(2).
        The provision on prohibition of default issuance has been changed 
    to follow the existing provision at section 70.8(e). In proposed 
    section 71.10(f)(2), EPA had provided that the prohibition would not 
    apply to permit revisions processed through the proposed de minimis 
    permit revision track, following the August 1994 proposed revisions to 
    part 70. As that track is not being adopted in this Phase I rule, the 
    exception has been deleted.
        Finally, section 71.10(g) on EPA objections has been changed from 
    the proposal in order to follow the test established under the current 
    part 70 rule for when EPA would object to proposed permits, and to 
    follow the promulgated part 70 language providing for what shall happen 
    when a permitting authority refuses to respond adequately to an EPA 
    objection. This change includes deletion of the proposed reference to 
    proposed section 71.7(a)(6), which is not being adopted as proposed in 
    this final rule.
    
    J. Section 71.11--Administrative Record, Public Participation, and 
    Administrative Review
    
        The Agency has chosen to establish part 71-specific rules in 
    today's promulgated section 71.11 for administrative procedures in 
    order to clarify for the public and the regulated community those 
    requirements associated specifically with Federal operating permits 
    under title V of the Act. Today's promulgated section 71.11 is based 
    closely on the provisions of 40 CFR part 124. Part 124 covers a number 
    of EPA permitting programs, and the process of identifying the separate 
    and distinct requirements associated with those individual programs can 
    be complex. The Agency feels that it is advantageous in this case to 
    describe the administrative procedures for today's promulgated part 71 
    within the rule itself, since that will avoid potential confusion as to 
    which provisions of part 124 apply to the part 71 program, and since 
    interested parties will not be required to refer to separate 
    regulations in discerning applicable administrative procedures.
        Certain aspects of section 71.11 that would correspond to proposed 
    streamlined part 71 permit revision processes discussed in the preamble 
    to the supplemental part 70 and 71 proposed rules published on August 
    31, 1995 (60 FR 45529), are not addressed in today's notice because the 
    Agency is not yet prepared to conduct final rulemaking for those 
    processes. In the meantime, EPA is promulgating permit revision 
    processes based on the current part 70 rule in response to numerous 
    comments on the proposed part 71.
        To accommodate basing part 71's permit revision procedures on the 
    existing part 70 rule, today's notice makes certain changes to the 
    regulatory language of section 71.11 as proposed on April 27, 1995 (60 
    FR 20804) in order to apply administrative procedures to the permit 
    revision tracks as appropriate. Changes to the regulatory language that 
    make reference to permit revision procedures were made in the first 
    paragraph of section 71.11 and in section 71.11(l)(1). These sections 
    make reference to specific types of permit revisions which in this 
    promulgated rule are those permit revision procedures found in 40 CFR 
    part 70, rather than the four-track permit revision procedures in the 
    April 27, 1995 proposed part 71. Section 71.11(l)(1) describes the 30-
    day period within which a person may request review of a final permit 
    decision. For significant modifications, the 30-day period begins with 
    the service of notice of the permitting authority's action. This is 
    unchanged from the proposal. For minor permit modifications and 
    administrative amendments, the 30-day period begins on the date the 
    minor permit modification or administrative amendment is effective.
        Section 71.11(d)(3)(i)(D) has been modified in response to comments
    
    [[Page 34226]]
    
    received which noted that under the proposal a requirement to notify 
    any unit of local government having jurisdiction over the area where a 
    source is located would result in notices to components of government 
    which have no relationship to air quality and its impacts. Promulgated 
    section 71.11(d)(3)(i)(D) stipulates that the local emergency planning 
    committee (not ``any'' unit of local government) and State agencies 
    having authority under State law with respect to the operation of the 
    source are among the entities to receive a copy of notices of 
    activities described in section 71.11(d)(1)(i).
        Additional changes to the regulatory language of section 71.11 
    relate to treatment of a final permit decision as enforceable and 
    effective where review by the EAB has been requested. In proposed 
    sections 71.11(i)(2) and 71.11(l)(6), the Agency proposed that a final 
    permit decision would become effective immediately upon issuance of 
    that decision unless a later effective date were specified in the 
    decision. It was pointed out by several commenters that, in other EPA 
    permitting programs, such as the Resource Conservation and Recovery Act 
    and PSD programs, an appeal request stays the effectiveness of a final 
    permit decision. See 40 CFR section 124.15(b)(2). The EPA agrees that 
    it would be unfair to force permittees to comply with permit terms 
    during the time that they are subject to appeal, and that the proposal 
    was inappropriately inconsistent with part 124 on this point. Thus, 
    sections 71.11(i)(2) and 71.11(l)(6) have been promulgated to conform 
    to the longstanding Agency approach reflected in 40 CFR section 124.15, 
    so that permittees are not unfairly required to comply with permit 
    terms pending their review by the EAB. Under the final rule, those 
    specific permit terms and conditions that are the subject of an appeal 
    to EAB would be stayed, while the rest of the permit would become 
    effective as otherwise provided in section 71.11(i)(2). Moreover, 
    section 71.11 (i)(2) itself has been changed so that it better tracks 
    part 124, which makes final permit issuance decisions immediately 
    effective only where no comments requested a change in the draft 
    permit; otherwise, permits are effective than sooner than 30 days after 
    the issuance decision or following the conclusion of appeal 
    proceedings, as applicable.
        In response to comments which expressed concern that applicants 
    should be able to appeal a final permit decision even in the absence of 
    having commented on a draft permit, the Agency believes that applicants 
    can appeal if the final permit differs from the draft permit, even if 
    the applicant did not submit comments on the draft permit. The Agency 
    does not believe it would be appropriate to allow applicants to appeal 
    where the final permit is identical to the draft permit, and the 
    applicant had not commented on the draft permit. It is a far more 
    efficient use of resources to resolve permitting issues in the 
    administrative issuance process, rather than to allow applicants to 
    raise issues on draft permits for the first time on appeal. To further 
    clarify the ability of the applicant to appeal a final permit, the 
    following language has been added to section 71.11(l)(1): ``or other 
    new grounds that were not reasonably foreseeable during the public 
    comment period on the draft permit''.
        Section 71.11(l)(6) has been added, incorporating language from 40 
    CFR part 124. Part 124 establishes general procedures clarifying the 
    rules to which appellants are subject in all permit programs under part 
    124, and therefore EPA believes it is appropriate to extend these 
    provisions to part 71 as well. This section outlines procedures for 
    motions for reconsideration of appeals of final orders. It stipulates a 
    10 day deadline for motions, and notes that motions are to be directed 
    to the EAB, unless the case had been referred to the Administrator by 
    the Board, and in which the Administrator had issued the final order. 
    The effective date of the final order is not stayed unless specifically 
    so ordered by the Board.
        One commenter suggested that the proposal's requirement of a right 
    to appeal every permit decision would be overly burdensome, commenting 
    that even de minimis revisions would be subject to appeal. The EPA 
    notes that final part 71 permitting actions are final actions for 
    purposes of judicial review under section 307(b)(1) of the Act. 
    Consequently, EPA does not have the discretion to eliminate the 
    opportunity for judicial review of final part 71 permitting actions. 
    Moreover, EPA disagrees that requiring administrative appeal to the EAB 
    as a prerequisite to judicial review is either redundant or jeopardizes 
    a source's ability to rely on its permit. Requiring administrative 
    exhaustion of remedies is longstanding practice in EPA permit programs, 
    and EPA notes that States with approved part 70 programs generally 
    require administrative appeal as a prerequisite to challenging permits 
    in State court. Also, in requiring administrative exhaustion, 
    litigation in Federal court over permit actions will often be avoided, 
    thus conserving both public and private resources. Finally, since 
    pending administrative appeal sources will be able to rely on the 
    application shield, they will not be placed in any greater ``jeopardy'' 
    than if they had directly appealed the final permit to Federal court.
        Changes have been made to section 71.11(n) to replace the term 
    ``Administrator'' with ``permitting authority,'' to allow for those 
    circumstances where a State has been delegated a part 71 program by 
    EPA.
    
    IV. Administrative Requirements
    
    A. Docket
    
        The docket for this regulatory action is A-93-51. All the documents 
    referenced in this preamble fall into one of two categories. They are 
    either reference materials that are considered to be generally 
    available to the public, or they are memoranda and reports prepared 
    specifically for this rulemaking. Both types of documents can be found 
    in Docket No. A-93-51.
    
    B. Executive Order 12866
    
        Under Executive Order 12866 (58 FR 51735 (October 4, 1993)), the 
    Agency must determine whether the regulatory action is ``significant'' 
    and therefore subject to the Office of Management and Budget (OMB) 
    review and the requirements of the Executive Order. The Order defines 
    ``significant'' regulatory action as one that is likely to lead to a 
    rule that may:
        (1) Have an annual effect on the economy of $100 million or more, 
    adversely and materially affecting a sector of the economy, 
    productivity, competition, jobs, the environment, public health or 
    safety, or State, local or Tribal governments or communities;
        (2) Create a serious inconsistency or otherwise interfere with an 
    action taken or planned by another agency;
        (3) Materially alter the budgetary impact of entitlements, grants, 
    user fees, or loan program or the rights and obligation of recipients 
    thereof;
        (4) Raise novel legal or policy issues arising out of legal 
    mandates, the President's priorities, or the principles set forth in 
    the Executive Order.
        Pursuant to the terms of Executive Order 12866, it has been 
    determined that this rule is a ``significant'' regulatory action. As 
    such, this action was submitted to OMB for review. Changes made in 
    response to OMB suggestions or recommendations will be documented in 
    the public record.
        The EPA has estimated the annualized cost of the part 71 program 
    based on the number of sources that would be subject to part 71 
    permitting requirements in the 8 States where EPA
    
    [[Page 34227]]
    
    believes the program will be implemented. A survey of those States 
    showed that the number of part 71 sources in those States (many of 
    which are not heavily industrialized) is much smaller than EPA's 
    original estimates. The EPA had previously assumed that part 71 sources 
    in 8 States would comprise 16 percent of all title V sources. However, 
    in the States where EPA is likely to administer a part 71 program, the 
    part 71 source population comprises slightly less than 6 percent of all 
    title V sources. The estimated annualized cost of implementing the part 
    71 program is $19.8 million to the Federal government and $18.1 million 
    to respondents, for a total of $37.9 million which reflects industry's 
    total expected costs of complying with the program. Since any costs 
    incurred by the Agency in administering a program would be recaptured 
    through fees imposed on sources, the true cost to the Federal 
    government is zero. The requirements for the costs result from section 
    502(d) of title V which mandates that EPA develop a Federal operating 
    permits program. The draft regulatory impact analysis (RIA) was made 
    available for public comment as part of the April 27, 1995 proposal. 
    The primary difference between the current RIA and the prior draft is 
    that the RIA now assesses impacts based on the streamlined permit 
    revision procedures that were proposed for part 70 and 71 in August of 
    1995, in lieu of the more cumbersome 4-track permit revision procedure 
    that was contained in the part 71 proposal. The proposed program is 
    designed to improve air quality by: indirectly improving the quality of 
    State-administered operating permits programs; encouraging the adoption 
    of lower cost control strategies based on economic incentive 
    approaches; improving the effectiveness of enforcement and oversight of 
    source compliance; facilitating the implementation of other titles of 
    the Act, such as title I; and improving the quality of emissions data 
    and other source-related data.
    
    C. Regulatory Flexibility Act
    
        The Regulatory Flexibility Act (5 U.S.C. 601) requires EPA to 
    consider potential impacts of proposed regulations on small entities. 
    If a preliminary analysis indicates that a proposed regulation would 
    have a significant adverse economic impact on a substantial number of 
    small entities, then a regulatory flexibility analysis must be 
    prepared.
        The original part 70 rule and the recently proposed revisions to 
    part 70 were determined to not have a significant adverse impact on 
    small entities. See 57 FR 32250, 32294 (July 21, 1992), and 60 FR 
    45530, 45563 (Aug. 31, 1995). Similarly, a regulatory flexibility 
    screening analysis of the part 71 rule revealed that the rule would not 
    have a significant adverse impact on a substantial number of small 
    entities, since few small entities would be subject to part 71 
    permitting requirements as a result of the rule's deferral of the 
    requirement to obtain a permit for nonmajor sources.
        Consequently, I hereby certify that the part 71 regulations will 
    not have a significant adverse effect on a substantial number of small 
    entities.
    
    D. Paperwork Reduction Act
    
        The OMB has approved the information collection requirements 
    contained in this rule under the provisions of the Paperwork Reduction 
    Act, 44 U.S.C. 3501 et. seq. and has assigned OMB control number 2060-
    0336.
        The information is planned to be collected to enable EPA to carry 
    out its obligations under the Act to determine which sources are 
    subject to the Federal Operating Permits Program and what requirements 
    should be included in permits for sources subject to the program. 
    Responses to the collection of information will be mandatory under 
    section 71.5(a) which requires owners or operators of sources subject 
    to the program to submit a timely and complete permit application and 
    under sections 71.6 (a) and (c) which require that permits include 
    requirements related to recordkeeping and reporting. As provided in 42 
    U.S.C. 7661b(e), sources may assert a business confidentiality claim 
    for the information collected under section 114(c) of the Act.
        The annual average burden on sources for the collection of 
    information is approximately 678,000 hours per year, or 329 hours per 
    source. The annual cost for the collection of information to 
    respondents is $18.1 million per year. The EPA has estimated the 
    annualized costs based on the number of sources that would be subject 
    to part 71 permitting requirements in the 8 States where EPA believes 
    the program will be implemented, most of which have fewer than average 
    number of part 71 sources per State. There is no burden for State and 
    local agencies. The annual cost to the Federal government is $19.8 
    million (assuming part 71 programs are delegated), which is recovered 
    from sources through permit fees. Thus, the total annual cost to 
    sources would be $37.9 million. Burden means the total time, effort, or 
    financial resources expended by persons to generate, maintain, retain, 
    or disclose or provide information to or for a Federal agency. This 
    includes the time needed to review instructions; develop, acquire, 
    install, and utilize technology and systems for the purposes of 
    collecting, validating, and verifying information, processing and 
    maintaining information, and disclosing and providing information; 
    adjust the existing ways to comply with any previously applicable 
    instructions and requirements; train personnel to be able to respond to 
    a collection of information; search data sources; complete and review 
    the collection of information; and transmit or otherwise disclose the 
    information.
        An Agency may not conduct or sponsor, and a person is not required 
    to respond to a collection of information unless it displays a 
    currently valid OMB control number. The OMB control numbers for EPA's 
    regulations are listed in 40 CFR Part 9 and 48 CFR Chapter 15. The EPA 
    is amending the table in 40 CFR part 9 of currently approved 
    information collection request (ICR) control numbers issued by OMB for 
    various regulations to list the information requirements contained in 
    this final rule.
        Send comments on the Agency's need for this information, the 
    accuracy of the provided burden estimates, and any suggested methods 
    for minimizing respondent burden, including through the use of 
    automated collection techniques, to the Director, Regulatory 
    Information Division, Office of Policy, Planning, and Evaluation, U.S. 
    Environmental Protection Agency (2136), 401 M Street, S.W., Washington, 
    DC 20460, and to the Office of Information and Regulatory Affairs, 
    Office of Management and Budget, 725 17th St., N.W., Washington, DC 
    20503, marked ``Attention: Desk Officer for EPA.'' Include the ICR 
    number in any correspondence.
    
    E. Unfunded Mandates Reform Act
    
        As noted in the ICR document, today's action imposes no costs on 
    State, local and Tribal governments. This is because the EPA incurs all 
    costs in cases where it implements a part 71 program. A State, local, 
    or Tribal government will incur costs where it elects to take 
    delegation of a part 71 program. As noted in the ICR document, EPA 
    expects that, of the estimated eight part 71 programs, States will take 
    delegation of all eight programs. However, the costs of running these 
    delegated programs do not represent costs imposed by today's action. 
    This is because the costs of running a delegated part 71 program are 
    essentially the same
    
    [[Page 34228]]
    
    as those of running an approved part 70 program. Furthermore, taking 
    delegation is optional on the part of States. Regardless of whether a 
    State, local, or Tribal agency chooses to take delegation of a part 71 
    program, the costs to these agencies imposed by this rule over and 
    above the costs of existing part 70 requirements are zero.
        Regarding the private sector, the EPA estimates that the total cost 
    of complying with the part 71 program would be $37.9 million per year, 
    assuming that the part 71 program is in effect in 8 States. The 
    estimated costs of collection of information would be $18.1 million per 
    year, and $19.8 million would be collected in fees.
        For these reasons, EPA believes that the total direct costs to 
    industry under today's action would not exceed $100 million in any 1 
    year. Therefore, the Agency concludes that it is not required by 
    Section 202 of the Unfunded Mandates Reform Act of 1995 to provide a 
    written statement to accompany this regulatory action because 
    promulgation of the rule would not result in the expenditure by State, 
    local, and Tribal governments, in the aggregate or by the private 
    sector, of $100,000,000 or more in any 1 year.
    
    F. Submission to Congress and the General Accounting Office
    
        Under section 801(a)(1)(A) of the Administrative Procedure Act 
    (APA), as amended by the Small Business Regulatory Enforcement Fairness 
    Act of 1996, EPA submitted a report containing this rule and other 
    required information to the U.S. Senate, the U.S. House of 
    Representatives, and the Comptroller General of the General Accounting 
    Office prior to publication of the rule in today's Federal Register. 
    This rule is not a ``major rule'' as defined by section 804(2) of the 
    APA as amended.
    
    List of Subjects
    
    40 CFR Part 9
    
        Reporting and Recordkeeping Requirements
    
    40 CFR Part 55
    
         Environmental Protection Air pollution control, Outer continental 
    shelf, Operating permits.
    
    40 CFR Part 71
    
        Air pollution control, Prevention of significant deterioration, New 
    source review, Fugitive emissions, Particulate matter, Volatile organic 
    compounds, Nitrogen dioxide, Carbon monoxide, Hydrocarbons, Lead, 
    Operating permits, Indian Tribes, Air pollution control--Tribal 
    authority.
    
        Dated: June 19, 1996.
    Carol M. Browner,
    Administrator.
    
        For the reasons set out in the preamble, title 40, chapter I of the 
    Code of Federal Regulations is amended as set forth below.
    
    PART 9--[AMENDED]
    
        1. In Part 9:
        a. The authority citation for part 9 continues to read as follows:
    
        Authority: 7 U.S.C. 135 et seq., 136-136y; 15 U.S.C. 2001, 2003, 
    2005, 2006, 2601-2671; 21 U.S.C. 331j, 346a, 348; 31 U.S.C. 9701; 33 
    U.S.C. 1251 et seq., 1311, 1313d, 1314, 1318, 1321, 1326, 1330, 
    1342, 1344, 1345 (d) and (e), 1361; E.O. 11735, 38 FR 21243, 3 CFR, 
    1971-1975 Comp. p. 973; 42 U.S.C. 241, 242b, 243, 246, 300f, 300g, 
    300g-1, 300g-2, 300g-3, 300g-4, 300g-5, 300g-6, 300j-1, 300j-2, 
    300j-3, 300j-4, 300j-9, 1857 et seq., 6901-6992k, 7401-7671q, 7542, 
    9601-9657, 11023, 11048.
    
        b. Section 9.1 is amended by adding the new entries to the table 
    under the indicated heading in numerical order to read as follows:
    
    
    Sec. 9.1  OMB approvals under the Paperwork Reduction Act.
    
    * * * * *
    
    ------------------------------------------------------------------------
                                                                 OMB control
                          40 CFR Citation                            No.    
    ------------------------------------------------------------------------
                                                                            
                      *        *        *        *        *                 
                                                                            
                        Federal Operating Permit Programs                   
    71.5.......................................................    2060-0336
    71.6(a),(c),(d),(g)........................................    2060-0336
    71.7.......................................................    2060-0336
    71.9(e)-(j)................................................    2060-0336
                                                                            
                      *        *        *        *        *                 
    ------------------------------------------------------------------------
    
    PART 55--[AMENDED]
    
        2. The authority citation for part 55 continues to read as follows:
    
        Authority: Section 328 of the Clean Air Act (Act) (42 U.S.C. 
    7401, et seq.) as amended by Public Law 101-549.
    
        3. Section 55.6 is amended by adding paragraph (c)(3) to read as 
    follows:
    
    
    Sec. 55.6  Permit requirements.
    
    * * * * *
        (c) * * *
        (3) If the COA does not have an operating permits program approved 
    pursuant to 40 CFR part 70 or if EPA has determined that the COA is not 
    adequately implementing an approved program, the applicable 
    requirements of 40 CFR part 71, the Federal operating permits program, 
    shall apply to the OCS sources. The applicable requirements of 40 CFR 
    part 71 will be implemented and enforced by the Administrator. The 
    Administrator may delegate the authority to implement and enforce all 
    or part of a Federal operating permits program to a State pursuant to 
    Sec. 55.11 of this part.
    * * * * *
        4. Section 55.10 is amended by revising paragraph (a)(1) and by 
    adding paragraph (b) to read as follows:
    
    
    Sec. 55.10  Fees.
    
        (a) * * *
        (1) The EPA will calculate and collect operating permit fees from 
    OCS sources in accordance with the requirements of 40 CFR part 71.
    * * * * *
        (b) The OCS sources located beyond 25 miles of States' seaward 
    boundaries. The EPA will calculate and collect operating permit fees 
    from OCS sources in accordance with the requirements of 40 CFR part 71.
        5. Section 55.13 is amended by adding paragraph (f) to read as 
    follows:
    
    
    Sec. 55.13  Federal requirements that apply to OCS sources.
    
    * * * * *
        (f) 40 CFR part 71 shall apply to OCS sources:
        (1) Located within 25 miles of States' seaward boundaries if the 
    requirements of 40 CFR part 71 are in effect in the COA.
        (2) Located beyond 25 miles of States' seaward boundaries.
        (3) When an operating permits program approved pursuant to 40 CFR 
    part 70 is in effect in the COA and a Federal operating permit is 
    issued to satisfy an EPA objection pursuant to 40 CFR 71.4(e).
    * * * * *
    
    PART 71--[AMENDED]
    
        6. The authority citation for part 71 continues to read as follows:
    
        Authority: 42 U.S.C. 7401 et seq.
    
        7. Subpart A of part 71 consisting of Secs. 71.1 through 71.12 is 
    added to read as follows:
    
    Subpart A--Operating Permits
    
    Sec.
    71.1  Program overview.
    71.2  Definitions.
    71.3  Sources subject to permitting requirements.
    71.4  Program implementation.
    71.5  Permit applications.
    71.6  Permit content.
    71.7  Permit issuance, renewal, reopenings, and revisions.
    71.8  Affected State review.
    71.9  Permit fees.
    71.10  Delegation of part 71 program.
    
    [[Page 34229]]
    
    71.11  Administrative record, public participation, and 
    administrative review.
    71.12  Prohibited acts.
    
    Subpart A--Operating Permits
    
    
    Sec. 71.1  Program overview.
    
        (a) This part sets forth the comprehensive Federal air quality 
    operating permits permitting program consistent with the requirements 
    of title V of the Act (42 U.S.C. 7401 et seq.) and defines the 
    requirements and the corresponding standards and procedures by which 
    the Administrator will issue operating permits. This permitting program 
    is designed to promote timely and efficient implementation of goals and 
    requirements of the Act.
        (b) All sources subject to the operating permit requirements of 
    title V and this part shall have a permit to operate that assures 
    compliance by the source with all applicable requirements.
        (c) The requirements of this part, including provisions regarding 
    schedules for submission and approval or disapproval of permit 
    applications, shall apply to the permitting of affected sources under 
    the acid rain program, except as provided herein or as modified by 
    title IV of the Act and 40 CFR parts 72 through 78.
        (d) Issuance of permits under this part may be coordinated with 
    issuance of permits under the Resource Conservation and Recovery Act 
    (42 U.S.C. 6901 et seq.) and under the Clean Water Act (33 U.S.C. 1251 
    et seq.), whether issued by the State, the U.S. Environmental 
    Protection Agency (EPA), or the U.S. Army Corps of Engineers.
        (e) Nothing in this part shall prevent a State from administering 
    an operating permits program and establishing more stringent 
    requirements not inconsistent with the Act.
    
    
    Sec. 71.2  Definitions.
    
        The following definitions apply to part 71. Except as specifically 
    provided in this section, terms used in this part retain the meaning 
    accorded them under the applicable requirements of the Act.
        Act means the Clean Air Act, as amended, 42 U.S.C. 7401 et seq.
        Affected source shall have the meaning given to it in 40 CFR 72.2.
        Affected States are:
        (1) All States and Tribal areas whose air quality may be affected 
    and that are contiguous to the State or Tribal area in which the 
    permit, permit modification or permit renewal is being proposed; or 
    that are within 50 miles of the permitted source. A Tribe and any 
    associated Tribal area shall be treated as a State under this paragraph 
    (1) only if EPA has determined that the Tribe is an eligible Tribe.
        (2) The State or Tribal area in which a part 71 permit, permit 
    modification, or permit renewal is being proposed. A Tribe and any 
    associated Tribal area shall be treated as a State under this paragraph 
    (2) only if EPA has determined that the Tribe is an eligible Tribe.
        (3) Those areas within the jurisdiction of the air pollution 
    control agency for the area in which a part 71 permit, permit 
    modification, or permit renewal is being proposed.
        Affected unit shall have the meaning given to it in 40 CFR 72.2.
        Applicable requirement means all of the following as they apply to 
    emissions units in a part 71 source (including requirements that have 
    been promulgated or approved by EPA through rulemaking at the time of 
    issuance but have future compliance dates):
        (1) Any standard or other requirement provided for in the 
    applicable implementation plan approved or promulgated by EPA through 
    rulemaking under title I of the Act that implements the relevant 
    requirements of the Act, including any revisions to that plan 
    promulgated in part 52 of this chapter;
        (2) Any term or condition of any preconstruction permits issued 
    pursuant to regulations approved or promulgated through rulemaking 
    under title I, including parts C or D, of the Act;
        (3) Any standard or other requirement under section 111 of the Act, 
    including section 111(d);
        (4) Any standard or other requirement under section 112 of the Act, 
    including any requirement concerning accident prevention under section 
    112(r)(7) of the Act;
        (5) Any standard or other requirement of the acid rain program 
    under title IV of the Act or 40 CFR parts 72 through 78;
        (6) Any requirements established pursuant to section 114(a)(3) or 
    504(b) of the Act;
        (7) Any standard or other requirement governing solid waste 
    incineration, under section 129 of the Act;
        (8) Any standard or other requirement for consumer and commercial 
    products, under section 183(e) of the Act;
        (9) Any standard or other requirement for tank vessels, under 
    section 183(f) of the Act;
        (10) Any standard or other requirement of the program to control 
    air pollution from outer continental shelf sources, under section 328 
    of the Act;
        (11) Any standard or other requirement of the regulations 
    promulgated at 40 CFR part 82 to protect stratospheric ozone under 
    title VI of the Act, unless the Administrator has determined that such 
    requirements need not be contained in a title V permit; and
        (12) Any national ambient air quality standard or increment or 
    visibility requirement under part C of title I of the Act, but only as 
    it would apply to temporary sources permitted pursuant to section 
    504(e) of the Act.
        Delegate agency means the State air pollution control agency, local 
    agency, other State agency, Tribal agency, or other agency authorized 
    by the Administrator pursuant to Sec. 71.10 to carry out all or part of 
    a permit program under part 71.
        Designated representative shall have the meaning given to it in 
    section 402(26) of the Act and 40 CFR 72.2.
        Draft permit means the version of a permit for which the permitting 
    authority offers public participation under Sec. 71.7 or Sec. 71.11 and 
    affected State review under Sec. 71.8.
        Eligible Indian Tribe or eligible Tribe means a Tribe that has been 
    determined by EPA to meet the criteria for being treated in the same 
    manner as a State, pursuant to the regulations implementing section 
    301(d)(2) of the Act.
        Emissions allowable under the permit means a federally enforceable 
    permit term or condition determined at issuance to be required by an 
    applicable requirement that establishes an emissions limit (including a 
    work practice standard) or a federally enforceable emissions cap that 
    the source has assumed to avoid an applicable requirement to which the 
    source would otherwise be subject.
        Emissions unit means any part or activity of a stationary source 
    that emits or has the potential to emit any regulated air pollutant or 
    any pollutant listed under section 112(b) of the Act. This term is not 
    meant to alter or affect the definition of the term ``unit'' for 
    purposes of title IV of the Act.
        EPA or the Administrator means the Administrator of the U.S. 
    Environmental Protection Agency (EPA) or his or her designee.
        Federal Indian reservation, Indian reservation or reservation means 
    all land within the limits of any Indian reservation under the 
    jurisdiction of the United States Government, notwithstanding the 
    issuance of any patent, and including rights-of-way running through the 
    reservation.
        Final permit means the version of a part 71 permit issued by the 
    permitting
    
    [[Page 34230]]
    
    authority that has completed all review procedures required by 
    Secs. 71.7, 71.8, and 71.11.
        Fugitive emissions are those emissions which could not reasonably 
    pass through a stack, chimney, vent, or other functionally-equivalent 
    opening.
        General permit means a part 71 permit that meets the requirements 
    of Sec. 71.6(d).
        Indian Tribe or Tribe means any Indian Tribe, band, nation, or 
    other organized group or community, including any Alaskan native 
    village, which is federally recognized as eligible for the special 
    programs and services provided by the United States to Indians because 
    of their status as Indians.
        Major source means any stationary source (or any group of 
    stationary sources that are located on one or more contiguous or 
    adjacent properties, and are under common control of the same person 
    (or persons under common control)), belonging to a single major 
    industrial grouping and that are described in paragraph (1), (2), or 
    (3) of this definition. For the purposes of defining ``major source,'' 
    a stationary source or group of stationary sources shall be considered 
    part of a single industrial grouping if all of the pollutant emitting 
    activities at such source or group of sources on contiguous or adjacent 
    properties belong to the same Major Group (i.e., all have the same two-
    digit code) as described in the Standard Industrial Classification 
    Manual, 1987.
        (1) A major source under section 112 of the Act, which is defined 
    as:
        (i) For pollutants other than radionuclides, any stationary source 
    or group of stationary sources located within a contiguous area and 
    under common control that emits or has the potential to emit, in the 
    aggregate, 10 tpy or more of any hazardous air pollutant which has been 
    listed pursuant to section 112(b) of the Act, 25 tpy or more of any 
    combination of such hazardous air pollutants, or such lesser quantity 
    as the Administrator may establish by rule. Notwithstanding the 
    preceding sentence, emissions from any oil or gas exploration or 
    production well (with its associated equipment) and emissions from any 
    pipeline compressor or pump station shall not be aggregated with 
    emissions from other similar units, whether or not such units are in a 
    contiguous area or under common control, to determine whether such 
    units or stations are major sources; or
        (ii) For radionuclides, ``major source'' shall have the meaning 
    specified by the Administrator by rule.
        (2) A major stationary source of air pollutants or any group of 
    stationary sources as defined in section 302 of the Act, that directly 
    emits, or has the potential to emit, 100 tpy or more of any air 
    pollutant (including any major source of fugitive emissions of any such 
    pollutant, as determined by rule by the Administrator). The fugitive 
    emissions of a stationary source shall not be considered in determining 
    whether it is a major stationary source for the purposes of section 
    302(j) of the Act, unless the source belongs to one of the following 
    categories of stationary source:
        (i) Coal cleaning plants (with thermal dryers);
        (ii) Kraft pulp mills;
        (iii) Portland cement plants;
        (iv) Primary zinc smelters;
        (v) Iron and steel mills;
        (vi) Primary aluminum ore reduction plants;
        (vii) Primary copper smelters;
        (viii) Municipal incinerators capable of charging more than 250 
    tons of refuse per day;
        (ix) Hydrofluoric, sulfuric, or nitric acid plants;
        (x) Petroleum refineries;
        (xi) Lime plants;
        (xii) Phosphate rock processing plants;
        (xiii) Coke oven batteries;
        (xiv) Sulfur recovery plants;
        (xv) Carbon black plants (furnace process);
        (xvi) Primary lead smelters;
        (xvii) Fuel conversion plants;
        (xviii) Sintering plants;
        (xix) Secondary metal production plants;
        (xx) Chemical process plants;
        (xxi) Fossil-fuel boilers (or combination thereof) totaling more 
    than 250 million British thermal units per hour heat input;
        (xxii) Petroleum storage and transfer units with a total storage 
    capacity exceeding 300,000 barrels;
        (xxiii) Taconite ore processing plants;
        (xxiv) Glass fiber processing plants;
        (xxv) Charcoal production plants;
        (xxvi) Fossil-fuel-fired steam electric plants of more than 250 
    million British thermal units per hour heat input; or
        (xxvii) Any other stationary source category which, as of August 7, 
    1980, is being regulated under section 111 or 112 of the Act.
        (3) A major stationary source as defined in part D of title I of 
    the Act, including:
        (i) For ozone nonattainment areas, sources with the potential to 
    emit 100 tpy or more of volatile organic compounds or oxides of 
    nitrogen in areas classified as ``marginal'' or ``moderate,'' 50 tpy or 
    more in areas classified as ``serious''; 25 tpy or more in areas 
    classified as ``severe,'' and 10 tpy or more in areas classified as 
    ``extreme''; except that the references in this paragraph (3)(i) to 
    100, 50, 25, and 10 tpy of nitrogen oxides shall not apply with respect 
    to any source for which the Administrator has made a finding, under 
    section 182(f) (1) or (2) of the Act, that requirements under section 
    182(f) of the Act do not apply;
        (ii) For ozone transport regions established pursuant to section 
    184 of the Act, sources with the potential to emit 50 tpy or more of 
    volatile organic compounds;
        (iii) For carbon monoxide nonattainment areas:
        (A) That are classified as ``serious,'' and
        (B) in which stationary sources contribute significantly to carbon 
    monoxide levels as determined under rules issued by the Administrator, 
    sources with the potential to emit 50 tpy or more of carbon monoxide; 
    and
        (iv) For particulate matter (PM-10) nonattainment areas classified 
    as ``serious,'' sources with the potential to emit 70 tpy or more of 
    PM-10.
        Part 70 permit means any permit or group of permits covering a part 
    70 source that has been issued, renewed, amended or revised pursuant to 
    40 CFR part 70.
        Part 70 program or State program means a program approved by the 
    Administrator under 40 CFR part 70.
        Part 70 source means any source subject to the permitting 
    requirements of 40 CFR part 70, as provided in Secs. 70.3(a) and 
    70.3(b).
        Part 71 permit, or permit (unless the context suggests otherwise) 
    means any permit or group of permits covering a part 71 source that has 
    been issued, renewed, amended or revised pursuant to this part.
        Part 71 program means a Federal operating permits program under 
    this part.
        Part 71 source means any source subject to the permitting 
    requirements of this part, as provided in Secs. 71.3(a) and 71.3(b).
        Permit modification means a revision to a part 71 permit that meets 
    the requirements of Sec. 71.7(e).
        Permit program costs means all reasonable (direct and indirect) 
    costs required to administer an operating permits program, as set forth 
    in Sec. 71.9(b).
        Permit revision means any permit modification or administrative 
    permit amendment.
        Permitting authority means one of the following:
        (1) The Administrator, in the case of EPA-implemented programs;
    
    [[Page 34231]]
    
        (2) A delegate agency authorized by the Administrator to carry out 
    a Federal permit program under this part; or
        (3) The State air pollution control agency, local agency, other 
    State agency, Indian Tribe, or other agency authorized by the 
    Administrator to carry out a permit program under 40 CFR part 70.
        Proposed permit means the version of a permit that the delegate 
    agency proposes to issue and forwards to the Administrator for review 
    in compliance with Sec. 71.10(d).
        Regulated air pollutant means the following:
        (1) Nitrogen oxides or any volatile organic compounds;
        (2) Any pollutant for which a national ambient air quality standard 
    has been promulgated;
        (3) Any pollutant that is subject to any standard promulgated under 
    section 111 of the Act;
        (4) Any Class I or II substance subject to a standard promulgated 
    under or established by title VI of the Act; or
        (5) Any pollutant subject to a standard promulgated under section 
    112 of the Act or other requirements established under section 112 of 
    the Act, including sections 112 (g), (j), and (r) of the Act, including 
    the following:
        (i) Any pollutant subject to requirements under section 112(j) of 
    the Act. If the Administrator fails to promulgate a standard by the 
    date established pursuant to section 112(e) of the Act, any pollutant 
    for which a subject source would be major shall be considered to be 
    regulated on the date 18 months after the applicable date established 
    pursuant to section 112(e) of the Act; and
        (ii) Any pollutant for which the requirements of section 112(g)(2) 
    of the Act have been met, but only with respect to the individual 
    source subject to section 112(g)(2) requirements.
        Regulated pollutant (for fee calculation), which is used only for 
    purposes of Sec. 71.9(c), means any regulated air pollutant except the 
    following:
        (1) Carbon monoxide;
        (2) Any pollutant that is a regulated air pollutant solely because 
    it is a Class I or II substance subject to a standard promulgated under 
    or established by title VI of the Act; or
        (3) Any pollutant that is a regulated air pollutant solely because 
    it is subject to a standard or regulation under section 112(r) of the 
    Act.
        Renewal means the process by which a permit is reissued at the end 
    of its term.
        Responsible official means one of the following:
        (1) For a corporation: a president, secretary, treasurer, or vice-
    president of the corporation in charge of a principal business 
    function, or any other person who performs similar policy or decision-
    making functions for the corporation, or a duly authorized 
    representative of such person if the representative is responsible for 
    the overall operation of one or more manufacturing, production, or 
    operating facilities applying for or subject to a permit and either:
        (i) the facilities employ more than 250 persons or have gross 
    annual sales or expenditures exceeding $25 million (in second quarter 
    1980 dollars); or
        (ii) the delegation of authority to such representative is approved 
    in advance by the permitting authority;
        (2) For a partnership or sole proprietorship: a general partner or 
    the proprietor, respectively;
        (3) For a municipality, State, Federal, or other public agency: 
    Either a principal executive officer or ranking elected official. For 
    the purposes of this part, a principal executive officer of a Federal 
    agency includes the chief executive officer having responsibility for 
    the overall operations of a principal geographic unit of the agency 
    (e.g., a Regional Administrator of EPA); or
        (4) For affected sources:
        (i) The designated representative insofar as actions, standards, 
    requirements, or prohibitions under title IV of the Act or 40 CFR parts 
    72 through 78 are concerned; and
        (ii) The designated representative for any other purposes under 
    part 71.
        Section 502(b)(10) changes are changes that contravene an express 
    permit term. Such changes do not include changes that would violate 
    applicable requirements or contravene federally enforceable permit 
    terms and conditions that are monitoring (including test methods), 
    recordkeeping, reporting, or compliance certification requirements.
        State means any non-Federal permitting authority, including any 
    local agency, interstate association, or statewide program. The term 
    ``State'' also includes the District of Columbia, the Commonwealth of 
    Puerto Rico, the Virgin Islands, Guam, American Samoa, and the 
    Commonwealth of the Northern Marianas Islands. Where such meaning is 
    clear from the context, ``State'' shall have its conventional meaning. 
    For purposes of the acid rain program, the term ``State'' shall be 
    limited to authorities within the 48 contiguous States and the District 
    of Columbia as provided in section 402(14) of the Act.
        Stationary source means any building, structure, facility, or 
    installation that emits or may emit any regulated air pollutant or any 
    pollutant listed under section 112(b) of the Act.
    
    
    Sec. 71.3  Sources Subject to Permitting Requirements.
    
        (a) Part 71 sources. The following sources are subject to the 
    permitting requirements under this part:
        (1) Any major source;
        (2) Any source, including an area source, subject to a standard, 
    limitation, or other requirement under section 111 of the Act;
        (3) Any source, including an area source, subject to a standard or 
    other requirement under section 112 of the Act, except that a source is 
    not required to obtain a permit solely because it is subject to 
    regulations or requirements under section 112(r) of the Act;
        (4) Any affected source; and
        (5) Any source in a source category designated by the Administrator 
    pursuant to this section.
        (b) Source category exemptions. (1) All sources listed in paragraph 
    (a) of this section that are not major sources, affected sources, or 
    solid waste incineration units required to obtain a permit pursuant to 
    section 129(e) of the Act are exempted from the obligation to obtain a 
    part 71 permit until such time as the Administrator completes a 
    rulemaking to determine how the program should be structured for 
    nonmajor sources and the appropriateness of any permanent exemptions in 
    addition to those provided for in paragraph (b)(4) of this section.
        (2) In the case of nonmajor sources subject to a standard or other 
    requirement under either section 111 or 112 of the Act after July 21, 
    1992 publication, the Administrator will determine whether to exempt 
    any or all such applicable sources from the requirement to obtain a 
    part 70 or part 71 permit at the time that the new standard is 
    promulgated.
        (3) Any source listed in paragraph (a) of this section exempt from 
    the requirement to obtain a permit under this section may opt to apply 
    for a permit under a part 71 program.
        (4) The following source categories are exempted from the 
    obligation to obtain a part 71 permit:
        (i) All sources and source categories that would be required to 
    obtain a permit solely because they are subject to 40 CFR part 60, 
    Subpart AAA---Standards of Performance for New Residential Wood 
    Heaters; and
        (ii) All sources and source categories that would be required to 
    obtain a permit solely because they are subject to 40 CFR part 61, 
    Subpart M--National Emission Standard for Hazardous Air
    
    [[Page 34232]]
    
    Pollutants for Asbestos, Sec. 61.145, Standard for Demolition and 
    Renovation.
        (c) Emissions units and part 71 sources. (1) For major sources, the 
    permitting authority shall include in the permit all applicable 
    requirements for all relevant emissions units in the major source.
        (2) For any nonmajor source subject to the part 71 program under 
    paragraphs (a) or (b) of this section, the permitting authority shall 
    include in the permit all applicable requirements applicable to 
    emissions units that cause the source to be subject to the part 71 
    program.
        (d) Fugitive emissions. Fugitive emissions from a part 71 source 
    shall be included in the permit application and the part 71 permit in 
    the same manner as stack emissions, regardless of whether the source 
    category in question is included in the list of sources contained in 
    the definition of major source.
    
    
    Sec. 71.4  Program implementation.
    
        (a) Part 71 programs for States. The Administrator will administer 
    and enforce a full or partial operating permits program for a State 
    (excluding Tribal areas) in the following situations:
        (1) A program for a State meeting the requirements of part 70 of 
    this chapter has not been granted full approval under Sec. 70.4 of this 
    chapter by the Administrator by July 31, 1996, and the State's part 70 
    program has not been granted interim approval under Sec. 70.4(d) of 
    this chapter for a period extending beyond July 31, 1996. The effective 
    date of such a part 71 program is July 31, 1996.
        (2) An operating permits program for a State which was granted 
    interim approval under Sec. 70.4(d) of this chapter has not been 
    granted full approval by the Administrator by the expiration of the 
    interim approval period or July 31, 1996, whichever is later. Such a 
    part 71 program shall be effective upon expiration of the interim 
    approval or July 31, 1996 whichever is later.
        (3) Any partial part 71 program will be effective only in those 
    portions of a State that are not covered by a partial part 70 program 
    that has been granted full or interim approval by the Administrator 
    pursuant to Sec. 70.4(c) of this chapter.
        (b) Part 71 programs for Tribal areas. The Administrator may 
    administer and enforce an operating permits program for a Tribal area, 
    as defined in Sec. 71.2, or by a rulemaking, when an operating permits 
    program for the area which meets the requirements of part 70 of this 
    chapter has not been granted full or interim approval by the 
    Administrator by July 31, 1996.
        (1) [Reserved]
        (2) The effective date of a part 71 program for a Tribal area shall 
    be November 15, 1997.
        (3) Notwithstanding paragraph (b)(2) of this section, the 
    Administrator, in consultation with the governing body of the Tribal 
    area, may adopt an earlier effective date.
        (4) Notwithstanding paragraph (i)(2) of this section, within 2 
    years of the effective date of the part 71 program for the Tribal area, 
    the Administrator shall take final action on permit applications from 
    part 71 sources that are submitted within the first full year after the 
    effective date of the part 71 program.
        (c) Part 71 programs imposed due to inadequate implementation. (1) 
    The Administrator will administer and enforce an operating permits 
    program for a permitting authority if the Administrator has notified 
    the permitting authority, in accordance with Sec. 70.10(b)(1) of this 
    chapter, of the Administrator's determination that a permitting 
    authority is not adequately administering or enforcing its approved 
    operating permits program, or any portion thereof, and the permitting 
    authority fails to do either of the following:
        (i) Correct the deficiencies within 18 months after the 
    Administrator issues the notice; or
        (ii) Take significant action to assure adequate administration and 
    enforcement of the program within 90 days of the Administrator's 
    notice.
        (2) The effective date of a part 71 program promulgated in 
    accordance with this paragraph (c) shall be:
        (i) Two years after the Administrator's notice if the permitting 
    authority has not corrected the deficiency within 18 months after the 
    date of the Administrator's notice; or
        (ii) Such earlier time as the Administrator determines appropriate 
    if the permitting authority fails, within 90 days of the 
    Administrator's notice, to take significant action to assure adequate 
    administration and enforcement of the program.
        (d) Part 71 programs for OCS sources. (1) Using the procedures of 
    this part, the Administrator will issue permits to any source which is 
    an outer continental shelf (OCS) source, as defined under Sec. 55.2 of 
    this chapter, is subject to the requirements of part 55 of this chapter 
    and section 328(a) of the Act, is subject to the requirement to obtain 
    a permit under title V of the Act, and is either:
        (i) Located beyond 25 miles of States' seaward boundaries; or
        (ii) Located within 25 miles of States' seaward boundaries and a 
    part 71 program is being administered and enforced by the Administrator 
    for the corresponding onshore area, as defined in Sec. 55.2 of this 
    chapter, for that source.
        (2) The requirements of Sec. 71.4(d)(1)(i) shall apply on July 31, 
    1996.
        (3) The requirements of Sec. 71.4(d)(1)(ii) apply upon the 
    effective date of a part 71 program for the corresponding onshore area.
        (e) Part 71 program for permits issued to satisfy an EPA objection. 
    Using the procedures of this part and 40 CFR 70.8 (c) or (d), or 40 CFR 
    70.7(g)(4) or (5) (i) and (ii), as appropriate, the Administrator will 
    deny, terminate, revise, revoke or reissue a permit which has been 
    proposed or issued by a permitting authority or will issue a part 71 
    permit when:
        (1) A permitting authority with an approved part 70 operating 
    permits program fails to respond to a timely objection to the issuance 
    of a permit made by the Administrator pursuant to section 505(b) of the 
    Act and Sec. 70.8(c) and (d) of this chapter.
        (2) The Administrator, under Sec. 70.7(g) of this chapter, finds 
    that cause exists to reopen a permit and the permitting authority fails 
    to either:
        (i) Submit to the Administrator a proposed determination of 
    termination, modification, or revocation and reissuance, as 
    appropriate; or
        (ii) Resolve any objection EPA makes to the permit which the 
    permitting authority proposes to issue in response to EPA's finding of 
    cause to reopen, and to terminate, revise, or revoke and reissue the 
    permit in accordance with that objection.
        (3) The requirements of this paragraph (e) shall apply on July 31, 
    1996.
        (f) Use of selected provisions of this part. The Administrator may 
    utilize any or all of the provisions of this part to administer the 
    permitting process for individual sources or take action on individual 
    permits, or may adopt through rulemaking portions of a State or Tribal 
    program in combination with provisions of this part to administer a 
    Federal program for the State or Tribal area in substitution of or 
    addition to the Federal program otherwise required by this part.
        (g) Public notice of part 71 programs. In taking action to 
    administer and enforce an operating permits program under this part, 
    the Administrator will publish a notice in the Federal Register 
    informing the public of such action and the effective date of any part 
    71 program as set forth in Sec. 71.4 (a), (b), (c), or (d)(1)(ii). The 
    publication of this part in the Federal Register on July 1, 1996
    
    [[Page 34233]]
    
    serves as the notice for the part 71 permit programs described in 
    Sec. 71.4(d)(1) (i) and (e). The EPA will also publish a notice in the 
    Federal Register of any delegation of a portion of the part 71 program 
    to a State, eligible Tribe, or local agency pursuant to the provisions 
    of Sec. 71.10. In addition to notices published in the Federal Register 
    under this paragraph (g), the Administrator will, to the extent 
    practicable, publish notice in a newspaper of general circulation 
    within the area subject to the part 71 program effectiveness or 
    delegation, and will send a letter to the Tribal governing body for an 
    Indian Tribe or the Governor (or his or her designee) of the affected 
    area to provide notice of such effectiveness or delegation.
        (h) Effect of limited deficiencies in State or Tribal programs. The 
    Administrator may administer and enforce a part 71 program in a State 
    or Tribal area even if only limited deficiencies exist either in the 
    initial program submittal for a State or eligible Tribe under part 70 
    of this chapter or in an existing State or Tribal program that has been 
    approved under part 70 of this chapter.
        (i) Transition plan for initial permit issuance. If a full or 
    partial part 71 program becomes effective in a State or Tribal area 
    prior to the issuance of part 70 permits to all part 70 sources under 
    an existing program that has been approved under part 70 of this 
    chapter, the Administrator shall take final action on initial permit 
    applications for all part 71 sources in accordance with the following 
    transition plan.
        (1) All part 71 sources that have not received part 70 permits 
    shall submit permit applications under this part within 1 year after 
    the effective date of the part 71 program.
        (2) Final action shall be taken on at least one-third of such 
    applications annually over a period not to exceed 3 years after such 
    effective date.
        (3) Any complete permit application containing an early reduction 
    demonstration under section 112(i)(5) of the Act shall be acted on 
    within 12 months of receipt of the complete application.
        (4) Submittal of permit applications and the permitting of affected 
    sources shall occur in accordance with the deadlines in title IV of the 
    Act and 40 CFR parts 72 through 78.
        (j) Delegation of part 71 programs. The Administrator may 
    promulgate a part 71 program in a State or Tribal area and delegate 
    part of the responsibility for administering the part 71 program to the 
    State or eligible Tribe in accordance with the provisions of 
    Sec. 71.10; however, delegation of a part of a program will not 
    constitute any type of approval of a State or Tribal operating permits 
    program under part 70 of this chapter. Where only selected portions of 
    a part 71 program are administered by the Administrator and the State 
    or eligible Tribe is delegated the remaining portions of the program, 
    the Delegation Agreement referred to in Sec. 71.10 will define the 
    respective roles of the State or eligible Tribe and the Administrator 
    in administering and enforcing the part 71 operating permits program.
        (k) EPA administration and enforcement of part 70 permits. When the 
    Administrator administers and enforces a part 71 program after a 
    determination and notice under Sec. 70.10(b)(1) of this chapter that a 
    State or Tribe is not adequately administering and enforcing an 
    operating permits program approved under part 70 of this chapter, the 
    Administrator will administer and enforce permits issued under the part 
    70 program until part 71 permits are issued using the procedures of 
    part 71. Until such time as part 70 permits are replaced by part 71 
    permits, the Administrator will revise, reopen, revise, terminate, or 
    revoke and reissue part 70 permits using the procedures of part 71 and 
    will assess and collect fees in accordance with the provisions of 
    Sec. 71.9.
        (l) Transition to approved part 70 program. The Administrator will 
    suspend the issuance of part 71 permits promptly upon publication of 
    notice of approval of a State or Tribal operating permits program that 
    meets the requirements of part 70 of this chapter. The Administrator 
    may retain jurisdiction over the part 71 permits for which the 
    administrative or judicial review process is not complete and will 
    address this issue in the notice of State program approval. After 
    approval of a State or Tribal program and the suspension of issuance of 
    part 71 permits by the Administrator:
        (1) The Administrator, or the permitting authority acting as the 
    Administrator's delegated agent, will continue to administer and 
    enforce part 71 permits until they are replaced by permits issued under 
    the approved part 70 program. Until such time as part 71 permits are 
    replaced by part 70 permits, the Administrator will revise, reopen, 
    revise, terminate, or revoke and reissue part 71 permits using the 
    procedures of the part 71 program. However, if the Administrator has 
    delegated authority to administer part 71 permits to a delegate agency, 
    the delegate agency will revise, reopen, terminate, or revoke and 
    reissue part 71 permits using the procedures of the approved part 70 
    program. If a part 71 permit expires prior to the issuance of a part 70 
    permit, all terms and conditions of the part 71 permit, including any 
    permit shield that may be granted pursuant to Sec. 71.6(f), shall 
    remain in effect until the part 70 permit is issued or denied, provided 
    that a timely and complete application for a permit renewal was 
    submitted to the permitting authority in accordance with the 
    requirements of the approved part 70 program.
        (2) A State or local agency or Indian Tribe with an approved part 
    70 operating permits program may issue part 70 permits for all sources 
    with part 71 permits in accordance with a permit issuance schedule 
    approved as part of the approved part 70 program or may issue part 70 
    permits to such sources at the expiration of the part 71 permits.
        (m) Exemption for certain territories. Upon petition by the 
    Governor of Guam, American Samoa, the Virgin Islands, or the 
    Commonwealth of the Northern Marianas Islands, the Administrator may 
    exempt any source or class of sources in such territory from the 
    requirement to have a part 71 permit under this chapter. Such an 
    exemption does not exempt such source or class of sources from any 
    requirement of section 112 of the Act, including the requirements of 
    section 112 (g) or (j).
        (1) Such exemption may be granted if the Administrator finds that 
    compliance with part 71 is not feasible or is unreasonable due to 
    unique geographical, meteorological, or economic factors of such 
    territory, or such other local factors as the Administrator deems 
    significant. Any such petition shall be considered in accordance with 
    section 307(d) of the Act, and any exemption granted under this 
    paragraph (m) shall be considered final action by the Administrator for 
    the purposes of section 307(b) of the Act.
        (2) The Administrator shall promptly notify the Committees on 
    Energy and Commerce and on Interior and Insular Affairs of the House of 
    Representatives and the Committees on Environment and Public Works and 
    on Energy and Natural Resources of the Senate upon receipt of any 
    petition under this paragraph (m) and of the approval or rejection of 
    such petition and the basis for such action.
        (n) Retention of records. The records for each draft, proposed, and 
    final permit application, renewal, or modification shall be kept by the 
    Administrator for a period of 5 years.
    
    
    Sec. 71.5  Permit applications.
    
        (a) Duty to apply. For each part 71 source, the owner or operator 
    shall submit a timely and complete permit
    
    [[Page 34234]]
    
    application in accordance with this section.
        (1) Timely application. (i) A timely application for a source which 
    does not have an existing operating permit issued by a State under the 
    State's approved part 70 program and is applying for a part 71 permit 
    for the first time is one that is submitted within 12 months after the 
    source becomes subject to the permit program or on or before such 
    earlier date as the permitting authority may establish. Sources 
    required to submit applications earlier than 12 months after the source 
    becomes subject to the permit program will be notified of the earlier 
    submittal date at least 6 months in advance of the date.
        (ii) Part 71 sources required to meet the requirements under 
    section 112(g) of the Act, or to have a permit under the 
    preconstruction review program approved into the applicable 
    implementation plan under part C or D of title I of the Act, shall file 
    a complete application to obtain the part 71 permit or permit revision 
    within 12 months after commencing operation or on or before such 
    earlier date as the permitting authority may establish. Sources 
    required to submit applications earlier than 12 months after the source 
    becomes subject to the permit program will be notified of the earlier 
    submittal date at least 6 months in advance of the date. Where an 
    existing part 70 or 71 permit would prohibit such construction or 
    change in operation, the source must obtain a permit revision before 
    commencing operation.
        (iii) For purposes of permit renewal, a timely application is one 
    that is submitted at least 6 months but not more that 18 months prior 
    to expiration of the part 70 or 71 permit.
        (iv) Applications for initial phase II acid rain permits shall be 
    submitted to the permitting authority by January 1, 1996 for sulfur 
    dioxide, and by January 1, 1998 for nitrogen oxides.
        (2) Complete application. To be deemed complete, an application 
    must provide all information required pursuant to paragraph (c) of this 
    section, except that applications for permit revision need supply such 
    information only if it is related to the proposed change. To be found 
    complete, an initial or renewal application must remit payment of fees 
    owed under the fee schedule established pursuant to Sec. 71.9(b). 
    Information required under paragraph (c) of this section must be 
    sufficient to evaluate the subject source and its application and to 
    determine all applicable requirements. A responsible official must 
    certify the submitted information consistent with paragraph (d) of this 
    section. Unless the permitting authority determines that an application 
    is not complete within 60 days of receipt of the application, such 
    application shall be deemed to be complete, except as otherwise 
    provided in Sec. 71.7(a)(4). If, while processing an application that 
    has been determined or deemed to be complete, the permitting authority 
    determines that additional information is necessary to evaluate or take 
    final action on that application, it may request such information in 
    writing and set a reasonable deadline for a response. The source's 
    ability to operate without a permit, as set forth in Sec. 71.7(b), 
    shall be in effect from the date the application is determined or 
    deemed to be complete until the final permit is issued, provided that 
    the applicant submits any requested additional information by the 
    deadline specified by the permitting authority.
        (3) Confidential information. An applicant may assert a business 
    confidentiality claim for information requested by the permitting 
    authority using procedures found at part 2, subpart B of this chapter.
        (b) Duty to supplement or correct application. Any applicant who 
    fails to submit any relevant facts or who has submitted incorrect 
    information in a permit application shall, upon becoming aware of such 
    failure or incorrect submittal, promptly submit such supplementary 
    facts or corrected information. In addition, an applicant shall provide 
    additional information as necessary to address any requirements that 
    become applicable to the source after the date it filed a complete 
    application but prior to release of a draft permit.
        (c) Standard application form and required information. The 
    permitting authority shall provide sources a standard application form 
    or forms. The permitting authority may use discretion in developing 
    application forms that best meet program needs and administrative 
    efficiency. The forms and attachments chosen, however, shall include 
    the elements specified below. An application may not omit information 
    needed to determine the applicability of, or to impose, any applicable 
    requirement, or to evaluate the fee amount required under the schedule 
    established pursuant to Sec. 71.9.
        (1) Identifying information, including company name and address (or 
    plant name and address if different from the company name), owner's 
    name and agent, and telephone number and names of plant site manager/
    contact.
        (2) A description of the source's processes and products (by 
    Standard Industrial Classification Code) including any associated with 
    each alternate scenario identified by the source.
        (3) The following emissions-related information:
        (i) All emissions of pollutants for which the source is major, and 
    all emissions of regulated air pollutants. A permit application shall 
    describe all emissions of regulated air pollutants emitted from any 
    emissions unit, except where such units are exempted under this 
    paragraph (c). The permitting authority shall require additional 
    information related to the emissions of air pollutants sufficient to 
    verify which requirements are applicable to the source, and other 
    information necessary to collect any permit fees owed under the fee 
    schedule established pursuant to Sec. 71.9(b).
        (ii) Identification and description of all points of emissions 
    described in paragraph (c)(3)(i) of this section in sufficient detail 
    to establish the basis for fees and applicability of requirements of 
    the Act.
        (iii) Emissions rates in tpy and in such terms as are necessary to 
    establish compliance consistent with the applicable standard reference 
    test method.
        (iv) The following information to the extent it is needed to 
    determine or regulate emissions: fuels, fuel use, raw materials, 
    production rates, and operating schedules.
        (v) Identification and description of air pollution control 
    equipment and compliance monitoring devices or activities.
        (vi) Limitations on source operation affecting emissions or any 
    work practice standards, where applicable, for all regulated pollutants 
    at the part 71 source.
        (vii) Other information required by any applicable requirement 
    (including information related to stack height limitations developed 
    pursuant to section 123 of the Act).
        (viii) Calculations on which the information in paragraphs (c)(3) 
    (i) through (vii) of this section is based.
        (4) The following air pollution control requirements:
        (i) Citation and description of all applicable requirements; and
        (ii) Description of or reference to any applicable test method for 
    determining compliance with each applicable requirement.
        (5) Other specific information that may be necessary to implement 
    and enforce other applicable requirements of the Act or of this part or 
    to determine the applicability of such requirements.
        (6) An explanation of any proposed exemptions from otherwise 
    applicable requirements.
    
    [[Page 34235]]
    
        (7) Additional information as determined to be necessary by the 
    permitting authority to define alternative operating scenarios 
    identified by the source pursuant to Sec. 71.6(a)(9) or to define 
    permit terms and conditions implementing Sec. 71.6(a)(10) or 
    Sec. 71.6(a)(13).
        (8) A compliance plan for all part 71 sources that contains all the 
    following:
        (i) A description of the compliance status of the source with 
    respect to all applicable requirements.
        (ii) A description as follows:
        (A) For applicable requirements with which the source is in 
    compliance, a statement that the source will continue to comply with 
    such requirements.
        (B) For applicable requirements that will become effective during 
    the permit term, a statement that the source will meet such 
    requirements on a timely basis.
        (C) For requirements for which the source is not in compliance at 
    the time of permit issuance, a narrative description of how the source 
    will achieve compliance with such requirements.
        (iii) A compliance schedule as follows:
        (A) For applicable requirements with which the source is in 
    compliance, a statement that the source will continue to comply with 
    such requirements.
        (B) For applicable requirements that will become effective during 
    the permit term, a statement that the source will meet such 
    requirements on a timely basis. A statement that the source will meet 
    in a timely manner applicable requirements that become effective during 
    the permit term shall satisfy this provision, unless a more detailed 
    schedule is expressly required by the applicable requirement.
        (C) A schedule of compliance for sources that are not in compliance 
    with all applicable requirements at the time of permit issuance. Such a 
    schedule shall include a schedule of remedial measures, including an 
    enforceable sequence of actions with milestones, leading to compliance 
    with any applicable requirements for which the source will be in 
    noncompliance at the time of permit issuance. This compliance schedule 
    shall resemble and be at least as stringent as that contained in any 
    judicial consent decree or administrative order to which the source is 
    subject. Any such schedule of compliance shall be supplemental to, and 
    shall not sanction noncompliance with, the applicable requirements on 
    which it is based.
        (iv) A schedule for submission of certified progress reports no 
    less frequently than every 6 months for sources required to have a 
    schedule of compliance to remedy a violation.
        (v) The compliance plan content requirements specified in this 
    paragraph shall apply and be included in the acid rain portion of a 
    compliance plan for an affected source, except as specifically 
    superseded by regulations promulgated under parts 72 through 78 of this 
    chapter with regard to the schedule and method(s) the source will use 
    to achieve compliance with the acid rain emissions limitations.
        (9) Requirements for compliance certification, including the 
    following:
        (i) A certification of compliance with all applicable requirements 
    by a responsible official consistent with paragraph (d) of this section 
    and section 114(a)(3) of the Act;
        (ii) A statement of methods used for determining compliance, 
    including a description of monitoring, recordkeeping, and reporting 
    requirements and test methods;
        (iii) A schedule for submission of compliance certifications during 
    the permit term, to be submitted no less frequently than annually, or 
    more frequently if specified by the underlying applicable requirement 
    or by the permitting authority; and
        (iv) A statement indicating the source's compliance status with any 
    applicable enhanced monitoring and compliance certification 
    requirements of the Act.
        (10) The use of nationally-standardized forms for acid rain 
    portions of permit applications and compliance plans, as required by 
    regulations promulgated under parts 72 through 78 of this chapter.
        (11) Insignificant activities and emissions levels. The following 
    types of insignificant activities and emissions levels need not be 
    included in permit applications. However, for insignificant activities 
    which are exempted because of size or production rate, a list of such 
    insignificant activities must be included in the application. An 
    application may not omit information needed to determine the 
    applicability of, or to impose, any applicable requirement, or to 
    calculate the fee amount required under the schedule established 
    pursuant to Sec. 71.9 of this part.
        (i) Insignificant activities:
        (A) Mobile sources;
        (B) Air-conditioning units used for human comfort that are not 
    subject to applicable requirements under title VI of the Act and do not 
    exhaust air pollutants into the ambient air from any manufacturing or 
    other industrial process;
        (C) Ventilating units used for human comfort that do not exhaust 
    air pollutants into the ambient air from any manufacturing or other 
    industrial process;
        (D) Heating units used for human comfort that do not provide heat 
    for any manufacturing or other industrial process;
        (E) Noncommercial food preparation;
        (F) Consumer use of office equipment and products;
        (G) Janitorial services and consumer use of janitorial products; 
    and
        (H) Internal combustion engines used for landscaping purposes.
        (ii) Insignificant emissions levels. Emissions meeting the criteria 
    in paragraph (c)(11)(ii)(A) or (c)(11)(ii)(B) of this section need not 
    be included in the application, but must be listed with sufficient 
    detail to identify the emission unit and indicate that the exemption 
    applies. Similar emission units, including similar capacities or sizes, 
    may be listed under a single description, provided the number of 
    emission units is included in the description. No additional 
    information is required at time of application, but the permitting 
    authority may request additional information during application 
    processing.
        (A) Emission criteria for regulated air pollutants, excluding 
    hazardous air pollutants (HAP). Potential to emit of regulated air 
    pollutants, excluding HAP, for any single emissions unit shall not 
    exceed 2 tpy.
        (B) Emission criteria for HAP. Potential to emit of any HAP from 
    any single emissions unit shall not exceed 1,000 lb per year or the de 
    minimis level established under section 112(g) of the Act, whichever is 
    less.
        (d) Any application form, report, or compliance certification 
    submitted pursuant to these regulations shall contain certification by 
    a responsible official of truth, accuracy, and completeness. This 
    certification and any other certification required under this part 
    shall state that, based on information and belief formed after 
    reasonable inquiry, the statements and information in the document are 
    true, accurate, and complete.
    
    
    Sec. 71.6  Permit content.
    
        (a) Standard permit requirements. Each permit issued under this 
    part shall include the following elements:
        (1) Emission limitations and standards, including those operational 
    requirements and limitations that assure compliance with all applicable 
    requirements at the time of permit issuance.
        (i) The permit shall specify and reference the origin of and 
    authority for each term or condition, and identify any
    
    [[Page 34236]]
    
    difference in form as compared to the applicable requirement upon which 
    the term or condition is based.
        (ii) The permit shall state that, where an applicable requirement 
    of the Act is more stringent than an applicable requirement of 40 CFR 
    parts 72 through 78, both provisions shall be incorporated into the 
    permit and shall be enforceable by the Administrator.
        (iii) If an applicable implementation plan allows a determination 
    of an alternative emission limit at a part 71 source, equivalent to 
    that contained in the plan, to be made in the permit issuance, renewal, 
    or significant modification process, and the permitting authority 
    elects to use such process, any permit containing such equivalency 
    determination shall contain provisions to ensure that any resulting 
    emissions limit has been demonstrated to be quantifiable, accountable, 
    enforceable, and based on replicable procedures.
        (2) Permit duration. The permitting authority shall issue permits 
    for a fixed term of 5 years in the case of affected sources, and for a 
    term not to exceed 5 years in the case of all other sources. 
    Notwithstanding this requirement, the permitting authority shall issue 
    permits for solid waste incineration units combusting municipal waste 
    subject to standards under section 129(e) of the Act for a period not 
    to exceed 12 years and shall review such permits at least every 5 
    years.
        (3) Monitoring and related recordkeeping and reporting 
    requirements. (i) Each permit shall contain the following requirements 
    with respect to monitoring:
        (A) All emissions monitoring and analysis procedures or test 
    methods required under the applicable requirements, including any 
    procedures and methods promulgated pursuant to sections 114(a)(3) or 
    504(b) of the Act;
        (B) Where the applicable requirement does not require periodic 
    testing or instrumental or noninstrumental monitoring (which may 
    consist of recordkeeping designed to serve as monitoring), periodic 
    monitoring sufficient to yield reliable data from the relevant time 
    period that are representative of the source's compliance with the 
    permit, as reported pursuant to paragraph (a)(3)(iii) of this section. 
    Such monitoring requirements shall assure use of terms, test methods, 
    units, averaging periods, and other statistical conventions consistent 
    with the applicable requirement. Recordkeeping provisions may be 
    sufficient to meet the requirements of this paragraph (a)(3)(i)(B); and
        (C) As necessary, requirements concerning the use, maintenance, 
    and, where appropriate, installation of monitoring equipment or 
    methods.
        (ii) With respect to recordkeeping, the permit shall incorporate 
    all applicable recordkeeping requirements and require, where 
    applicable, the following:
        (A) Records of required monitoring information that include the 
    following:
        (1) The date, place as defined in the permit, and time of sampling 
    or measurements;
        (2) The date(s) analyses were performed;
        (3) The company or entity that performed the analyses;
        (4) The analytical techniques or methods used;
        (5) The results of such analyses; and
        (6) The operating conditions as existing at the time of sampling or 
    measurement;
        (B) Retention of records of all required monitoring data and 
    support information for a period of at least 5 years from the date of 
    the monitoring sample, measurement, report, or application. Support 
    information includes all calibration and maintenance records and all 
    original strip-chart recordings for continuous monitoring 
    instrumentation, and copies of all reports required by the permit.
        (iii) With respect to reporting, the permit shall incorporate all 
    applicable reporting requirements and require the following:
        (A) Submittal of reports of any required monitoring at least every 
    6 months. All instances of deviations from permit requirements must be 
    clearly identified in such reports. All required reports must be 
    certified by a responsible official consistent with Sec. 71.5(d).
        (B) Prompt reporting of deviations from permit requirements, 
    including those attributable to upset conditions as defined in the 
    permit, the probable cause of such deviations, and any corrective 
    actions or preventive measures taken. Where the underlying applicable 
    requirement contains a definition of prompt or otherwise specifies a 
    time frame for reporting deviations, that definition or time frame 
    shall govern. Where the underlying applicable requirement fails to 
    address the time frame for reporting deviations, reports of deviations 
    shall be submitted to the permitting authority based on the following 
    schedule:
        (1) For emissions of a hazardous air pollutant or a toxic air 
    pollutant (as identified in an applicable regulation) that continue for 
    more than an hour in excess of permit requirements, the report must be 
    made with 24 hours of the occurrence.
        (2) For emissions of any regulated air pollutant, excluding those 
    listed in paragraph (a)(3)(iii)(B)(1) of this section, that continue 
    for more than two hours in excess of permit requirements, the report 
    must be made within 48 hours.
        (3) For all other deviations from permit requirements, the report 
    shall be contained in the report submitted in accordance with the 
    timeframe given in paragraph (a)(3)(iii)(A).
        (4) A permit may contain a more stringent reporting requirement 
    than required by paragraphs (a)(3)(iii)(B)(1), (2), or (3).
        If any of the above conditions are met, the source must notify the 
    permitting authority by telephone or facsimile based on the timetable 
    listed in paragraphs (a)(3)(iii)(B) (1) through (4) of this section. A 
    written notice, certified consistent with Sec. 71.5(d), must be 
    submitted within 10 working days of the occurrence. All deviations 
    reported under paragraph (a)(3)(iii)(A) of this section must also be 
    identified in the 6 month report required under paragraph 
    (a)(3)(iii)(A) of this section.
        (C) For purposes of paragraph (a)(3)(iii)(B) of this section, 
    deviation means any condition determined by observation, by data from 
    any monitoring protocol, or by any other monitoring which is required 
    by the permit that can be used to determine compliance, that identifies 
    that an emission unit subject to a part 71 permit term or condition has 
    failed to meet an applicable emission limitation or standard or that a 
    work practice was not complied with or completed. For a condition 
    lasting more than 24 hours which constitutes a deviation, each 24 hour 
    period is considered a separate deviation. Included in the meaning of 
    deviation are any of the following:
        (1) A condition where emissions exceed an emission limitation or 
    standard;
        (2) A condition where process or control device parameter values 
    demonstrate that an emission limitation or standard has not been met;
        (3) Any other condition in which observations or data collected 
    demonstrates noncompliance with an emission limitation or standard or 
    any work practice or operating condition required by the permit.
        (4) A permit condition prohibiting emissions exceeding any 
    allowances that the source lawfully holds under 40 CFR parts 72 through 
    78.
        (i) No permit revision shall be required for increases in emissions 
    that are authorized by allowances acquired pursuant to the acid rain 
    program,
    
    [[Page 34237]]
    
    provided that such increases do not require a permit revision under any 
    other applicable requirement.
        (ii) No limit shall be placed on the number of allowances held by 
    the source. The source may not, however, use allowances as a defense to 
    noncompliance with any other applicable requirement.
        (iii) Any such allowance shall be accounted for according to the 
    procedures established in regulations 40 CFR parts 72 through 78.
        (5) A severability clause to ensure the continued validity of the 
    various permit requirements in the event of a challenge to any portions 
    of the permit.
        (6) Provisions stating the following:
        (i) The permittee must comply with all conditions of the part 71 
    permit. Any permit noncompliance constitutes a violation of the Act and 
    is grounds for enforcement action; for permit termination, revocation 
    and reissuance, or modification; or for denial of a permit renewal 
    application.
        (ii) Need to halt or reduce activity not a defense. It shall not be 
    a defense for a permittee in an enforcement action that it would have 
    been necessary to halt or reduce the permitted activity in order to 
    maintain compliance with the conditions of this permit.
        (iii) The permit may be modified, revoked, reopened, and reissued, 
    or terminated for cause. The filing of a request by the permittee for a 
    permit modification, revocation and reissuance, or termination, or of a 
    notification of planned changes or anticipated noncompliance does not 
    stay any permit condition.
        (iv) The permit does not convey any property rights of any sort, or 
    any exclusive privilege.
        (v) The permittee shall furnish to the permitting authority, within 
    a reasonable time, any information that the permitting authority may 
    request in writing to determine whether cause exists for modifying, 
    revoking and reissuing, or terminating the permit or to determine 
    compliance with the permit. Upon request, the permittee shall also 
    furnish to the permitting authority copies of records required to be 
    kept by the permit or, in the case of a program delegated pursuant to 
    Sec. 71.10, for information claimed to be confidential, the permittee 
    may furnish such records directly to the Administrator along with a 
    claim of confidentiality.
        (7) A provision to ensure that a part 71 source pays fees to the 
    Administrator consistent with the fee schedule approved pursuant to 
    Sec. 71.9.
        (8) Emissions trading. A provision stating that no permit revision 
    shall be required, under any approved economic incentives, marketable 
    permits, emissions trading and other similar programs or processes for 
    changes that are provided for in the permit.
        (9) Terms and conditions for reasonably anticipated operating 
    scenarios identified by the source in its application as approved by 
    the permitting authority. Such terms and conditions:
        (i) Shall require the source, contemporaneously with making a 
    change from one operating scenario to another, to record in a log at 
    the permitted facility a record of the scenario under which it is 
    operating;
        (ii) May extend the permit shield described in paragraph (f) of 
    this section to all terms and conditions under each such operating 
    scenario; and
        (iii) Must ensure that the terms and conditions of each such 
    alternative scenario meet all applicable requirements and the 
    requirements of this part.
        (10) Terms and conditions, if the permit applicant requests them, 
    for the trading of emissions increases and decreases in the permitted 
    facility, to the extent that the applicable requirements provide for 
    trading such increases and decreases without a case-by-case approval of 
    each emissions trade. Such terms and conditions:
        (i) Shall include all terms required under paragraphs (a) and (c) 
    of this section to determine compliance;
        (ii) May extend the permit shield described in paragraph (f) of 
    this section to all terms and conditions that allow such increases and 
    decreases in emissions; and
        (iii) Must meet all applicable requirements and requirements of 
    this part.
        (11) Permit expiration. A provision to ensure that a part 71 permit 
    expires upon the earlier occurrence of the following events:
        (i) twelve years elapses from the date of issuance to a solid waste 
    incineration unit combusting municipal waste subject to standards under 
    section 112(e) of the Act; or
        (ii) five years elapses from the date of issuance; or
        (iii) the source is issued a part 70 permit.
        (12) Off Permit Changes. A provision allowing changes that are not 
    addressed or prohibited by the permit, other than those subject to the 
    requirements of 40 CFR parts 72 through 78 or those that are 
    modifications under any provision of title I of the Act to be made 
    without a permit revision, provided that the following requirements are 
    met:
        (i) Each such change shall meet all applicable requirements and 
    shall not violate any existing permit term or condition;
        (ii) Sources must provide contemporaneous written notice to the 
    permitting authority (and EPA, in the case of a program delegated 
    pursuant to Sec. 71.10) of each such change, except for changes that 
    qualify as insignificant under Sec. 71.5(c)(11). Such written notice 
    shall describe each such change, including the date, any change in 
    emissions, pollutants emitted, and any applicable requirement that 
    would apply as a result of the change;
        (iii) The change shall not qualify for the shield under 
    Sec. 71.6(f);
        (iv) The permittee shall keep a record describing changes made at 
    the source that result in emissions of a regulated air pollutant 
    subject to an applicable requirement, but not otherwise regulated under 
    the permit, and the emissions resulting from those changes.
        (13) Operational flexibility. Provisions consistent with paragraphs 
    (a)(3)(i) through (iii) of this section to allow changes within a 
    permitted facility without requiring a permit revision, if the changes 
    are not modifications under any provision of title I of the Act and the 
    changes do not exceed the emissions allowable under the permit (whether 
    expressed therein as a rate of emissions or in terms of total 
    emissions): Provided, that the facility provides the Administrator (in 
    the case of a program delegated pursuant to Sec. 71.10) and the 
    permitting authority with written notification as required below in 
    advance of the proposed changes, which shall be a minimum of 7 days.
        (i) The permit shall allow the permitted source to make section 
    502(b)(10) changes without requiring a permit revision, if the changes 
    are not modifications under any provision of title I of the Act and the 
    changes do not exceed the emissions allowable under the permit (whether 
    expressed therein as a rate of emissions or in terms of total 
    emissions).
        (A) For each such change, the written notification required above 
    shall include a brief description of the change within the permitted 
    facility, the date on which the change will occur, any change in 
    emissions, and any permit term or condition that is no longer 
    applicable as a result of the change.
        (B) The permit shield described in Sec. 71.6(f) shall not apply to 
    any change made pursuant to this paragraph (a)(13)(i).
        (ii) The permit may provide for the permitted source to trade 
    increases and decreases in emissions in the permitted facility, where 
    the applicable
    
    [[Page 34238]]
    
    implementation plan provides for such emissions trades without 
    requiring a permit revision and based on the 7-day notice prescribed in 
    this paragraph (a)(13)(ii) of this section. This provision is available 
    in those cases where the permit does not already provide for such 
    emissions trading.
        (A) Under this paragraph (a)(13)(ii), the written notification 
    required above shall include such information as may be required by the 
    provision in the applicable implementation plan authorizing the 
    emissions trade, including at a minimum, when the proposed change will 
    occur, a description of each such change, any change in emissions, the 
    permit requirements with which the source will comply using the 
    emissions trading provisions of the applicable implementation plan, and 
    the pollutants emitted subject to the emissions trade. The notice shall 
    also refer to the provisions with which the source will comply in the 
    applicable implementation plan and that provide for the emissions 
    trade.
        (B) The permit shield described in Sec. 71.6(f) shall not extend to 
    any change made under this paragraph (a)(13)(ii). Compliance with the 
    permit requirements that the source will meet using the emissions trade 
    shall be determined according to requirements of the applicable 
    implementation plan authorizing the emissions trade.
        (iii) The permit shall require the permitting authority, if a 
    permit applicant requests it, to issue permits that contain terms and 
    conditions, including all terms required under Sec. 71.6 (a) and (c) to 
    determine compliance, allowing for the trading of emissions increases 
    and decreases in the permitted facility solely for the purpose of 
    complying with a federally-enforceable emissions cap that is 
    established in the permit independent of otherwise applicable 
    requirements. The permit applicant shall include in its application 
    proposed replicable procedures and permit terms that ensure the 
    emissions trades are quantifiable and enforceable. The permitting 
    authority shall not be required to include in the emissions trading 
    provisions any emissions units for which emissions are not quantifiable 
    or for which there are no replicable procedures to enforce the 
    emissions trades. The permit shall also require compliance with all 
    applicable requirements.
        (A) Under this paragraph (a)(13)(iii), the written notification 
    required above shall state when the change will occur and shall 
    describe the changes in emissions that will result and how these 
    increases and decreases in emissions will comply with the terms and 
    conditions of the permit.
        (B) The permit shield described in Sec. 71.6(f) may extend to terms 
    and conditions that allow such increases and decreases in emissions.
        (b) Federally-enforceable requirements. All terms and conditions in 
    a part 71 permit, including any provisions designed to limit a source's 
    potential to emit, are enforceable by the Administrator and citizens 
    under the Act.
        (c) Compliance requirements. All part 71 permits shall contain the 
    following elements with respect to compliance:
        (1) Consistent with paragraph (a)(3) of this section, compliance 
    certification, testing, monitoring, reporting, and recordkeeping 
    requirements sufficient to assure compliance with the terms and 
    conditions of the permit. Any document (including reports) required by 
    a part 71 permit shall contain a certification by a responsible 
    official that meets the requirements of Sec. 71.5(d).
        (2) Inspection and entry requirements that require that, upon 
    presentation of credentials and other documents as may be required by 
    law, the permittee shall allow the permitting authority or an 
    authorized representative to perform the following:
        (i) Enter upon the permittee's premises where a part 71 source is 
    located or emissions-related activity is conducted, or where records 
    must be kept under the conditions of the permit;
        (ii) Have access to and copy, at reasonable times, any records that 
    must be kept under the conditions of the permit;
        (iii) Inspect at reasonable times any facilities, equipment 
    (including monitoring and air pollution control equipment), practices, 
    or operations regulated or required under the permit; and
        (iv) As authorized by the Act, sample or monitor at reasonable 
    times substances or parameters for the purpose of assuring compliance 
    with the permit or applicable requirements.
        (3) A schedule of compliance consistent with Sec. 71.5(c)(8).
        (4) Progress reports consistent with an applicable schedule of 
    compliance and Sec. 71.5(c)(8) to be submitted at least semiannually, 
    or at a more frequent period if specified in the applicable requirement 
    or by the permitting authority. Such progress reports shall contain the 
    following:
        (i) Dates for achieving the activities, milestones, or compliance 
    required in the schedule of compliance, and dates when such activities, 
    milestones or compliance were achieved; and
        (ii) An explanation of why any dates in the schedule of compliance 
    were not or will not be met, and any preventive or corrective measures 
    adopted.
        (5) Requirements for compliance certification with terms and 
    conditions contained in the permit, including emission limitations, 
    standards, or work practices. Permits shall include each of the 
    following:
        (i) The frequency (not less than annually or such more frequent 
    periods as specified in the applicable requirement or by the permitting 
    authority) of submissions of compliance certifications;
        (ii) In accordance with Sec. 71.6(a)(3), a means for monitoring the 
    compliance of the source with its emissions limitations, standards, and 
    work practices;
        (iii) A requirement that the compliance certification include the 
    following:
        (A) The identification of each term or condition of the permit that 
    is the basis of the certification;
        (B) The compliance status;
        (C) Whether compliance was continuous or intermittent;
        (D) The method(s) used for determining the compliance status of the 
    source, currently and over the reporting period consistent with 
    paragraph (a)(3) of this section; and
        (E) Such other facts as the permitting authority may require to 
    determine the compliance status of the source;
        (iv) A requirement that all compliance certifications be submitted 
    to the Administrator as well as to the permitting authority; and
        (v) Such additional requirements as may be specified pursuant to 
    sections 114(a)(3) and 504(b) of the Act.
        (6) Such other provisions as the permitting authority may require.
        (d) General permits. (1) The permitting authority may, after notice 
    and opportunity for public participation provided under Sec. 71.11, 
    issue a general permit covering numerous similar sources. Any general 
    permit shall comply with all requirements applicable to other part 71 
    permits and shall identify criteria by which sources may qualify for 
    the general permit. To sources that qualify, the permitting authority 
    shall grant the conditions and terms of the general permit. 
    Notwithstanding the shield provisions of paragraph (f) of this section, 
    the source shall be subject to enforcement action for operation without 
    a part 71 permit if the source is later determined not to qualify for 
    the conditions and terms of the general permit. General permits shall 
    not be authorized for affected sources under the acid rain
    
    [[Page 34239]]
    
    program unless otherwise provided in 40 CFR parts 72 through 78.
        (2) Part 71 sources that would qualify for a general permit must 
    apply to the permitting authority for coverage under the terms of the 
    general permit or must apply for a part 71 permit consistent with 
    Sec. 71.5. The permitting authority may, in the general permit, provide 
    for applications which deviate from the requirements of Sec. 71.5, 
    provided that such applications meet the requirements of title V of the 
    Act, and include all information necessary to determine qualification 
    for, and to assure compliance with, the general permit. Without 
    repeating the public participation procedures required under 
    Sec. 71.11, the permitting authority may grant a source's request for 
    authorization to operate under a general permit, but such a grant shall 
    not be a final permit action for purposes of judicial review.
        (e) Temporary sources. The permitting authority may issue a single 
    permit authorizing emissions from similar operations by the same source 
    owner or operator at multiple temporary locations. The operation must 
    be temporary and involve at least one change of location during the 
    term of the permit. No affected source shall be permitted as a 
    temporary source. Permits for temporary sources shall include the 
    following:
        (1) Conditions that will assure compliance with all applicable 
    requirements at all authorized locations;
        (2) Requirements that the owner or operator notify the permitting 
    authority at least 10 days in advance of each change in location; and
        (3) Conditions that assure compliance with all other provisions of 
    this section.
        (f) Permit shield. (1) Except as provided in this part, the 
    permitting authority may expressly include in a part 71 permit a 
    provision stating that compliance with the conditions of the permit 
    shall be deemed compliance with any applicable requirements as of the 
    date of permit issuance, provided that:
        (i) Such applicable requirements are included and are specifically 
    identified in the permit; or
        (ii) The permitting authority, in acting on the permit application 
    or revision, determines in writing that other requirements specifically 
    identified are not applicable to the source, and the permit includes 
    the determination or a concise summary thereof.
        (2) A part 71 permit that does not expressly state that a permit 
    shield exists shall be presumed not to provide such a shield.
        (3) Nothing in this paragraph or in any part 71 permit shall alter 
    or affect the following:
        (i) The provisions of section 303 of the Act (emergency orders), 
    including the authority of the Administrator under that section;
        (ii) The liability of an owner or operator of a source for any 
    violation of applicable requirements prior to or at the time of permit 
    issuance;
        (iii) The applicable requirements of the acid rain program, 
    consistent with section 408(a) of the Act; or
        (iv) The ability of EPA to obtain information from a source 
    pursuant to section 114 of the Act.
        (g) Emergency provision. (1) Definition. An ``emergency'' means any 
    situation arising from sudden and reasonably unforeseeable events 
    beyond the control of the source, including acts of God, which 
    situation requires immediate corrective action to restore normal 
    operation, and that causes the source to exceed a technology-based 
    emission limitation under the permit, due to unavoidable increases in 
    emissions attributable to the emergency. An emergency shall not include 
    noncompliance to the extent caused by improperly designed equipment, 
    lack of preventative maintenance, careless or improper operation, or 
    operator error.
        (2) Effect of an emergency. An emergency constitutes an affirmative 
    defense to an action brought for noncompliance with such technology-
    based emission limitations if the conditions of paragraph (g)(3) of 
    this section are met.
        (3) The affirmative defense of emergency shall be demonstrated 
    through properly signed, contemporaneous operating logs, or other 
    relevant evidence that:
        (i) An emergency occurred and that the permittee can identify the 
    cause(s) of the emergency;
        (ii) The permitted facility was at the time being properly 
    operated;
        (iii) During the period of the emergency the permittee took all 
    reasonable steps to minimize levels of emissions that exceeded the 
    emission standards, or other requirements in the permit; and
        (iv) The permittee submitted notice of the emergency to the 
    permitting authority within 2 working days of the time when emission 
    limitations were exceeded due to the emergency. This notice fulfills 
    the requirement of paragraph (a)(3)(iii)(B) of this section. This 
    notice must contain a description of the emergency, any steps taken to 
    mitigate emissions, and corrective actions taken.
        (4) In any enforcement proceeding, the permittee seeking to 
    establish the occurrence of an emergency has the burden of proof.
        (5) This provision is in addition to any emergency or upset 
    provision contained in any applicable requirement.
    
    
    Sec. 71.7  Permit issuance, renewal, reopenings, and revisions.
    
        (a) Action on application. (1) A permit, permit modification, or 
    renewal may be issued only if all of the following conditions have been 
    met:
        (i) The permitting authority has received a complete application 
    for a permit, permit modification, or permit renewal, except that a 
    complete application need not be received before issuance of a general 
    permit under Sec. 71.6(d);
        (ii) Except for modifications qualifying for minor permit 
    modification procedures under paragraphs (e) (1) and (2) of this 
    section, the permitting authority has complied with the requirements 
    for public participation under this section or Sec. 71.11, as 
    applicable;
        (iii) The permitting authority has complied with the requirements 
    for notifying and responding to affected States under Sec. 71.8(a);
        (iv) The conditions of the permit provide for compliance with all 
    applicable requirements and the requirements of this part; and
        (v) In the case of a program delegated pursuant to Sec. 71.10, the 
    Administrator has received a copy of the proposed permit and any 
    notices required under Sec. 71.10(d) and has not objected to issuance 
    of the permit under Sec. 71.10(g) within the time period specified 
    therein.
        (2) Except as provided under the initial transition plan provided 
    for under Sec. 71.4(i) or under 40 CFR part 72 or title V of the Act 
    for the permitting of affected sources under the acid rain program, the 
    permitting authority shall take final action on each permit application 
    (including a request for permit modification or renewal) within 18 
    months after receiving a complete application.
        (3) The permitting authority shall ensure that priority is given to 
    taking action on applications for construction or modification under 
    title I, parts C and D of the Act.
        (4) The permitting authority shall promptly provide notice to the 
    applicant of whether the application is complete. Unless the permitting 
    authority requests additional information or otherwise notifies the 
    applicant of incompleteness within 60 days of receipt of an 
    application, the
    
    [[Page 34240]]
    
    application shall be deemed complete. For modifications processed 
    through minor permit modification procedures, such as those in 
    paragraphs (e) (1) and (2) of this section, the permitting authority 
    need not make a completeness determination.
        (5) The permitting authority shall provide a statement that sets 
    forth the legal and factual basis for the draft permit conditions 
    (including references to the applicable statutory or regulatory 
    provisions). The permitting authority shall send this statement to any 
    person who requests it, and to EPA, in the case of a program delegated 
    pursuant to Sec. 71.10.
        (6) The submittal of a complete application shall not affect the 
    requirement that any source have a preconstruction permit under title I 
    of the Act.
        (b) Requirement for a permit. Except as provided in the following 
    sentence, Sec. 71.6(a)(13), and paragraphs (e)(1)(v) and e(2)(v) of 
    this section, no part 71 source may operate after the time that it is 
    required to submit a timely and complete application under this part, 
    except in compliance with a permit issued under this part. If a part 71 
    source submits a timely and complete application for permit issuance 
    (including for renewal), the source's failure to have a part 71 permit 
    is not a violation of this part until the permitting authority takes 
    final action on the permit application, except as noted in this 
    section. This protection shall cease to apply if, subsequent to the 
    completeness determination made pursuant to paragraph (a)(4) of this 
    section, and as required by Sec. 71.5(c), the applicant fails to submit 
    by the deadline specified in writing by the permitting authority any 
    additional information identified as being needed to process the 
    application.
        (c) Permit renewal and expiration. (1) (i) Permits being renewed 
    are subject to the same procedural requirements, including those for 
    public participation, affected State review, and EPA review (in the 
    case of a program delegated pursuant to Sec. 71.10) that apply to 
    initial permit issuance.
        (ii) Permit expiration terminates the source's right to operate 
    unless a timely and complete renewal application has been submitted 
    consistent with paragraph (b) of this section and Sec. 71.5(a)(1)(iii).
        (2) In the case of a program delegated pursuant to Sec. 71.10, if 
    the permitting authority fails to act in a timely way on permit 
    renewal, EPA may invoke its authority under section 505(e) of the Act 
    to terminate or revoke and reissue the permit.
        (3) If a timely and complete application for a permit renewal is 
    submitted, consistent with Sec. 71.5(a)(2), but the permitting 
    authority has failed to issue or deny the renewal permit before the end 
    of the term of the previous part 70 or 71 permit, then the permit shall 
    not expire until the renewal permit has been issued or denied and any 
    permit shield that may be granted pursuant to Sec. 71.6(f) may extend 
    beyond the original permit term until renewal; or all the terms and 
    conditions of the permit including any permit shield that may be 
    granted pursuant to Sec. 71.6(f) shall remain in effect until the 
    renewal permit has been issued or denied.
        (d) Administrative permit amendments. (1) An ``administrative 
    permit amendment'' is a permit revision that:
        (i) Corrects typographical errors;
        (ii) Identifies a change in the name, address, or phone number of 
    any person identified in the permit, or provides a similar minor 
    administrative change at the source;
        (iii) Requires more frequent monitoring or reporting by the 
    permittee;
        (iv) Allows for a change in ownership or operational control of a 
    source where the permitting authority determines that no other change 
    in the permit is necessary, provided that a written agreement 
    containing a specific date for transfer of permit responsibility, 
    coverage, and liability between the current and new permittee has been 
    submitted to the permitting authority;
        (v) Incorporates into the part 71 permit the requirements from 
    preconstruction review permits authorized under an EPA-approved 
    program, provided that such a program meets procedural requirements 
    substantially equivalent to the requirements of Secs. 71.7 and 71.8 
    (and Sec. 71.10 in the case of a delegated program) that would be 
    applicable to the change if it were subject to review as a permit 
    modification, and compliance requirements substantially equivalent to 
    those contained in Sec. 71.6; or
        (vi) Incorporates any other type of change which the Administrator 
    has determined to be similar to those in paragraphs (d)(1)(i) through 
    (iv) of this section.
        (2) Administrative permit amendments for purposes of the acid rain 
    portion of the permit shall be governed by 40 CFR part 72.
        (3) Administrative permit amendment procedures. An administrative 
    permit amendment may be made by the permitting authority consistent 
    with the following:
        (i) The permitting authority shall take no more than 60 days from 
    receipt of a request for an administrative permit amendment to take 
    final action on such request, and may incorporate such changes without 
    providing notice to the public or affected States provided that it 
    designates any such permit revisions as having been made pursuant to 
    this paragraph.
        (ii) The permitting authority shall submit a copy of the revised 
    permit to the Administrator in the case of a program delegated pursuant 
    to Sec. 71.10.
        (iii) The source may implement the changes addressed in the request 
    for an administrative amendment immediately upon submittal of the 
    request.
        (4) The permitting authority may, upon taking final action granting 
    a request for an administrative permit amendment, allow coverage by the 
    permit shield in Sec. 71.6(f) for administrative permit amendments made 
    pursuant to paragraph (d)(1)(v) of this section which meet the relevant 
    requirements of Secs. 71.6, 71.7, and 71.8 for significant permit 
    modifications.
        (e) Permit modifications. A permit modification is any revision to 
    a part 71 permit that cannot be accomplished under the provisions for 
    administrative permit amendments under paragraph (d) of this section. A 
    permit modification for purposes of the acid rain portion of the permit 
    shall be governed by 40 CFR part 72.
        (1) Minor permit modification procedures.
        (i) Criteria.
        (A) Minor permit modification procedures may be used only for those 
    permit modifications that:
        (1) Do not violate any applicable requirement;
        (2) Do not involve significant changes to existing monitoring, 
    reporting, or recordkeeping requirements in the permit;
        (3) Do not require or change a case-by-case determination of an 
    emission limitation or other standard, or a source-specific 
    determination for temporary sources of ambient impacts, or a visibility 
    or increment analysis;
        (4) Do not seek to establish or change a permit term or condition 
    for which there is no corresponding underlying applicable requirement 
    and that the source has assumed to avoid an applicable requirement to 
    which the source would otherwise be subject. Such terms and conditions 
    include:
        (i) A federally enforceable emissions cap assumed to avoid 
    classification as a modification under any provision of title I; and
        (ii) An alternative emissions limit approved pursuant to 
    regulations
    
    [[Page 34241]]
    
    promulgated under section 112(i)(5) of the Act;
        (5) Are not modifications under any provision of title I of the 
    Act; and
        (6) Are not required to be processed as a significant modification.
        (B) Notwithstanding paragraphs (e)(1)(i)(A) and (e)(2)(i) of this 
    section, minor permit modification procedures may be used for permit 
    modifications involving the use of economic incentives, marketable 
    permits, emissions trading, and other similar approaches, to the extent 
    that such minor permit modification procedures are explicitly provided 
    for in an applicable implementation plan or in applicable requirements 
    promulgated by EPA.
        (ii) Application. An application requesting the use of minor permit 
    modification procedures shall meet the requirements of Sec. 71.5(c) and 
    shall include the following:
        (A) A description of the change, the emissions resulting from the 
    change, and any new applicable requirements that will apply if the 
    change occurs;
        (B) The source's suggested draft permit;
        (C) Certification by a responsible official, consistent with 
    Sec. 71.5(d), that the proposed modification meets the criteria for use 
    of minor permit modification procedures and a request that such 
    procedures be used; and
        (D) Completed forms for the permitting authority to use to notify 
    affected States (and the Administrator in the case of a program 
    delegated pursuant to Sec. 71.10) as required under Secs. 71.8 and 
    71.10(d).
        (iii) EPA and affected State notification. Within 5 working days of 
    receipt of a complete permit modification application, the permitting 
    authority shall meet its obligation under Sec. 71.8(a) to notify 
    affected States (and its obligation under Sec. 71.10(d) to notify the 
    Administrator in the case of a program delegated pursuant to 
    Sec. 71.10) of the requested permit modification. In the case of a 
    program delegated pursuant to Sec. 71.10, the permitting authority 
    promptly shall send any notice required under Sec. 71.8(b) to the 
    Administrator.
        (iv) Timetable for issuance. In the case of a program delegated 
    pursuant to Sec. 71.10, the permitting authority may not issue a final 
    permit modification until after EPA's 45-day review period or until EPA 
    has notified the permitting authority that EPA will not object to 
    issuance of the permit modification, whichever is first, although the 
    permitting authority can approve the permit modification prior to that 
    time. Within 90 days of the permitting authority's receipt of an 
    application under minor permit modification procedures (or 15 days 
    after the end of the Administrator's 45-day review period under 
    Sec. 71.10(g) in the case of a program delegated pursuant to 
    Sec. 71.10, whichever is later), the permitting authority shall:
        (A) Issue the permit modification as proposed;
        (B) Deny the permit modification application;
        (C) Determine that the requested modification does not meet the 
    minor permit modification criteria and should be reviewed under the 
    significant modification procedures; or
        (D) Revise the draft permit modification (and, in the case of a 
    program delegated pursuant to Sec. 71.10, transmit to the Administrator 
    the new proposed permit modification as required by Sec. 71.10(d)).
        (v) Source's ability to make change. The source may make the change 
    proposed in its minor permit modification application immediately after 
    it files such application. After the source makes the change allowed by 
    the preceding sentence, and until the permitting authority takes any of 
    the actions specified in paragraphs (e)(1)(iv) (A) through (C) of this 
    section, the source must comply with both the applicable requirements 
    governing the change and the proposed permit terms and conditions. 
    During this time period, the source need not comply with the existing 
    permit terms and conditions it seeks to modify. However, if the source 
    fails to comply with its proposed permit terms and conditions during 
    this time period, the existing permit terms and conditions it seeks to 
    modify may be enforced against it.
        (vi) Permit shield. The permit shield under Sec. 71.6(f) may not 
    extend to minor permit modifications.
        (2) Group processing of minor permit modifications. Consistent with 
    this paragraph, the permitting authority may modify the procedure 
    outlined in paragraph (e)(1) of this section to process groups of a 
    source's applications for certain modifications eligible for minor 
    permit modification processing.
        (i) Criteria. Group processing of modifications may be used only 
    for those permit modifications:
        (A) That meet the criteria for minor permit modification procedures 
    under paragraph (e)(1)(i)(A) of this section; and
        (B) That collectively are below the threshold level of 10 percent 
    of the emissions allowed by the permit for the emissions unit for which 
    the change is requested, 20 percent of the applicable definition of 
    major source in Sec. 71.2, or 5 tpy, whichever is least.
        (ii) Application. An application requesting the use of group 
    processing procedures shall meet the requirements of Sec. 71.5(c) and 
    shall include the following:
        (A) A description of the change, the emissions resulting from the 
    change, and any new applicable requirements that will apply if the 
    change occurs.
        (B) The source's suggested draft permit.
        (C) Certification by a responsible official, consistent with 
    Sec. 71.5(d), that the proposed modification meets the criteria for use 
    of group processing procedures and a request that such procedures be 
    used.
        (D) A list of the source's other pending applications awaiting 
    group processing, and a determination of whether the requested 
    modification, aggregated with these other applications, equals or 
    exceeds the threshold set under paragraph (e)(2)(i)(B) of this section.
        (E) Certification, consistent with Sec. 71.5(d), that, in the case 
    of a program delegated pursuant to Sec. 71.10, the source has notified 
    EPA of the proposed modification. Such notification need only contain a 
    brief description of the requested modification.
        (F) Completed forms for the permitting authority to use to notify 
    affected States as required under Sec. 71.8 (and the Administrator as 
    required under Sec. 71.10(d) in the case of a program delegated 
    pursuant to Sec. 71.10).
        (iii) EPA and affected State notification. On a quarterly basis or 
    within 5 business days of receipt of an application demonstrating that 
    the aggregate of a source's pending applications equals or exceeds the 
    threshold level set under paragraph (e)(2)(i)(B) of this section, 
    whichever is earlier, the permitting authority promptly shall meet its 
    obligation under Sec. 71.8(a) to notify affected States (and its 
    obligation under Sec. 71.10(d) to notify EPA in the case of a program 
    delegated pursuant to Sec. 71.10) of the requested permit modification. 
    The permitting authority shall send any notice required under 
    Sec. 71.8(b) to the Administrator in the case of a program delegated 
    pursuant to Sec. 71.10.
        (iv) Timetable for issuance. The provisions of paragraph (e)(1)(iv) 
    of this section shall apply to modifications eligible for group 
    processing, except that the permitting authority shall take one of the 
    actions specified in paragraphs (e)(1)(iv) (A) through (D) of this 
    section within 180 days of receipt of the application (or, in the case 
    of a program delegated pursuant to Sec. 71.10, 15 days
    
    [[Page 34242]]
    
    after the end of the Administrator's 45-day review period under 
    Sec. 71.10(g), whichever is later).
        (v) Source's ability to make change. The provisions of paragraph 
    (e)(1)(v) of this section shall apply to modifications eligible for 
    group processing.
        (vi) Permit shield. The provisions of paragraph (e)(1)(vi) of this 
    section shall also apply to modifications eligible for group 
    processing.
        (3) Significant modification procedures.
        (i) Criteria. Significant modification procedures shall be used for 
    applications requesting permit modifications that do not qualify as 
    minor permit modifications or as administrative amendments. Every 
    significant change in existing monitoring permit terms or conditions 
    and every relaxation of reporting or recordkeeping permit terms or 
    conditions shall be considered significant. Nothing herein shall be 
    construed to preclude the permittee from making changes consistent with 
    this part that would render existing permit compliance terms and 
    conditions irrelevant.
        (ii) Significant permit modifications shall meet all requirements 
    of this part, including those for applications, public participation, 
    review by affected States, and review by EPA (in the case of a program 
    delegated pursuant to Sec. 71.10), as they apply to permit issuance and 
    permit renewal. The permitting authority shall design and implement 
    this review process to complete review on the majority of significant 
    permit modifications within 9 months after receipt of a complete 
    application.
        (f) Reopening for cause. (1) Each issued permit shall include 
    provisions specifying the conditions under which the permit will be 
    reopened prior to the expiration of the permit. A permit shall be 
    reopened and revised under any of the following circumstances:
        (i) Additional applicable requirements under the Act become 
    applicable to a major part 71 source with a remaining permit term of 3 
    or more years. Such a reopening shall be completed not later than 18 
    months after promulgation of the applicable requirement. No such 
    reopening is required if the effective date of the requirement is later 
    than the date on which the permit is due to expire, unless the original 
    permit or any of its terms and conditions have been extended pursuant 
    to paragraph (c)(3) of this section.
        (ii) Additional requirements (including excess emissions 
    requirements) become applicable to an affected source under the acid 
    rain program. Upon approval by the Administrator, excess emissions 
    offset plans shall be deemed to be incorporated into the permit.
        (iii) The permitting authority (or EPA, in the case of a program 
    delegated pursuant to Sec. 71.10) determines that the permit contains a 
    material mistake or that inaccurate statements were made in 
    establishing the emissions standards or other terms or conditions of 
    the permit.
        (iv) The permitting authority (or EPA, in the case of a program 
    delegated pursuant to Sec. 71.10) determines that the permit must be 
    revised or revoked to assure compliance with the applicable 
    requirements.
        (2) Proceedings to reopen and issue a permit shall follow the same 
    procedures as apply to initial permit issuance and shall affect only 
    those parts of the permit for which cause to reopen exists, and shall 
    be made as expeditiously as practicable.
        (3) Reopenings under paragraph (f)(1) of this section shall not be 
    initiated before a notice of such intent is provided to the part 71 
    source by the permitting authority at least 30 days in advance of the 
    date that the permit is to be reopened, except that the permitting 
    authority may provide a shorter time period in the case of an 
    emergency.
        (g) Reopenings for cause by EPA for delegated programs. (1) In the 
    case of a program delegated pursuant to Sec. 71.10, if the 
    Administrator finds that cause exists to terminate, modify, or revoke 
    and reissue a permit pursuant to paragraph (f) of this section, the 
    Administrator will notify the permitting authority and the permittee of 
    such finding in writing.
        (2) The permitting authority shall, within 90 days after receipt of 
    such notification, forward to EPA a proposed determination of 
    termination, modification, or revocation and reissuance, as 
    appropriate. The Administrator may extend this 90-day period for an 
    additional 90 days if he or she finds that a new or revised permit 
    application is necessary or that the permitting authority must require 
    the permittee to submit additional information.
        (3) The Administrator will review the proposed determination from 
    the permitting authority within 90 days of receipt.
        (4) The permitting authority shall have 90 days from receipt of an 
    EPA objection to resolve any objection that EPA makes and to terminate, 
    modify, or revoke and reissue the permit in accordance with the 
    Administrator's objection.
        (5) If the permitting authority fails to submit a proposed 
    determination pursuant to paragraph (g)(2) of this section or fails to 
    resolve any objection pursuant to paragraph (g)(4) of this section, the 
    Administrator will terminate, modify, or revoke and reissue the permit 
    after taking the following actions:
        (i) Providing at least 30 days' notice to the permittee in writing 
    of the reasons for any such action. This notice may be given during the 
    procedures in paragraphs (g) (1) through (4) of this section.
        (ii) Providing the permittee an opportunity for comment on the 
    Administrator's proposed action and an opportunity for a hearing.
    
    
    Sec. 71.8  Affected State review.
    
        (a) Notice of draft permits. When a part 71 operating permits 
    program becomes effective in a State or Tribal area, the permitting 
    authority shall provide notice of each draft permit to any affected 
    State, as defined in Sec. 71.2, on or before the time that the 
    permitting authority provides this notice to the public pursuant to 
    Sec. 71.7 or Sec. 71.11(d) except to the extent Sec. 71.7(e)(1) or (2) 
    requires the timing of the notice to be different.
        (b) Notice of refusal to accept recommendations. Prior to issuance 
    of the final permit, the permitting authority shall notify any affected 
    State in writing of any refusal by the permitting authority to accept 
    all recommendations for the proposed permit that the affected State 
    submitted during the public or affected State review period. The notice 
    shall include the permitting authority's reasons for not accepting any 
    such recommendation. The permitting authority is not required to accept 
    recommendations that are not based on applicable requirements or the 
    requirements of this part. In the case of a program delegated pursuant 
    to Sec. 71.10, the permitting authority shall include such notice as 
    part of the submittal of the proposed permit to the Administrator (or 
    as soon as possible after the submittal for minor permit modification 
    procedures allowed under Sec. 71.7(e)(1) or (2)).
        (c) Waiver of notice requirements. The Administrator may waive the 
    requirements of paragraph (a) of this section for any category of 
    sources (including any class, type, or size within such category) other 
    than major sources by regulation for a category of sources nationwide.
        (d) Notice provided to Indian Tribes. The permitting authority 
    shall provide notice of each draft permit to any federally recognized 
    Indian Tribe whose air quality may be affected by the permitting action 
    and whose reservation
    
    [[Page 34243]]
    
    or Tribal area is contiguous to the jurisdiction in which the part 71 
    permit is proposed or is within 50 miles of the permitted source.
    
    
    Sec. 71.9  Permit fees
    
        (a) Fee requirement. The owners or operators of part 71 sources 
    shall pay annual fees, or the equivalent over some other period, that 
    are sufficient to cover the permit program costs, in accordance with 
    the procedures described in this section.
        (b) Permit program costs. These costs include, but are not limited 
    to, the costs of the following activities as they relate to a part 71 
    program:
        (1) Reviewing and acting on any application for a permit, permit 
    revision, or permit renewal, including the development of an applicable 
    requirement as part of the processing of a permit, or permit revision 
    or renewal;
        (2) Processing permit reopenings;
        (3) General administrative costs of the permit program, including 
    transition planning, interagency coordination, contract management, 
    training, informational services and outreach activities, assessing and 
    collecting fees, the tracking of permit applications, compliance 
    certifications, and related data entry;
        (4) Implementing and enforcing the terms of any part 71 permit (not 
    including any court costs or other costs associated with an enforcement 
    action), including adequate resources to determine which sources are 
    subject to the program;
        (5) Emissions and ambient monitoring, modeling, analyses, 
    demonstrations, preparation of inventories, and tracking emissions, 
    provided these activities are needed in order to issue and implement 
    part 71 permits; and
        (6) Providing direct and indirect support to small business 
    stationary sources in determining applicable requirements and in 
    receiving permits under this part (to the extent that these services 
    are not provided by a State Small Business Stationary Source Technical 
    and Environmental Compliance Assistance Program).
        (c) Establishment of fee schedule. (1) For part 71 programs that 
    are administered by EPA, each part 71 source shall pay an annual fee in 
    the amount of $32 per ton (as adjusted pursuant to the criteria set 
    forth in paragraph (n)(1) of this section) times the total tons of the 
    actual emissions of each regulated pollutant (for fee calculation) 
    emitted from the source, including fugitive emissions.
        (2) For part 71 programs that are fully delegated pursuant to 
    Sec. 71.10:
        (i) Where the EPA has not suspended its part 71 fee collection 
    pursuant to paragraph (c)(2)(ii) of this section, the annual fee for 
    each part 71 source shall be $24 per ton (as adjusted pursuant to the 
    criteria set forth in paragraph (n)(1) of this section) times the total 
    tons of the actual emissions of each regulated pollutant (for fee 
    calculation) emitted from the source, including fugitive emissions.
        (ii) Where the delegate State collects fees from part 71 sources 
    under State law which are sufficient to fund the delegated part 71 
    program, the EPA may suspend its collection of part 71 fees. The 
    specific terms and conditions regarding the suspension of fee 
    collection will be addressed in the applicable delegation agreement 
    pursuant to Sec. 71.10.
        (3) For part 71 programs that are administered by EPA with 
    contractor assistance, the per ton fee shall vary depending on the 
    extent of contractor involvement and the cost to EPA of contractor 
    assistance. The EPA shall establish a per ton fee that is based on the 
    contractor costs for the specific part 71 program that is being 
    administered, using the following formula:
    
    Cost per ton=(E x 32)+[(1-E) x $C]
    Where E represents EPA's proportion of total effort (expressed as a 
    percentage of total effort) needed to administer the part 71 program, 
    1-E represents the contractor's effort, and C represents the contractor 
    assistance cost on a per ton basis. C shall be computed by using the 
    following formula:
    
    C=[B+T+N] divided by 12,300,000
    
    Where B represents the base cost (contractor costs), where T represents 
    travel costs, and where N represents nonpersonnel data management and 
    tracking costs.
        (4) For programs that are delegated in part, the fee shall be 
    computed using the following formula:
        Cost per ton=(E x 32)+(D x 24)+[(1-E-D) x $C]
    Where E and D represent, respectively, the EPA and delegate agency 
    proportions of total effort (expressed as a percentage of total effort) 
    needed to administer the part 71 program, 1-E-D represents the 
    contractor's effort, and C represents the contractor assistance cost on 
    a per ton basis. C shall be computed using the formula for contractor 
    assistance cost found in paragraph (c)(3) of this section and shall be 
    zero if contractor assistance is not utilized.
        (5) The following emissions shall be excluded from the calculation 
    of fees under paragraph (c)(1) through (c)(4) of this section:
        (i) The amount of a part 71 source's actual emissions of each 
    regulated pollutant (for fee calculation) that the source emits in 
    excess of four thousand (4,000) tpy;
        (ii) A part 71 source's actual emissions of any regulated pollutant 
    (for fee calculation) already included in the fee calculation; and
        (iii) The insignificant quantities of actual emissions not required 
    to be listed or calculated in a permit application pursuant to 
    Sec. 71.5(c)(11).
        (6) ``Actual emissions'' means the actual rate of emissions in tpy 
    of any regulated pollutant (for fee calculation) emitted from a part 71 
    source over the preceding calendar year. Actual emissions shall be 
    calculated using each emissions unit's actual operating hours, 
    production rates, in-place control equipment, and types of materials 
    processed, stored, or combusted during the preceding calendar year.
        (7) Notwithstanding the provisions of paragraph (c) (1) through (4) 
    of this section, if the Administrator determines that the fee 
    structures provided in paragraphs (c)(1) through (4) of this section do 
    not reflect the costs of administering a part 71 program, then the 
    Administrator shall by rule set a fee which adequately reflects permit 
    program costs for that program.
        (d) Prohibition on fees with respect to emissions from affected 
    units. Notwithstanding any other provision of this section, during the 
    years 1995 through 1999 inclusive, no fee for purposes of title V shall 
    be required to be paid with respect to emissions from any affected unit 
    under section 404 of the Act.
        (e) Submission of initial fee calculation work sheets and fees. (1) 
    Each part 71 source shall complete and submit an initial fee 
    calculation work sheet as provided in paragraphs (e)(2), (f), and (g) 
    of this section and shall complete and submit fee calculation work 
    sheets thereafter as provided in paragraph (h) of this section. 
    Calculations of actual or estimated emissions and calculation of the 
    fees owed by a source shall be computed by the source on fee 
    calculation work sheets provided by EPA. Fee payment of the full amount 
    must accompany each initial fee calculation work sheet.
        (2) The fee calculation work sheet shall require the source to 
    submit a report of its actual emissions for the preceding calendar year 
    and to compute fees owed based on those emissions. For sources that 
    have been issued part 70 or part 71 permits, actual emissions shall be 
    computed using compliance methods required by the most recent permit. 
    If actual emissions cannot be determined
    
    [[Page 34244]]
    
    using the compliance methods in the permit, the actual emissions should 
    be determined using federally recognized procedures. If a source 
    commenced operation during the preceding calendar year, the source 
    shall estimate its actual emissions for the current calendar year. In 
    such a case, fees for the source shall be based on the total emissions 
    estimated.
        (3) The initial fee calculation worksheet shall be certified by a 
    responsible official consistent with Sec. 71.5(d).
        (f) Deadlines for submission. (1) When EPA withdraws approval of a 
    part 70 program and implements a part 71 program, part 71 sources shall 
    submit initial fee calculation work sheets and fees in accordance with 
    the following schedule:
        (i) Sources having SIC codes between 0100 and 2499 inclusive shall 
    complete and submit fee calculation work sheets and fees within 6 
    months of the effective date of the part 71 program;
        (ii) Sources having SIC codes between 2500 and 2999 inclusive shall 
    complete and submit fee calculation work sheets and fees within 7 
    months of the effective date of the part 71 program;
        (iii) Sources having SIC codes between 3000 and 3999 inclusive 
    shall complete and submit fee calculation work sheets and fees within 8 
    months of the effective date of the part 71 program;
        (iv) Sources having SIC codes higher than 3999 shall complete and 
    submit fee calculation work sheets and fees within 9 months of the 
    effective date of the part 71 program.
        (2) Sources that are required under either paragraph (f)(1) or (g) 
    of this section to submit fee calculation work sheets and fees between 
    January 1 and March 31 may estimate their emissions for the preceding 
    calendar year in lieu of submitting actual emissions data. If the 
    source's initial fee calculation work sheet was based on estimated 
    emissions for the source's preceding calendar year, then the source 
    shall reconcile the fees owed when it submits its annual emissions 
    report, as provided in paragraph (h)(3) of this section.
        (3) When EPA implements a part 71 program that does not replace an 
    approved part 70 program, part 71 sources shall submit initial fee 
    calculation work sheets and initial fees when submitting their permit 
    applications in accordance with the requirements of Sec. 71.5(a)(1).
        (4) Notwithstanding the above, sources that become subject to the 
    part 71 program after the program's effective date shall submit an 
    initial fee calculation work sheet and initial fees when submitting 
    their permit applications in accordance with the requirements of 
    Sec. 71.5(a)(1).
        (g) Fees for sources that are issued part 71 permits following an 
    EPA objection pursuant to Sec. 71.4(e). Fees for such sources shall be 
    determined as provided in paragraph (c)(1) of this section. However, 
    initial fee calculation work sheets for such sources and full payment 
    of the initial fee shall be due three months after the date on which 
    the source's part 71 permit is issued.
        (h) Annual emissions reports--(1) Deadlines for submission. Each 
    part 71 source shall submit an annual report of its actual emissions 
    for the preceding calendar year, a fee calculation work sheet (based on 
    the report), and full payment of the annual fee each year on the 
    anniversary date of its initial fee calculation work sheet, except that 
    sources that were required to submit initial fee calculation work 
    sheets between January 1 and March 31 inclusive shall submit subsequent 
    annual emissions reports and fee calculation work sheets by April 1.
        (2) Annual emissions reports and fee calculation worksheets shall 
    be certified by a responsible official consistent with Sec. 71.5(d).
        (3) For sources that have been issued part 70 or part 71 permits, 
    actual emissions shall be computed using methods required by the most 
    current permit for determining compliance.
        (4) If the source's initial fee calculation work sheet was based on 
    estimated emissions for the source's current or preceding calendar 
    year, then the source shall reconcile the fees owed when it submits its 
    annual emissions report. The source shall compare the estimated 
    emissions from the initial work sheet and the actual emissions from the 
    report and shall enter such information on the fee calculation work 
    sheet that accompanies the annual report. The source shall recompute 
    the initial fee accordingly and shall remit any underpayment with the 
    report and work sheet. The EPA shall credit any overpayment to the 
    source's account.
        (i) Recordkeeping requirements. Part 71 sources shall retain, in 
    accordance with the provisions of Sec. 71.6(a)(3)(ii), all work sheets 
    and other materials used to determine fee payments. Records shall be 
    retained for 5 years following the year in which the emissions data is 
    submitted.
        (j) Fee assessment errors. (1) If EPA determines than a source has 
    completed the fee calculation work sheet incorrectly, the permitting 
    authority shall bill the applicant for the corrected fee or credit 
    overpayments to the source's account.
        (2) Each source notified by the permitting authority of additional 
    amounts due shall remit full payment within 30 days of receipt of an 
    invoice from the permitting authority.
        (3) An owner or operator of a part 71 source who thinks that the 
    assessed fee is in error shall provide a written explanation of the 
    alleged error to the permitting authority along with the assessed fee. 
    The permitting authority shall, within 90 days of receipt of the 
    correspondence, review the data to determine whether the assessed fee 
    was in error. If an error was made, the overpayment shall be credited 
    to the account of the part 71 source.
        (k) Remittance procedure. (1) Each remittance under this section 
    shall be in United States currency and shall be paid by money order, 
    bank draft, certified check, corporate check, or electronic funds 
    transfer payable to the order of the U.S. Environmental Protection 
    Agency.
        (2) Each remittance shall be sent to the Environmental Protection 
    Agency to the address designated on the fee calculation work sheet or 
    the invoice.
        (l) Penalty and interest assessment. (1) The permitting authority 
    shall assess interest on payments which are received later than the 
    date due. The interest rate shall be the sum of the Federal short-term 
    rate determined by the Secretary of the Treasury in accordance with 
    section 6621(a)(2) of the Internal Revenue Code of 1986, plus 3 
    percentage points.
        (2) The permitting authority shall assess a penalty charge of 50 
    percent of the fee amount if the fee is not paid within 30 days of the 
    payment due date.
        (3) If a source underpays the fee owed, except as provided in 
    paragraph (l)(4) of this section, the permitting authority shall assess 
    a penalty charge of 50 percent on the amount by which the fee was 
    underpaid. Interest shall also be assessed, computed under paragraph 
    (l)(1) of this section, on the amount by which the fee was underpaid.
        (4) If a source bases its initial fee calculation on estimated 
    emissions from the source's current or preceding calendar year, as 
    provided under paragraph (h)(4) of this section, and underpays its fee 
    based on an underestimation of these emissions, the permitting 
    authority shall assess a penalty charge of 50 percent on certain of 
    these underpayments, according to the following provisions:
        (i) The penalty charge shall be assessed whenever a source's 
    underpayment exceeds the underpayment penalty cutoff established in 
    paragraph (l)(4)(iii) of this section. The penalty amount shall be 50
    
    [[Page 34245]]
    
    percent of the portion of the underpayment which is in excess of the 
    underpayment penalty cutoff.
        (ii) Where a source is subject to a penalty for underpayment 
    pursuant to paragraph (l)(4)(i) of this section, interest as computed 
    under paragraph (l)(1) of this section shall be assessed on that 
    portion of the underpayment which is in excess of the underpayment 
    penalty cutoff established in paragraph (l)(4)(iii) of this section.
        (iii) The underpayment penalty cutoff for a source shall be the sum 
    of the following:
        (A) 50 percent of the portion of the initial fee amount which was 
    calculated from estimated emissions of HAP listed pursuant to 112(b) of 
    the Act, and
        (B) 20 percent of the portion of initial fee amount which was 
    calculated from estimated emissions of the remainder of the regulated 
    air pollutants (for fee calculation).
        (m) Failure to remit fees. The permitting authority shall not issue 
    a final permit or permit revision until all fees, interest and 
    penalties assessed against a source under this section are paid. The 
    initial application of a source shall not be found complete unless the 
    source has paid all fees owed.
        (n) Adjustments of fee schedules. 
        (1) The fee schedules provided in paragraphs (c) (1) through (4) of 
    this section shall remain in effect until December 31, 1996. 
    Thereafter, the fee schedules shall be changed annually by the 
    percentage, if any, of any annual increase in the Consumer Price Index.
        (2) Part 71 permit program costs and fees will be reviewed by the 
    Administrator at least every 2 years, and changes will be made to the 
    fee schedule as necessary to reflect permit program costs.
        (3) When changes to a fee schedule are made based on periodic 
    reviews by the Administrator, the changes will be published in the 
    Federal Register.
        (o) Use of revenue. All fees, penalties, and interest collected 
    under this part shall be deposited in a special fund in the U.S. 
    Treasury, which thereafter shall be available for appropriation, to 
    remain available until expended, subject to appropriation, to carry out 
    the activities required by this part.
    
    
    Sec. 71.10  Delegation of part 71 program.
    
        (a) Delegation of part 71 program. The Administrator may delegate, 
    in whole or in part, with or without signature authority, the authority 
    to administer a part 71 operating permits program to a State, eligible 
    Tribe, local, or other non-State agency in accordance with the 
    provisions of this section. In order to be delegated authority to 
    administer a part 71 program, the delegate agency must submit a legal 
    opinion from the Attorney General from the State, or the attorney for 
    the State, local, interstate, or eligible Tribal agency that has 
    independent legal counsel, stating that the laws of the State, 
    locality, interstate compact or Indian Tribe provide adequate authority 
    to carry out all aspects of the delegated program. A Delegation of 
    Authority Agreement (Agreement) shall set forth the terms and 
    conditions of the delegation, shall specify the provisions that the 
    delegate agency shall be authorized to implement, and shall be entered 
    into by the Administrator and the delegate agency. The Agreement shall 
    become effective upon the date that both the Administrator and the 
    delegate agency have signed the Agreement. Once delegation becomes 
    effective, the delegate agency will be responsible, to the extent 
    specified in the Agreement, for administering the part 71 program for 
    the area subject to the Agreement.
        (b) Publication of Notice of Delegation of Authority Agreement. The 
    Administrator shall publish a notice in the Federal Register informing 
    the public of any delegation of a portion of the part 71 program to a 
    State, eligible Tribe, or local agency.
        (c) Revision or revocation of Delegation of Authority Agreement. An 
    Agreement may be modified, amended, or revoked, in part or in whole, by 
    the Administrator after consultation with the delegate agency.
        (d) Transmission of information to the Administrator.
        (1) When a part 71 program has been delegated in accordance with 
    the provisions of this section, the delegate agency shall provide to 
    the Administrator a copy of each permit application (including any 
    application for permit modification), each proposed permit, and each 
    final part 71 permit. The applicant may be required by the delegate 
    agency to provide a copy of the permit application (including the 
    compliance plan) directly to the Administrator. Upon agreement with the 
    Administrator, the delegate agency may submit to the Administrator a 
    permit application summary form and any relevant portion of the permit 
    application and compliance plan, in place of the complete permit 
    application and compliance plan. To the extent practicable, the 
    preceding information shall be provided in computer-readable format 
    compatible with EPA's national database management system.
        (2) The Administrator may waive the requirements of paragraph 
    (d)(1) of this section for any category of sources (including any 
    class, type, or size within such category) other than major sources by 
    regulation for a category of sources nationwide.
        (e) Retention of records. The records for each draft, proposed, and 
    final permit, and application for permit renewal or modification shall 
    be kept for a period of 5 years by the delegate agency. The delegate 
    agency shall also submit to the Administrator such information as the 
    Administrator may reasonably require to ascertain whether the delegate 
    agency is implementing, administering, and enforcing the delegated part 
    71 program in compliance with the requirements of the Act and of this 
    part.
        (f) Prohibition of default issuance. (1) For the purposes of 
    Federal law and title V of the Act, when a part 71 program has been 
    delegated in accordance with the provisions of this section, no part 71 
    permit (including a permit renewal or modification) will be issued 
    until affected States have had an opportunity to review the draft 
    permit as required pursuant to Sec. 71.8(a) and EPA has had an 
    opportunity to review the proposed permit.
        (2) To receive delegation of signature authority, the legal opinion 
    submitted by the delegate agency pursuant to paragraph (a) of this 
    section shall certify that no applicable provision of State, local or 
    Tribal law requires that a part 71 permit or renewal be issued after a 
    certain time if the delegate agency has failed to take action on the 
    application (or includes any other similar provision providing for 
    default issuance of a permit), unless EPA has waived such review for 
    EPA and affected States.
        (g) EPA objection. (1) The Administrator will object to the 
    issuance of any proposed permit determined by the Administrator not to 
    be in compliance with applicable requirements or requirements under 
    this part. No permit for which an application must be transmitted to 
    the Administrator under paragraph (d)(1) of this section shall be 
    issued if the Administrator objects to its issuance in writing within 
    45 days of receipt of the proposed permit and all necessary supporting 
    information. When a part 71 program has been delegated in accordance 
    with the provisions of this section, failure of the delegate agency to 
    do any of the following shall constitute grounds for an objection by 
    the Administrator:
        (i) Comply with paragraph (d) of this section;
        (ii) Submit any information necessary to review adequately the 
    proposed permit;
    
    [[Page 34246]]
    
        (iii) Process the permit under the procedures required by 
    Secs. 71.7 and 71.11; or
        (iv) Comply with the requirements of Sec. 71.8(a).
        (2) Any EPA objection under paragraph (g)(1) of this section shall 
    include a statement of the Administrator's reason(s) for objection and 
    a description of the terms and conditions that the permit must include 
    to respond to the objection. The Administrator will provide the permit 
    applicant a copy of the objection.
        (3) If the delegate agency fails, within 90 days after the date of 
    an objection under paragraph (g)(1) of this section, to revise and 
    submit to the Administrator the proposed permit in response to the 
    objection, the Administrator shall issue or deny the permit in 
    accordance with the requirements of this part.
        (h) Public petitions. In the case of a delegated program, any 
    interested person may petition the Administrator to reopen a permit for 
    cause as provided in Sec. 71.11(n).
        (i) Appeal of permits. When a part 71 program has been delegated 
    with signature authority in accordance with the provisions of this 
    section, any person or affected State that submitted recommendations or 
    comments on the draft permit, or that participated in the public 
    hearing process may petition the Environmental Appeals Board in 
    accordance with Sec. 71.11(l)(1).
        (j) Nondelegable conditions. (1) The Administrator's authority to 
    object to the issuance of a part 71 permit cannot be delegated to an 
    agency not within EPA.
        (2) The Administrator's authority to act upon petitions submitted 
    pursuant to paragraph (h) of this section cannot be delegated to an 
    agency not within EPA.
    
    
    Sec. 71.11  Administrative record, public participation, and 
    administrative review.
    
        The provisions of this section shall apply to all permit 
    proceedings. Notwithstanding the preceding sentence, paragraphs (a) 
    through (h) and paragraph (j) of this section shall not apply to permit 
    revisions qualifying as minor permit modifications or administrative 
    amendments, except that public notice of the granting of appeals of 
    such actions under paragraph (l)(3) of this section shall be provided 
    pursuant to paragraph (d)(1)(i)(E) of this section, and except that 
    affected States shall be provided notice of minor permit modifications 
    under Sec. 71.8 as pursuant to paragraph (d)(3)(i)(B) of this section.
        (a) Draft permits. (1) The permitting authority shall promptly 
    provide notice to the applicant of whether the application is complete 
    pursuant to Sec. 71.7(a)(3).
        (2) Once an application for an initial permit, permit revision, or 
    permit renewal is complete, the permitting authority shall decide 
    whether to prepare a draft permit or to deny the application.
        (3) If the permitting authority initially decides to deny the 
    permit application, it shall issue a notice of intent to deny. A notice 
    of intent to deny the permit application is a type of draft permit and 
    follows the same procedures as any draft permit prepared under this 
    section. If the permitting authority's final decision is that the 
    initial decision to deny the permit application was incorrect, it shall 
    withdraw the notice of intent to deny and proceed to prepare a draft 
    permit under paragraph (a)(4) of this section.
        (4) If the permitting authority decides to prepare a draft permit, 
    it shall prepare a draft permit that contains the permit conditions 
    required under Sec. 71.6.
        (5) All draft permits prepared under this section shall be publicly 
    noticed and made available for public comment.
        (b) Statement of basis. The permitting authority shall prepare a 
    statement of basis for every draft permit subject to this section. The 
    statement of basis shall briefly describe the derivation of the 
    conditions of the draft permit and the reasons for them or, in the case 
    of notices of intent to deny or terminate, reasons supporting the 
    initial decision. The statement of basis shall be sent to the applicant 
    and, on request, to any other person.
        (c) Administrative record for draft permits.
        (1) The provisions of a draft permit shall be based on the 
    administrative record defined in this section.
        (2) For preparing a draft permit, the administrative record shall 
    consist of:
        (i) The application and any supporting data furnished by the 
    applicant;
        (ii) The draft permit or notice of intent to deny the application 
    or to terminate the permit;
        (iii) The statement of basis;
        (iv) All documents cited in the statement of basis; and
        (v) Other documents contained in the supporting file for the draft 
    permit.
        (3) Material readily available at the permitting authority or 
    published material that is generally available, and that is included in 
    the administrative record under paragraphs (b) and (c) of this section 
    need not be physically included with the rest of the record as long as 
    it is specifically referred to in the statement of basis.
        (d) Public notice of permit actions and public comment period.
        (1) Scope.
        (i) The permitting authority shall give public notice that the 
    following actions have occurred:
        (A) A permit application has been initially denied under paragraph 
    (a) of this section;
        (B) A draft permit has been prepared under paragraph (a) of this 
    section;
        (C) A hearing has been scheduled under paragraph (f) of this 
    section; and
        (D) A public comment period has been reopened under paragraph (h) 
    of this section;
        (E) An appeal has been granted under paragraph (l)(3) of this 
    section.
        (ii) No public notice is required when a request for permit 
    revision, revocation and reissuance, or termination has been denied 
    under paragraph (a)(2) of this section. Written notice of that denial 
    shall be given to the requester and to the permittee.
        (iii) Public notices may describe more than one permit or permit 
    action.
        (2) Timing. (i) Public notice of the preparation of a draft permit, 
    (including a notice of intent to deny a permit application), shall 
    allow at least 30 days for public comment.
        (ii) Public notice of a public hearing shall be given at least 30 
    days before the hearing. Public notice of the hearing may be given at 
    the same time as public notice of the draft permit and the two notices 
    may be combined.
        (iii) The permitting authority shall provide such notice and 
    opportunity for participation to affected States on or before the time 
    that the permitting authority provides this notice to the public.
        (3) Methods. Public notice of activities described in paragraph 
    (d)(1)(i) of this section shall be given by the following methods:
        (i) By mailing a copy of a notice to the following persons (any 
    person otherwise entitled to receive notice under paragraph (d) of this 
    section may waive his or her rights to receive notice for any permit):
        (A) The applicant;
        (B) Affected States;
        (C) Air pollution control agencies of affected States, Tribal and 
    local air pollution control agencies which have jurisdiction over the 
    area in which the source is located, the chief executives of the city 
    and county where the source is located, any comprehensive regional land 
    use planning agency and any State or Federal Land Manager whose lands 
    may be affected by emissions from the source;
        (D) The local emergency planning committee having jurisdiction over 
    the
    
    [[Page 34247]]
    
    area where the source is located, and State agencies having authority 
    under State law with respect to the operation of such source;
        (E) Persons on a mailing list developed by:
        (1) Including those who request in writing to be on the list;
        (2) Soliciting persons for ``area lists'' from participants in past 
    permit proceedings in that area; and
        (3) Notifying the public of the opportunity to be put on the 
    mailing list through periodic publication in the public press and, 
    where deemed appropriate by the permitting authority, in such 
    publications as regional and State funded newsletters, environmental 
    bulletins, or State law journals. The permitting authority may update 
    the mailing list from time to time by requesting written indication of 
    continued interest from those listed. The permitting authority may 
    delete from the list the name of any person who fails to respond to 
    such a request.
        (ii) By publication of a notice in a daily or weekly newspaper of 
    general circulation within the area affected by the source.
        (iii) By any other method reasonably calculated to give actual 
    notice of the action in question to the persons potentially affected by 
    it, including press releases or any other forum or medium to elicit 
    public participation.
        (4) Contents--(i) All public notices. All public notices issued 
    under this subpart shall contain the following minimum information:
        (A) The name and address of the permitting authority processing the 
    permit;
        (B) The name and address of the permittee or permit applicant and, 
    if different, of the facility regulated by the permit, except in the 
    case of draft general permits;
        (C) The activity or activities involved in the permit action;
        (D) The emissions change involved in any permit revision;
        (E) The name, address, and telephone number of a person whom 
    interested persons may contact for instructions on how to obtain 
    additional information, such as a copy of the draft permit, the 
    statement of basis, the application, relevant supporting materials, and 
    other materials available to the permitting authority that are relevant 
    to the permitting decision.
        (F) A brief description of the comment procedures required by 
    paragraph (e) of this section, a statement of procedures to request a 
    hearing (unless a hearing has already been scheduled) and other 
    procedures by which the public may participate in the final permit 
    decision;
        (G) The location of the administrative record, the times at which 
    the record will be open for public inspection, and a statement that all 
    data submitted by the applicant are available as part of the 
    administrative record; and
        (H) Any additional information considered necessary or proper.
        (ii) Public notices for hearings. Public notice of a hearing may be 
    combined with other notices required under paragraph (d)(1) of this 
    section. Any public notice of a hearing under paragraph (f) of this 
    section shall contain the following information:
        (A) The information described in paragraph (d)(4)(i) of this 
    section;
        (B) Reference to the date of previous public notices relating to 
    the permit;
        (C) The date, time, and place of the hearing; and
        (D) A brief description of the nature and purpose of the hearing, 
    including the applicable rules and the comment procedures.
        (5) All persons identified in paragraphs (d)(3)(i) (A), (B), (C), 
    (D), and (E) of this section shall be mailed a copy of the public 
    hearing notice described in paragraph (d)(4)(ii) of this section.
        (e) Public comments and requests for public hearings. During the 
    public comment period provided under paragraph (a) of this section, any 
    interested person may submit written comments on the draft permit and 
    may request a public hearing, if no hearing has already been scheduled. 
    A request for a public hearing shall be in writing and shall state the 
    nature of the issues proposed to be raised at the hearing. All comments 
    shall be considered in making the final decision and shall be answered 
    as provided in paragraph (j) of this section. The permitting authority 
    will keep a record of the commenters and of the issues raised during 
    the public participation process, and such records shall be available 
    to the public.
        (f) Public hearings. (1) The permitting authority shall hold a 
    hearing whenever it finds, on the basis of requests, a significant 
    degree of public interest in a draft permit.
        (2) The permitting authority may also hold a public hearing at its 
    discretion, whenever, for instance, such a hearing might clarify one or 
    more issues involved in the permit decision.
        (3) Public notice of the hearing shall be given as specified in 
    paragraph (d) of this section.
        (4) Whenever a public hearing is held, the permitting authority 
    shall designate a Presiding Officer for the hearing who shall be 
    responsible for its scheduling and orderly conduct.
        (5) Any person may submit oral or written statements and data 
    concerning the draft permit. Reasonable limits may be set upon the time 
    allowed for oral statements, and the submission of statements in 
    writing may be required. The public comment period under paragraph (d) 
    of this section shall be automatically extended to the close of any 
    public hearing under this section. The hearing officer may also extend 
    the comment period by so stating at the hearing.
        (6) A tape recording or written transcript of the hearing shall be 
    made available to the public.
        (g) Obligation to raise issues and provide information during the 
    public comment period. All persons, including applicants, who believe 
    any condition of a draft permit is inappropriate or that the permitting 
    authority's initial decision to deny an application, terminate a 
    permit, or prepare a draft permit is inappropriate, must raise all 
    reasonably ascertainable issues and submit all reasonably ascertainable 
    arguments supporting their position by the close of the public comment 
    period (including any public hearing). Any supporting materials that 
    are submitted shall be included in full and may not be incorporated by 
    reference, unless they are already part of the administrative record in 
    the same proceeding, or consist of State or Federal statutes and 
    regulations, EPA documents of general applicability, or other generally 
    available reference materials. In the case of a program delegated 
    pursuant to Sec. 71.10, if requested by the Administrator, the 
    permitting authority shall make supporting materials not already 
    included in the administrative record available to EPA. The permitting 
    authority may direct commenters to provide such materials directly to 
    EPA. A comment period longer than 30 days may be necessary to give 
    commenters a reasonable opportunity to comply with the requirements of 
    this section. Additional time shall be granted to the extent that a 
    commenter who requests additional time demonstrates the need for such 
    time.
        (h) Reopening of the public comment period. (1) The permitting 
    authority may order the public comment period reopened if the 
    procedures of paragraph (h) of this section could expedite the decision 
    making process. When the public comment period is reopened under 
    paragraph (h) of this section, all persons, including applicants, who 
    believe any condition of a draft permit is inappropriate or that the 
    permitting authority's initial decision to deny an application, 
    terminate a permit, or prepare a draft permit is inappropriate, must 
    submit all reasonably available factual grounds supporting their
    
    [[Page 34248]]
    
    position, including all supporting material, by a date not less than 30 
    days after public notice under paragraph (h)(2) of this section, set by 
    the permitting authority. Thereafter, any person may file a written 
    response to the material filed by any other person, by a date, not less 
    than 20 days after the date set for filing of the material, set by the 
    permitting authority.
        (2) Public notice of any comment period under this paragraph (h) 
    shall identify the issues to which the requirements of paragraphs 
    (h)(1) through (4) of this section shall apply.
        (3) On its own motion or on the request of any person, the 
    permitting authority may direct that the requirements of paragraph 
    (h)(1) of this section shall apply during the initial comment period 
    where it reasonably appears that issuance of the permit will be 
    contested and that applying the requirements of paragraph (h)(1) of 
    this section will substantially expedite the decision making process. 
    The notice of the draft permit shall state whenever this has been done.
        (4) A comment period of longer than 30 days may be necessary in 
    complicated proceedings to give commenters a reasonable opportunity to 
    comply with the requirements of this section. Commenters may request 
    longer comment periods and they may be granted to the extent the 
    permitting authority finds it necessary.
        (5) If any data, information, or arguments submitted during the 
    public comment period appear to raise substantial new questions 
    concerning a permit, the permitting authority may take one or more of 
    the following actions:
        (i) Prepare a new draft permit, appropriately modified;
        (ii) Prepare a revised statement of basis, and reopen the comment 
    period; or
        (iii) Reopen or extend the comment period to give interested 
    persons an opportunity to comment on the information or arguments 
    submitted.
        (6) Comments filed during the reopened comment period shall be 
    limited to the substantial new questions that caused the reopening. The 
    public notice shall define the scope of the reopening.
        (7) Public notice of any of the above actions shall be issued under 
    paragraph (d) of this section.
        (i) Issuance and effective date of permit. (1) After the close of 
    the public comment period on a draft permit, the permitting authority 
    shall issue a final permit decision. The permitting authority shall 
    notify the applicant and each person who has submitted written comments 
    or requested notice of the final permit decision. This notice shall 
    include reference to the procedures for appealing a decision on a 
    permit. For the purposes of this section, a final permit decision means 
    a final decision to issue, deny, revise, revoke and reissue, renew, or 
    terminate a permit.
        (2) A final permit decision shall become effective 30 days after 
    the service of notice of the decision, unless:
        (i) A later effective date is specified in the decision;
        (ii) Review is requested under paragraph (l) of this section (in 
    which case the specific terms and conditions of the permit which are 
    the subject of the request for review shall be stayed); or
        (iii) No comments requested a change in the draft permit, in which 
    case the permit shall become effective immediately upon issuance.
        (j) Response to comments. (1) At the time that any final permit 
    decision is issued, the permitting authority shall issue a response to 
    comments. This response shall:
        (i) Specify which provisions, if any, of the draft permit have been 
    changed in the final permit decision, and the reasons for the change; 
    and
        (ii) Briefly describe and respond to all significant comments on 
    the draft permit raised during the public comment period, or during any 
    hearing.
        (2) Any documents cited in the response to comments shall be 
    included in the administrative record for the final permit decision as 
    defined in paragraph (k) of this section. If new points are raised or 
    new material supplied during the public comment period, the permitting 
    authority may document its response to those matters by adding new 
    materials to the administrative record.
        (3) The response to comments shall be available to the public.
        (4) The permitting authority will notify in writing any affected 
    State of any refusal to accept recommendations for the permit that the 
    State submitted during the public or affected State review period.
        (k) Administrative record for final permits. (1) The permitting 
    authority shall base final permit decisions on the administrative 
    record defined in paragraph (k)(2) of this section.
        (2) The administrative record for any final permit shall consist 
    of:
        (i) All comments received during any public comment period, 
    including any extension or reopening;
        (ii) The tape or transcript of any hearing(s) held;
        (iii) Any written material submitted at such a hearing;
        (iv) The response to comments and any new materials placed in the 
    record;
        (v) Other documents contained in the supporting file for the 
    permit;
        (vi) The final permit;
        (vii) The application and any supporting data furnished by the 
    applicant;
        (viii) The draft permit or notice of intent to deny the application 
    or to terminate the permit;
        (ix) The statement of basis for the draft permit;
        (x) All documents cited in the statement of basis;
        (xi) Other documents contained in the supporting file for the draft 
    permit.
        (3) The additional documents required under paragraph (k)(2) of 
    this section should be added to the record as soon as possible after 
    their receipt or publication by the permitting authority. The record 
    shall be complete on the date the final permit is issued.
        (4) Material readily available at the permitting authority, or 
    published materials which are generally available and which are 
    included in the administrative record under the standards of paragraph 
    (j) of this section need not be physically included in the same file as 
    the rest of the record as long as it is specifically referred to in the 
    statement of basis or in the response to comments.
        (l) Appeal of permits. (1) Within 30 days after a final permit 
    decision has been issued, any person who filed comments on the draft 
    permit or participated in the public hearing may petition the 
    Environmental Appeals Board to review any condition of the permit 
    decision. Any person who failed to file comments or failed to 
    participate in the public hearing on the draft permit may petition for 
    administrative review only to the extent of the changes from the draft 
    to the final permit decision or other new grounds that were not 
    reasonably foreseeable during the public comment period on the draft 
    permit. The 30-day period within which a person may request review 
    under this section begins with the service of notice of the permitting 
    authority's action unless a later date is specified in that notice, 
    except that the 30-day period within which a person may request review 
    of a minor permit modification or administrative amendment begins upon 
    the effective date of such action to revise the permit. The petition 
    shall include a statement of the reasons supporting that review, 
    including a demonstration that any issues raised were raised during the 
    public comment period (including any public hearing) to the extent 
    required by these regulations unless the petitioner demonstrates that 
    it was impracticable to raise such objections within such period or 
    unless
    
    [[Page 34249]]
    
    the grounds for such objection arose after such period, and, when 
    appropriate, a showing that the condition in question is based on:
        (i) A finding of fact or conclusion of law which is clearly 
    erroneous; or
        (ii) An exercise of discretion or an important policy consideration 
    which the Environmental Appeals Board should, in its discretion, 
    review.
        (2) The Board may also decide on its initiative to review any 
    condition of any permit issued under this part. The Board must act 
    under paragraph (l) of this section within 30 days of the service date 
    of notice of the permitting authority's action.
        (3) Within a reasonable time following the filing of the petition 
    for review, the Board shall issue an order either granting or denying 
    the petition for review. To the extent review is denied, the conditions 
    of the final permit decision become final agency action. Public notice 
    of any grant of review by the Board under paragraph (l)(1) or (2) of 
    this section shall be given as provided in paragraph (d) of this 
    section. Public notice shall set forth a briefing schedule for the 
    appeal and shall state that any interested person may file an amicus 
    brief. Notice of denial of review shall be sent only to the permit 
    applicant and to the person(s) requesting review.
        (4) A petition to the Board under paragraph (l)(1) of this section 
    is, under 42 U.S.C. 307(b), a prerequisite to seeking judicial review 
    of the final agency action.
        (5) For purposes of judicial review, final agency action occurs 
    when a final permit is issued or denied by the permitting authority and 
    agency review procedures are exhausted. A final permit decision shall 
    be issued by the permitting authority:
        (i) When the Board issues notice to the parties that review has 
    been denied;
        (ii) When the Board issues a decision on the merits of the appeal 
    and the decision does not include a remand of the proceedings; or
        (iii) Upon the completion of remand proceedings if the proceedings 
    are remanded, unless the Board's remand order specifically provides 
    that appeal of the remand decision will be required to exhaust 
    administrative remedies.
        (6) Motions to reconsider a final order shall be filed within ten 
    (10) days after service of the final order. Every such motion must set 
    forth the matters claimed to have been erroneously decided and the 
    nature of the alleged errors. Motions for reconsideration under this 
    provision shall be directed to, and decided by, the Board. Motions for 
    reconsideration directed to the Administrator, rather than to the 
    Board, will not be considered, except in cases that the Board has 
    referred to the Administrator and in which the Administrator has issued 
    the final order. A motion for reconsideration shall not stay the 
    effective date of the final order unless specifically so ordered by the 
    Board.
        (m) Computation of time. (1) Any time period scheduled to begin on 
    the occurrence of an act or event shall begin on the day after the act 
    or event.
        (2) Any time period scheduled to begin before the occurrence of an 
    act or event shall be computed so that the period ends on the day 
    before the act or event, except as otherwise provided.
        (3) If the final day of any time period falls on a weekend or legal 
    holiday, the time period shall be extended to the next working day.
        (4) Whenever a party or interested person has the right or is 
    required to act within a prescribed period after the service of notice 
    or other paper upon him or her by mail, 3 days shall be added to the 
    prescribed time.
        (n) Public petitions to the Permitting Authority.
        (1) Any interested person (including the permittee) may petition 
    the permitting authority to reopen a permit for cause, and the 
    permitting authority may commence a permit reopening on its own 
    initiative. However, the permitting authority shall not revise, revoke 
    and reissue, or terminate a permit except for the reasons specified in 
    Sec. 71.7(f)(1) or Sec. 71.6(a)(6)(i). All requests shall be in writing 
    and shall contain facts or reasons supporting the request.
        (2) If the permitting authority decides the request is not 
    justified, it shall send the requester a brief written response giving 
    a reason for the decision. Denials of requests for revision, revocation 
    and reissuance, or termination are not subject to public notice, 
    comment, or hearings. Denials by the permitting authority may be 
    informally appealed to the Environmental Appeals Board by a letter 
    briefly setting forth the relevant facts. The Board may direct the 
    permitting authority to begin revision, revocation and reissuance, or 
    termination proceedings under paragraph (n)(3) of this section. The 
    appeal shall be considered denied if the Board takes no action within 
    60 days after receiving it. This informal appeal is, under 42 U.S.C. 
    307, a prerequisite to seeking judicial review of EPA action in denying 
    a request for revision, revocation and reissuance, or termination.
        (3) If the permitting authority decides the request is justified 
    and that cause exists to revise, revoke and reissue or terminate a 
    permit, it shall initiate proceedings to reopen the permit pursuant to 
    Sec. 71.7(f) or Sec. 71.7(g).
    
    
    Sec. 71.12  Prohibited acts.
    
        Violations of any applicable requirement; any permit term or 
    condition; any fee or filing requirement; any duty to allow or carry 
    out inspection, entry, or monitoring activities; or any regulation or 
    order issued by the permitting authority pursuant to this part are 
    violations of the Act and are subject to full Federal enforcement 
    authorities available under the Act.
    
    [FR Doc. 96-16257 Filed 6-28-96; 8:45 am]
    BILLING CODE 6560-50-P
    
    
    

Document Information

Effective Date:
7/31/1996
Published:
07/01/1996
Department:
Environmental Protection Agency
Entry Type:
Rule
Action:
Final rule.
Document Number:
96-16257
Dates:
July 31, 1996.
Pages:
34202-34249 (48 pages)
Docket Numbers:
FRL-5526-7
RINs:
2060-AD68: Federal Operating Permit Rules
RIN Links:
https://www.federalregister.gov/regulations/2060-AD68/federal-operating-permit-rules
PDF File:
96-16257.pdf
CFR: (29)
40 CFR 71.10)
40 CFR 71.6(a)(13)
40 CFR 71.5(a)(1)
40 CFR 71.8(b)
40 CFR 71.5(c)(11)
More ...